Athlon By Al Dar 2 construction progress
The registered completion date for Athlon By Al Dar 2 in Wadi Al Safa 5 is September 2028. At the last site inspection, in October 2026, it was 20% built. The developer is Aurora Spv 3.
20%
Built, at the site inspection of 22 October 2026
Running behind its date
- Registered completion date
- September 2028
- Finish at recent pace
- January 2031
- Construction started
- July 2024
- First registered
- July 2024
- Developer
- Aurora Spv 3
- Community
- Wadi Al Safa 5
- Units
- 599
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- أثلون من الدار 2
- Project number
- 3145
- Site inspections
- 7
Schedule
Between December 2025 and October 2026 the site added about 1.6 points a month. At that rate it would finish around January 2031, more than three months after its registered date of September 2028.
Site inspections
22 October 2026
20%+8.1 pts
23 July 2026
12%+3.9 pts
13 April 2026
8.4%+4.2 pts
11 December 2025
4.2%+3.3 pts
26 June 2025
0.9%+0.6 pts
10 January 2025
0.3%+0.3 pts
19 June 2024
0%
Context
Wadi Al Safa 5 has 13 projects under construction, 24% built on average.
Aurora Spv 3 has 6 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Athlon By Al Dar 2?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Athlon By Al Dar 2 handover date?
- The registered completion date is September 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2031. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Athlon By Al Dar 2?
- Athlon By Al Dar 2 was 20% built at the site inspection on 22 October 2026. The site has been inspected 7 times since June 2024. The Land Department took 39 site photos at its inspections.
- Is Athlon By Al Dar 2 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2028.
- Who is building Athlon By Al Dar 2?
- The registered developer is Aurora Spv 3. It has 5 other projects under construction in Dubai.
- Which bank holds the escrow account for Athlon By Al Dar 2?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Athlon By Al Dar 1Also by Aurora Spv 3. 27%, Due May 2028.
- Rise By Athlon 1Also by Aurora Spv 3. 3.7%, Due December 2029.
- Rise By Athlon 2Also by Aurora Spv 3. 3.7%, Due January 2030.
- Rise By Athlon 3Also by Aurora Spv 3. 0.5%, Due January 2030.
- Haven By Aldar 1Nearby in Wadi Al Safa 5. 61%, Due November 2027.
- Haven By Aldar 2Nearby in Wadi Al Safa 5. 53%.
- Haven By Aldar 3Nearby in Wadi Al Safa 5. 69%, Due March 2028.
- Verdes By Haven 1Nearby in Wadi Al Safa 5. 18%, Due May 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.