La Tilia At Villanova Phase 2 construction progress
The registered completion date for La Tilia At Villanova Phase 2 in Wadi Al Safa 5 is August 2028. At the last site inspection, in October 2026, it was 11% built. The developer is North Dubailand Projects.
11%
Built, at the site inspection of 5 October 2026
Running behind its date
- Registered completion date
- August 2028
- Finish at recent pace
- February 2034
- Construction started
- January 2025
- First registered
- December 2024
- Developer
- North Dubailand Projects
- Community
- Wadi Al Safa 5
- Units
- 440
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- لا تيليا في فيلانوفا المرحلة 2
- Project number
- 3456
- Site inspections
- 7
Schedule
Between December 2025 and October 2026 the site added about 1.0 points a month. At that rate it would finish around February 2034, more than three months after its registered date of August 2028.
Site inspections
5 October 2026
11%+5.2 pts
29 June 2026
5.3%+3.9 pts
24 March 2026
1.5%+0.4 pts
22 December 2025
1.1%+0.4 pts
8 September 2025
0.6%+0.5 pts
26 June 2025
0.1%+0.1 pts
18 December 2024
0%
Context
Wadi Al Safa 5 has 13 projects under construction, 24% built on average.
North Dubailand Projects has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in La Tilia At Villanova Phase 2?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the La Tilia At Villanova Phase 2 handover date?
- The registered completion date is August 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2034. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on La Tilia At Villanova Phase 2?
- La Tilia At Villanova Phase 2 was 11% built at the site inspection on 5 October 2026. The site has been inspected 7 times since December 2024. The Land Department took 29 site photos at its inspections.
- Is La Tilia At Villanova Phase 2 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2028.
- Who is building La Tilia At Villanova Phase 2?
- The registered developer is North Dubailand Projects. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for La Tilia At Villanova Phase 2?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- La Tilia At Villanova Phase 1Also by North Dubailand Projects. 14%, Due August 2028.
- Haven By Aldar 1Nearby in Wadi Al Safa 5. 61%, Due November 2027.
- Haven By Aldar 2Nearby in Wadi Al Safa 5. 53%.
- Haven By Aldar 3Nearby in Wadi Al Safa 5. 69%, Due March 2028.
- Athlon By Al Dar 1Nearby in Wadi Al Safa 5. 27%, Due May 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)