Skip to content

Haven By Aldar 3 construction progress

The registered completion date for Haven By Aldar 3 in Wadi Al Safa 5 is March 2028. At the last site inspection, in October 2026, it was 69% built. The developer is Aurora Spv 1.

69%

Built, at the site inspection of 21 October 2026

On pace for its date

Registered completion date
March 2028
Finish at recent pace
April 2027
Construction started
April 2024
First registered
January 2024
Developer
Aurora Spv 1
Units
292
Escrow bank
First Abu Dhabi Bank
Name in Arabic
جنان من الدار 3
Project number
2875
Site inspections
7

Schedule

Since December 2025 Haven By Aldar 3 has added about 5.6 points a month. That puts 100% around April 2027, within three months of its registered completion date of March 2028.

0%25%50%75%100%20242025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

21 October 2026

69%+11 pts

  • Haven By Aldar 3 construction site, inspection photo 1, 21 October 2026
  • Haven By Aldar 3 construction site, inspection photo 2, 21 October 2026
  • Haven By Aldar 3 construction site, inspection photo 3, 21 October 2026
  • Haven By Aldar 3 construction site, inspection photo 4, 21 October 2026

28 July 2026

58%+18 pts

  • Haven By Aldar 3 construction site, inspection photo 1, 28 July 2026
  • Haven By Aldar 3 construction site, inspection photo 2, 28 July 2026
  • Haven By Aldar 3 construction site, inspection photo 3, 28 July 2026
  • Haven By Aldar 3 construction site, inspection photo 4, 28 July 2026

13 April 2026

40%+28 pts

  • Haven By Aldar 3 construction site, inspection photo 1, 13 April 2026
  • Haven By Aldar 3 construction site, inspection photo 2, 13 April 2026
  • Haven By Aldar 3 construction site, inspection photo 3, 13 April 2026
  • Haven By Aldar 3 construction site, inspection photo 4, 13 April 2026

12 December 2025

12%+9.0 pts

  • Haven By Aldar 3 construction site, inspection photo 1, 12 December 2025
  • Haven By Aldar 3 construction site, inspection photo 2, 12 December 2025
  • Haven By Aldar 3 construction site, inspection photo 3, 12 December 2025
  • Haven By Aldar 3 construction site, inspection photo 4, 12 December 2025

26 June 2025

2.7%+2.2 pts

  • Haven By Aldar 3 construction site, inspection photo 1, 26 June 2025
  • Haven By Aldar 3 construction site, inspection photo 2, 26 June 2025
  • Haven By Aldar 3 construction site, inspection photo 3, 26 June 2025
  • Haven By Aldar 3 construction site, inspection photo 4, 26 June 2025

10 January 2025

0.5%+0.5 pts

  • Haven By Aldar 3 construction site, inspection photo 1, 10 January 2025
  • Haven By Aldar 3 construction site, inspection photo 2, 10 January 2025
  • Haven By Aldar 3 construction site, inspection photo 3, 10 January 2025

12 December 2023

0%

  • Haven By Aldar 3 construction site, inspection photo 1, 12 December 2023
  • Haven By Aldar 3 construction site, inspection photo 2, 12 December 2023
  • Haven By Aldar 3 construction site, inspection photo 3, 12 December 2023

All 51 site photos, by inspection date

Context

Wadi Al Safa 5 has 13 projects under construction, 24% built on average.

Aurora Spv 1 has 5 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Haven By Aldar 3?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Haven By Aldar 3 handover date?
The registered completion date is March 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Haven By Aldar 3?
Haven By Aldar 3 was 69% built at the site inspection on 21 October 2026. The site has been inspected 7 times since December 2023. The Land Department took 51 site photos at its inspections.
Is Haven By Aldar 3 delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of March 2028.
Who is building Haven By Aldar 3?
The registered developer is Aurora Spv 1. It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for Haven By Aldar 3?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.