Bianca construction progress
Bianca in Wadi Al Safa 2 is 56% built at the Land Department inspection of June 2026. Developer Reportage Prime Properties. Completion registered for December 2026.
56%
Built, at the Land Department site inspection of 3 June 2026
Running behind its date
- Completion date (Land Department)
- December 2026
- Finish at recent pace
- January 2028
- Construction started
- September 2023
- Registered with the Land Department
- March 2023
- Developer
- Reportage Prime Properties
- Community
- Wadi Al Safa 2
- Units
- 653
- Escrow bank
- Al Masraf
- Name in Arabic
- بيانكا
- Land Department project number
- 2553
- Land Department site inspections
- 8
Schedule
Between June 2025 and June 2026 the site added about 2.2 points a month. At that rate it would finish around January 2028, more than three months after the December 2026 date registered with the Land Department.
Site inspections
3 June 2026
56%+8.2 pts
5 February 2026
48%+12 pts
21 October 2025
36%+5.4 pts
11 June 2025
30%+10 pts
12 March 2025
20%+9.4 pts
23 December 2024
10%+10 pts
9 May 2024
0.2%+0.2 pts
15 March 2023
0%
Context
Wadi Al Safa 2 has 2 projects under construction, 66% built on average.
Reportage Prime Properties has 9 projects under construction in Dubai; 3 have passed their registered completion date.
Own a unit in Bianca?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Bianca be completed?
- The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around January 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Bianca is built?
- 56%, measured at the Land Department site inspection on 3 June 2026. The Land Department engineers have inspected the site 8 times since March 2023.
- Is Bianca delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building Bianca?
- The registered developer is Reportage Prime Properties. It has 8 other projects under construction in Dubai.
- Which bank holds the escrow account for Bianca?
- Al Masraf. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Verdana (Phase 1)Also by Reportage Prime Properties. 95%, Due December 2025, passed.
- Verdana(Phase 2)Also by Reportage Prime Properties. 94%.
- Verdana ResidenceAlso by Reportage Prime Properties. 96%, Due December 2025, passed.
- Verdana 2Also by Reportage Prime Properties. 56%.
- Sobha ReserveNearby in Wadi Al Safa 2. 75%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)