La Tilia At Villanova Phase 2 construction progress

La Tilia At Villanova Phase 2 in Wadi Al Safa 5 is 5.3% built at the Land Department inspection of June 2026. Developer North Dubailand Projects. Completion registered for August 2028.

11%

Built, at the Land Department site inspection of 29 June 2026

Running behind its date

Completion date (Land Department)
August 2028
Finish at recent pace
September 2042
Construction started
January 2025
Registered with the Land Department
December 2024
Developer
North Dubailand Projects
Units
440
Escrow bank
First Abu Dhabi Bank
Name in Arabic
لا تيليا في فيلانوفا المرحلة 2
Land Department project number
3456
Land Department site inspections
6

Schedule

Between September 2025 and June 2026 the site added about 0.5 points a month. At that rate it would finish around September 2042, more than three months after the August 2028 date registered with the Land Department.

0%25%50%75%100%2025202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

29 June 2026

5.3%+3.9 pts

  • La Tilia At Villanova Phase 2 construction site, Land Department inspection photo 1, 29 June 2026
  • La Tilia At Villanova Phase 2 construction site, Land Department inspection photo 2, 29 June 2026
  • La Tilia At Villanova Phase 2 construction site, Land Department inspection photo 3, 29 June 2026
  • La Tilia At Villanova Phase 2 construction site, Land Department inspection photo 4, 29 June 2026

24 March 2026

1.5%+0.4 pts

  • La Tilia At Villanova Phase 2 construction site, Land Department inspection photo 1, 24 March 2026
  • La Tilia At Villanova Phase 2 construction site, Land Department inspection photo 2, 24 March 2026
  • La Tilia At Villanova Phase 2 construction site, Land Department inspection photo 3, 24 March 2026
  • La Tilia At Villanova Phase 2 construction site, Land Department inspection photo 4, 24 March 2026

22 December 2025

1.1%+0.4 pts

  • La Tilia At Villanova Phase 2 construction site, Land Department inspection photo 1, 22 December 2025
  • La Tilia At Villanova Phase 2 construction site, Land Department inspection photo 2, 22 December 2025
  • La Tilia At Villanova Phase 2 construction site, Land Department inspection photo 3, 22 December 2025

8 September 2025

0.6%+0.5 pts

  • La Tilia At Villanova Phase 2 construction site, Land Department inspection photo 1, 8 September 2025
  • La Tilia At Villanova Phase 2 construction site, Land Department inspection photo 2, 8 September 2025
  • La Tilia At Villanova Phase 2 construction site, Land Department inspection photo 3, 8 September 2025

26 June 2025

0.1%+0.1 pts

  • La Tilia At Villanova Phase 2 construction site, Land Department inspection photo 1, 26 June 2025
  • La Tilia At Villanova Phase 2 construction site, Land Department inspection photo 2, 26 June 2025
  • La Tilia At Villanova Phase 2 construction site, Land Department inspection photo 3, 26 June 2025
  • La Tilia At Villanova Phase 2 construction site, Land Department inspection photo 4, 26 June 2025

18 December 2024

0%

  • La Tilia At Villanova Phase 2 construction site, Land Department inspection photo 1, 18 December 2024
  • La Tilia At Villanova Phase 2 construction site, Land Department inspection photo 2, 18 December 2024

All 21 site photos, by inspection date

Context

Wadi Al Safa 5 has 13 projects under construction, 17% built on average.

North Dubailand Projects has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in La Tilia At Villanova Phase 2?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will La Tilia At Villanova Phase 2 be completed?
The completion date registered with the Dubai Land Department is August 2028. At the pace of its recent inspections the site would reach 100% around September 2042. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of La Tilia At Villanova Phase 2 is built?
11%, measured at the Land Department site inspection on 29 June 2026. The Land Department engineers have inspected the site 6 times since December 2024.
Is La Tilia At Villanova Phase 2 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2028.
Who is building La Tilia At Villanova Phase 2?
The registered developer is North Dubailand Projects. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for La Tilia At Villanova Phase 2?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.