Off-plan projects in Wadi Al Safa 5
13 projects in Wadi Al Safa 5 are under construction. On average they are 24% built. The next one due is Haven By Aldar 1, in November 2027.
- Haven By Aldar 3Aurora Spv 169%Due March 2028
- Haven By Aldar 1Aurora Spv 161%Due November 2027
- Haven By Aldar 2Aurora Spv 153%No date set
- Verdes By Haven 2Aurora Spv 127%Due June 2028
- Athlon By Al Dar 1Aurora Spv 327%Due May 2028
- Athlon By Al Dar 2Aurora Spv 320%Due September 2028
- Verdes By Haven 1Aurora Spv 118%Due May 2028
- La Tilia At Villanova Phase 1North Dubailand Projects14%Due August 2028
- La Tilia At Villanova Phase 2North Dubailand Projects11%Due August 2028
- Rise By Athlon 2Aurora Spv 33.7%Due January 2030
- Rise By Athlon 1Aurora Spv 33.7%Due December 2029
- Rise By Athlon 4Aurora Spv 30.6%Due December 2029
- Rise By Athlon 3Aurora Spv 30.5%Due January 2030
Questions
How many off-plan projects are under construction in Wadi Al Safa 5?
13 projects are under construction in Wadi Al Safa 5, 24% built on average at the latest site inspections.
Which Wadi Al Safa 5 projects are due to finish next?
By registered completion date: Haven By Aldar 1 (November 2027, 61% built), Haven By Aldar 3 (March 2028, 69% built) and Athlon By Al Dar 1 (May 2028, 27% built). RERA asks developers to update these dates as projects move, so check the register before relying on one.
How many Wadi Al Safa 5 projects are past their completion date?
None. Every project here with a registered completion date is still inside it.
Which developers are building in Wadi Al Safa 5?
The developers with the most projects here are Aurora Spv 3 (6), Aurora Spv 1 (5) and North Dubailand Projects (2), out of 3 building in Wadi Al Safa 5.
Reading these figures
Each percentage is the share of construction recorded at the latest site inspection. The completion date is the one the developer registered, and RERA asks developers to update it when it reviews a project. Open a project to see its latest inspections, the site photos and whether it is keeping pace with that date.
What happens at handover and how to snag a new home cover the steps after 100%.
Source: the Dubai Land Department’s Mashrooi register, read daily. Projects listed as cancelled or finished are not shown.