Bianca construction progress
The registered completion date for Bianca in Wadi Al Safa 2 is December 2026. At the last site inspection, in June 2026, it was 56% built. The developer is Reportage Prime Properties.
56%
Built, at the site inspection of 3 June 2026
Running behind its date
- Registered completion date
- December 2026
- Finish at recent pace
- January 2028
- Construction started
- September 2023
- First registered
- March 2023
- Developer
- Reportage Prime Properties
- Community
- Wadi Al Safa 2
- Units
- 653
- Escrow bank
- Al Masraf
- Name in Arabic
- بيانكا
- Project number
- 2553
- Site inspections
- 8
Schedule
Between June 2025 and June 2026 the site added about 2.2 points a month. At that rate it would finish around January 2028, more than three months after its registered date of December 2026.
Site inspections
3 June 2026
56%+8.2 pts
5 February 2026
48%+12 pts
21 October 2025
36%+5.4 pts
11 June 2025
30%+10 pts
12 March 2025
20%+9.4 pts
23 December 2024
10%+10 pts
9 May 2024
0.2%+0.2 pts
15 March 2023
0%
Context
Wadi Al Safa 2 has 2 projects under construction, 68% built on average.
Reportage Prime Properties has 9 projects under construction in Dubai; 4 have passed their registered completion date.
Own a unit in Bianca?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Bianca handover date?
- The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Bianca?
- Bianca was 56% built at the site inspection on 3 June 2026. The site has been inspected 8 times since March 2023. The Land Department took 68 site photos at its inspections.
- Is Bianca delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building Bianca?
- The registered developer is Reportage Prime Properties. It has 8 other projects under construction in Dubai.
- Which bank holds the escrow account for Bianca?
- Al Masraf. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Verdana (Phase 1)Also by Reportage Prime Properties. 95%, Due December 2025, passed.
- Verdana(Phase 2)Also by Reportage Prime Properties. 94%, Due December 2025, passed.
- Verdana ResidenceAlso by Reportage Prime Properties. 96%, Due December 2025, passed.
- Verdana 2Also by Reportage Prime Properties. 56%.
- Sobha ReserveNearby in Wadi Al Safa 2. 80%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)