Bianca construction progress

Bianca in Wadi Al Safa 2 is 56% built at the Land Department inspection of June 2026. Developer Reportage Prime Properties. Completion registered for December 2026.

56%

Built, at the Land Department site inspection of 3 June 2026

Running behind its date

Completion date (Land Department)
December 2026
Finish at recent pace
January 2028
Construction started
September 2023
Registered with the Land Department
March 2023
Community
Wadi Al Safa 2
Units
653
Escrow bank
Al Masraf
Name in Arabic
بيانكا
Land Department project number
2553
Land Department site inspections
8

Schedule

Between June 2025 and June 2026 the site added about 2.2 points a month. At that rate it would finish around January 2028, more than three months after the December 2026 date registered with the Land Department.

0%25%50%75%100%202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

3 June 2026

56%+8.2 pts

  • Bianca construction site, Land Department inspection photo 1, 3 June 2026
  • Bianca construction site, Land Department inspection photo 2, 3 June 2026
  • Bianca construction site, Land Department inspection photo 3, 3 June 2026
  • Bianca construction site, Land Department inspection photo 4, 3 June 2026

5 February 2026

48%+12 pts

  • Bianca construction site, Land Department inspection photo 1, 5 February 2026
  • Bianca construction site, Land Department inspection photo 2, 5 February 2026
  • Bianca construction site, Land Department inspection photo 3, 5 February 2026
  • Bianca construction site, Land Department inspection photo 4, 5 February 2026

21 October 2025

36%+5.4 pts

  • Bianca construction site, Land Department inspection photo 1, 21 October 2025
  • Bianca construction site, Land Department inspection photo 2, 21 October 2025
  • Bianca construction site, Land Department inspection photo 3, 21 October 2025
  • Bianca construction site, Land Department inspection photo 4, 21 October 2025

11 June 2025

30%+10 pts

  • Bianca construction site, Land Department inspection photo 1, 11 June 2025
  • Bianca construction site, Land Department inspection photo 2, 11 June 2025
  • Bianca construction site, Land Department inspection photo 3, 11 June 2025
  • Bianca construction site, Land Department inspection photo 4, 11 June 2025

12 March 2025

20%+9.4 pts

  • Bianca construction site, Land Department inspection photo 1, 12 March 2025
  • Bianca construction site, Land Department inspection photo 2, 12 March 2025
  • Bianca construction site, Land Department inspection photo 3, 12 March 2025
  • Bianca construction site, Land Department inspection photo 4, 12 March 2025

23 December 2024

10%+10 pts

  • Bianca construction site, Land Department inspection photo 1, 23 December 2024
  • Bianca construction site, Land Department inspection photo 2, 23 December 2024
  • Bianca construction site, Land Department inspection photo 3, 23 December 2024
  • Bianca construction site, Land Department inspection photo 4, 23 December 2024

9 May 2024

0.2%+0.2 pts

  • Bianca construction site, Land Department inspection photo 1, 9 May 2024
  • Bianca construction site, Land Department inspection photo 2, 9 May 2024
  • Bianca construction site, Land Department inspection photo 3, 9 May 2024

15 March 2023

0%

  • Bianca construction site, Land Department inspection photo 1, 15 March 2023

All 68 site photos, by inspection date

Context

Wadi Al Safa 2 has 2 projects under construction, 66% built on average.

Reportage Prime Properties has 9 projects under construction in Dubai; 3 have passed their registered completion date.

Own a unit in Bianca?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Bianca be completed?
The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around January 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Bianca is built?
56%, measured at the Land Department site inspection on 3 June 2026. The Land Department engineers have inspected the site 8 times since March 2023.
Is Bianca delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Bianca?
The registered developer is Reportage Prime Properties. It has 8 other projects under construction in Dubai.
Which bank holds the escrow account for Bianca?
Al Masraf. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.