Verdes By Haven 2 construction progress

The registered completion date for Verdes By Haven 2 in Wadi Al Safa 5 is June 2028. At the last site inspection, in October 2026, it was 27% built. The developer is Aurora Spv 1.

27%

Built, at the site inspection of 21 October 2026

Running behind its date

Registered completion date
June 2028
Finish at recent pace
April 2029
Construction started
January 2026
First registered
September 2024
Developer
Aurora Spv 1
Units
59
Escrow bank
First Abu Dhabi Bank
Name in Arabic
فيرديس من جنان 2
Project number
3189
Site inspections
6

Schedule

Between December 2025 and October 2026 the site added about 2.4 points a month. At that rate it would finish around April 2029, more than three months after its registered date of June 2028.

0%25%50%75%100%2025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

21 October 2026

27%+12 pts

  • Verdes By Haven 2 construction site, inspection photo 1, 21 October 2026
  • Verdes By Haven 2 construction site, inspection photo 2, 21 October 2026
  • Verdes By Haven 2 construction site, inspection photo 3, 21 October 2026
  • Verdes By Haven 2 construction site, inspection photo 4, 21 October 2026

23 July 2026

15%+8.6 pts

  • Verdes By Haven 2 construction site, inspection photo 1, 23 July 2026
  • Verdes By Haven 2 construction site, inspection photo 2, 23 July 2026
  • Verdes By Haven 2 construction site, inspection photo 3, 23 July 2026
  • Verdes By Haven 2 construction site, inspection photo 4, 23 July 2026

13 April 2026

6.7%+4.1 pts

  • Verdes By Haven 2 construction site, inspection photo 1, 13 April 2026
  • Verdes By Haven 2 construction site, inspection photo 2, 13 April 2026

11 December 2025

2.5%+0.8 pts

  • Verdes By Haven 2 construction site, inspection photo 1, 11 December 2025
  • Verdes By Haven 2 construction site, inspection photo 2, 11 December 2025
  • Verdes By Haven 2 construction site, inspection photo 3, 11 December 2025
  • Verdes By Haven 2 construction site, inspection photo 4, 11 December 2025

22 August 2025

1.7%+1.7 pts

  • Verdes By Haven 2 construction site, inspection photo 1, 22 August 2025
  • Verdes By Haven 2 construction site, inspection photo 2, 22 August 2025
  • Verdes By Haven 2 construction site, inspection photo 3, 22 August 2025
  • Verdes By Haven 2 construction site, inspection photo 4, 22 August 2025

27 August 2024

0%

  • Verdes By Haven 2 construction site, inspection photo 1, 27 August 2024
  • Verdes By Haven 2 construction site, inspection photo 2, 27 August 2024

All 22 site photos, by inspection date

Context

Wadi Al Safa 5 has 13 projects under construction, 24% built on average.

Aurora Spv 1 has 5 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Verdes By Haven 2?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Verdes By Haven 2 handover date?
The registered completion date is June 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Verdes By Haven 2?
Verdes By Haven 2 was 27% built at the site inspection on 21 October 2026. The site has been inspected 6 times since August 2024. The Land Department took 22 site photos at its inspections.
Is Verdes By Haven 2 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
Who is building Verdes By Haven 2?
The registered developer is Aurora Spv 1. It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for Verdes By Haven 2?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.