Verdes By Haven 1 construction photos

36 photos from 7 site inspections, newest first. The percentage is how much of Verdes By Haven 1 was built on the day of each visit.

21 October 202618% built

23 July 202613% built

13 April 20269.4% built

11 December 20252.0% built

22 August 20250.9% built

10 January 20250.1% built

27 August 20240% built

Back to Verdes By Haven 1 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.