Athlon By Al Dar 1 construction progress

Athlon By Al Dar 1 in Wadi Al Safa 5 is 18% built at the Land Department inspection of July 2026. Developer Aurora Spv 3. Completion registered for May 2028.

18%

Built, at the Land Department site inspection of 23 July 2026

Running behind its date

Completion date (Land Department)
May 2028
Finish at recent pace
August 2031
Construction started
July 2024
Registered with the Land Department
July 2024
Developer
Aurora Spv 3
Units
893
Escrow bank
First Abu Dhabi Bank
Name in Arabic
أثلون من الدار 1
Land Department project number
3143
Land Department site inspections
6

Schedule

Between December 2025 and July 2026 the site added about 1.3 points a month. At that rate it would finish around August 2031, more than three months after the May 2028 date registered with the Land Department.

0%25%50%75%100%2025202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

23 July 2026

18%+5.1 pts

  • Athlon By Al Dar 1 construction site, Land Department inspection photo 1, 23 July 2026
  • Athlon By Al Dar 1 construction site, Land Department inspection photo 2, 23 July 2026
  • Athlon By Al Dar 1 construction site, Land Department inspection photo 3, 23 July 2026
  • Athlon By Al Dar 1 construction site, Land Department inspection photo 4, 23 July 2026

13 April 2026

13%+4.8 pts

  • Athlon By Al Dar 1 construction site, Land Department inspection photo 1, 13 April 2026
  • Athlon By Al Dar 1 construction site, Land Department inspection photo 2, 13 April 2026
  • Athlon By Al Dar 1 construction site, Land Department inspection photo 3, 13 April 2026
  • Athlon By Al Dar 1 construction site, Land Department inspection photo 4, 13 April 2026

11 December 2025

8.3%+6.8 pts

  • Athlon By Al Dar 1 construction site, Land Department inspection photo 1, 11 December 2025
  • Athlon By Al Dar 1 construction site, Land Department inspection photo 2, 11 December 2025
  • Athlon By Al Dar 1 construction site, Land Department inspection photo 3, 11 December 2025
  • Athlon By Al Dar 1 construction site, Land Department inspection photo 4, 11 December 2025

26 June 2025

1.5%+1.2 pts

  • Athlon By Al Dar 1 construction site, Land Department inspection photo 1, 26 June 2025
  • Athlon By Al Dar 1 construction site, Land Department inspection photo 2, 26 June 2025
  • Athlon By Al Dar 1 construction site, Land Department inspection photo 3, 26 June 2025
  • Athlon By Al Dar 1 construction site, Land Department inspection photo 4, 26 June 2025

10 January 2025

0.3%+0.3 pts

  • Athlon By Al Dar 1 construction site, Land Department inspection photo 1, 10 January 2025
  • Athlon By Al Dar 1 construction site, Land Department inspection photo 2, 10 January 2025
  • Athlon By Al Dar 1 construction site, Land Department inspection photo 3, 10 January 2025

19 June 2024

0%

  • Athlon By Al Dar 1 construction site, Land Department inspection photo 1, 19 June 2024
  • Athlon By Al Dar 1 construction site, Land Department inspection photo 2, 19 June 2024

All 34 site photos, by inspection date

Context

Wadi Al Safa 5 has 13 projects under construction, 17% built on average. Athlon By Al Dar 1 is ahead of that average.

Aurora Spv 3 has 6 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Athlon By Al Dar 1?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Athlon By Al Dar 1 be completed?
The completion date registered with the Dubai Land Department is May 2028. At the pace of its recent inspections the site would reach 100% around August 2031. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Athlon By Al Dar 1 is built?
18%, measured at the Land Department site inspection on 23 July 2026. The Land Department engineers have inspected the site 6 times since June 2024.
Is Athlon By Al Dar 1 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2028.
Who is building Athlon By Al Dar 1?
The registered developer is Aurora Spv 3. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Athlon By Al Dar 1?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.