Athlon By Al Dar 2 construction progress

The registered completion date for Athlon By Al Dar 2 in Wadi Al Safa 5 is September 2028. At the last site inspection, in October 2026, it was 20% built. The developer is Aurora Spv 3.

20%

Built, at the site inspection of 22 October 2026

Running behind its date

Registered completion date
September 2028
Finish at recent pace
January 2031
Construction started
July 2024
First registered
July 2024
Developer
Aurora Spv 3
Units
599
Escrow bank
First Abu Dhabi Bank
Name in Arabic
أثلون من الدار 2
Project number
3145
Site inspections
7

Schedule

Between December 2025 and October 2026 the site added about 1.6 points a month. At that rate it would finish around January 2031, more than three months after its registered date of September 2028.

0%25%50%75%100%2025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

22 October 2026

20%+8.1 pts

  • Athlon By Al Dar 2 construction site, inspection photo 1, 22 October 2026
  • Athlon By Al Dar 2 construction site, inspection photo 2, 22 October 2026
  • Athlon By Al Dar 2 construction site, inspection photo 3, 22 October 2026
  • Athlon By Al Dar 2 construction site, inspection photo 4, 22 October 2026

23 July 2026

12%+3.9 pts

  • Athlon By Al Dar 2 construction site, inspection photo 1, 23 July 2026
  • Athlon By Al Dar 2 construction site, inspection photo 2, 23 July 2026
  • Athlon By Al Dar 2 construction site, inspection photo 3, 23 July 2026
  • Athlon By Al Dar 2 construction site, inspection photo 4, 23 July 2026

13 April 2026

8.4%+4.2 pts

  • Athlon By Al Dar 2 construction site, inspection photo 1, 13 April 2026
  • Athlon By Al Dar 2 construction site, inspection photo 2, 13 April 2026
  • Athlon By Al Dar 2 construction site, inspection photo 3, 13 April 2026
  • Athlon By Al Dar 2 construction site, inspection photo 4, 13 April 2026

11 December 2025

4.2%+3.3 pts

  • Athlon By Al Dar 2 construction site, inspection photo 1, 11 December 2025
  • Athlon By Al Dar 2 construction site, inspection photo 2, 11 December 2025
  • Athlon By Al Dar 2 construction site, inspection photo 3, 11 December 2025
  • Athlon By Al Dar 2 construction site, inspection photo 4, 11 December 2025

26 June 2025

0.9%+0.6 pts

  • Athlon By Al Dar 2 construction site, inspection photo 1, 26 June 2025
  • Athlon By Al Dar 2 construction site, inspection photo 2, 26 June 2025
  • Athlon By Al Dar 2 construction site, inspection photo 3, 26 June 2025
  • Athlon By Al Dar 2 construction site, inspection photo 4, 26 June 2025

10 January 2025

0.3%+0.3 pts

  • Athlon By Al Dar 2 construction site, inspection photo 1, 10 January 2025
  • Athlon By Al Dar 2 construction site, inspection photo 2, 10 January 2025
  • Athlon By Al Dar 2 construction site, inspection photo 3, 10 January 2025

19 June 2024

0%

  • Athlon By Al Dar 2 construction site, inspection photo 1, 19 June 2024

All 39 site photos, by inspection date

Context

Wadi Al Safa 5 has 13 projects under construction, 24% built on average.

Aurora Spv 3 has 6 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Athlon By Al Dar 2?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Athlon By Al Dar 2 handover date?
The registered completion date is September 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2031. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Athlon By Al Dar 2?
Athlon By Al Dar 2 was 20% built at the site inspection on 22 October 2026. The site has been inspected 7 times since June 2024. The Land Department took 39 site photos at its inspections.
Is Athlon By Al Dar 2 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2028.
Who is building Athlon By Al Dar 2?
The registered developer is Aurora Spv 3. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Athlon By Al Dar 2?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.