Verdes By Haven 1 construction progress

Verdes By Haven 1 in Wadi Al Safa 5 is 13% built at the Land Department inspection of July 2026. Developer Aurora Spv 1. Completion registered for May 2028.

13%

Built, at the Land Department site inspection of 23 July 2026

Running behind its date

Completion date (Land Department)
May 2028
Finish at recent pace
November 2032
Construction started
February 2025
Registered with the Land Department
September 2024
Developer
Aurora Spv 1
Units
988
Escrow bank
First Abu Dhabi Bank
Name in Arabic
فيرديس من جنان 1
Land Department project number
3188
Land Department site inspections
6

Schedule

Between August 2025 and July 2026 the site added about 1.1 points a month. At that rate it would finish around November 2032, more than three months after the May 2028 date registered with the Land Department.

0%25%50%75%100%2025202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

23 July 2026

13%+4.0 pts

  • Verdes By Haven 1 construction site, Land Department inspection photo 1, 23 July 2026
  • Verdes By Haven 1 construction site, Land Department inspection photo 2, 23 July 2026
  • Verdes By Haven 1 construction site, Land Department inspection photo 3, 23 July 2026
  • Verdes By Haven 1 construction site, Land Department inspection photo 4, 23 July 2026

13 April 2026

9.4%+7.4 pts

  • Verdes By Haven 1 construction site, Land Department inspection photo 1, 13 April 2026
  • Verdes By Haven 1 construction site, Land Department inspection photo 2, 13 April 2026
  • Verdes By Haven 1 construction site, Land Department inspection photo 3, 13 April 2026
  • Verdes By Haven 1 construction site, Land Department inspection photo 4, 13 April 2026

11 December 2025

2.0%+1.2 pts

  • Verdes By Haven 1 construction site, Land Department inspection photo 1, 11 December 2025
  • Verdes By Haven 1 construction site, Land Department inspection photo 2, 11 December 2025
  • Verdes By Haven 1 construction site, Land Department inspection photo 3, 11 December 2025
  • Verdes By Haven 1 construction site, Land Department inspection photo 4, 11 December 2025

22 August 2025

0.9%+0.8 pts

  • Verdes By Haven 1 construction site, Land Department inspection photo 1, 22 August 2025
  • Verdes By Haven 1 construction site, Land Department inspection photo 2, 22 August 2025
  • Verdes By Haven 1 construction site, Land Department inspection photo 3, 22 August 2025
  • Verdes By Haven 1 construction site, Land Department inspection photo 4, 22 August 2025

10 January 2025

0.1%+0.1 pts

  • Verdes By Haven 1 construction site, Land Department inspection photo 1, 10 January 2025
  • Verdes By Haven 1 construction site, Land Department inspection photo 2, 10 January 2025

27 August 2024

0%

  • Verdes By Haven 1 construction site, Land Department inspection photo 1, 27 August 2024
  • Verdes By Haven 1 construction site, Land Department inspection photo 2, 27 August 2024

All 26 site photos, by inspection date

Context

Wadi Al Safa 5 has 13 projects under construction, 17% built on average.

Aurora Spv 1 has 5 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Verdes By Haven 1?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Verdes By Haven 1 be completed?
The completion date registered with the Dubai Land Department is May 2028. At the pace of its recent inspections the site would reach 100% around November 2032. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Verdes By Haven 1 is built?
13%, measured at the Land Department site inspection on 23 July 2026. The Land Department engineers have inspected the site 6 times since August 2024.
Is Verdes By Haven 1 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2028.
Who is building Verdes By Haven 1?
The registered developer is Aurora Spv 1. It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for Verdes By Haven 1?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.