Haven By Aldar 3 construction progress
The registered completion date for Haven By Aldar 3 in Wadi Al Safa 5 is March 2028. At the last site inspection, in October 2026, it was 69% built. The developer is Aurora Spv 1.
69%
Built, at the site inspection of 21 October 2026
On pace for its date
- Registered completion date
- March 2028
- Finish at recent pace
- April 2027
- Construction started
- April 2024
- First registered
- January 2024
- Developer
- Aurora Spv 1
- Community
- Wadi Al Safa 5
- Units
- 292
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- جنان من الدار 3
- Project number
- 2875
- Site inspections
- 7
Schedule
Since December 2025 Haven By Aldar 3 has added about 5.6 points a month. That puts 100% around April 2027, within three months of its registered completion date of March 2028.
Site inspections
21 October 2026
69%+11 pts
28 July 2026
58%+18 pts
13 April 2026
40%+28 pts
12 December 2025
12%+9.0 pts
26 June 2025
2.7%+2.2 pts
10 January 2025
0.5%+0.5 pts
12 December 2023
0%
Context
Wadi Al Safa 5 has 13 projects under construction, 24% built on average.
Aurora Spv 1 has 5 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Haven By Aldar 3?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Haven By Aldar 3 handover date?
- The registered completion date is March 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Haven By Aldar 3?
- Haven By Aldar 3 was 69% built at the site inspection on 21 October 2026. The site has been inspected 7 times since December 2023. The Land Department took 51 site photos at its inspections.
- Is Haven By Aldar 3 delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of March 2028.
- Who is building Haven By Aldar 3?
- The registered developer is Aurora Spv 1. It has 4 other projects under construction in Dubai.
- Which bank holds the escrow account for Haven By Aldar 3?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Haven By Aldar 1Also by Aurora Spv 1. 61%, Due November 2027.
- Haven By Aldar 2Also by Aurora Spv 1. 53%.
- Verdes By Haven 1Also by Aurora Spv 1. 18%, Due May 2028.
- Verdes By Haven 2Also by Aurora Spv 1. 27%, Due June 2028.
- Athlon By Al Dar 1Nearby in Wadi Al Safa 5. 27%, Due May 2028.
- Athlon By Al Dar 2Nearby in Wadi Al Safa 5. 20%, Due September 2028.
- La Tilia At Villanova Phase 1Nearby in Wadi Al Safa 5. 14%, Due August 2028.
- La Tilia At Villanova Phase 2Nearby in Wadi Al Safa 5. 11%, Due August 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.










.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)



.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)