La Tilia At Villanova Phase 1 construction progress

The registered completion date for La Tilia At Villanova Phase 1 in Wadi Al Safa 5 is August 2028. At the last site inspection, in October 2026, it was 14% built. The developer is North Dubailand Projects.

14%

Built, at the site inspection of 5 October 2026

Running behind its date

Registered completion date
August 2028
Finish at recent pace
March 2032
Construction started
January 2025
First registered
December 2024
Developer
North Dubailand Projects
Units
410
Escrow bank
First Abu Dhabi Bank
Name in Arabic
لا تيليا في فيلانوفا المرحلة 1
Project number
3455
Site inspections
7

Schedule

Between December 2025 and October 2026 the site added about 1.3 points a month. At that rate it would finish around March 2032, more than three months after its registered date of August 2028.

0%25%50%75%100%2025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

5 October 2026

14%+8.7 pts

  • La Tilia At Villanova Phase 1 construction site, inspection photo 1, 5 October 2026
  • La Tilia At Villanova Phase 1 construction site, inspection photo 2, 5 October 2026
  • La Tilia At Villanova Phase 1 construction site, inspection photo 3, 5 October 2026
  • La Tilia At Villanova Phase 1 construction site, inspection photo 4, 5 October 2026

29 June 2026

5.0%+2.8 pts

  • La Tilia At Villanova Phase 1 construction site, inspection photo 1, 29 June 2026
  • La Tilia At Villanova Phase 1 construction site, inspection photo 2, 29 June 2026
  • La Tilia At Villanova Phase 1 construction site, inspection photo 3, 29 June 2026
  • La Tilia At Villanova Phase 1 construction site, inspection photo 4, 29 June 2026

24 March 2026

2.2%+0.9 pts

  • La Tilia At Villanova Phase 1 construction site, inspection photo 1, 24 March 2026
  • La Tilia At Villanova Phase 1 construction site, inspection photo 2, 24 March 2026
  • La Tilia At Villanova Phase 1 construction site, inspection photo 3, 24 March 2026
  • La Tilia At Villanova Phase 1 construction site, inspection photo 4, 24 March 2026

22 December 2025

1.3%+0.5 pts

  • La Tilia At Villanova Phase 1 construction site, inspection photo 1, 22 December 2025
  • La Tilia At Villanova Phase 1 construction site, inspection photo 2, 22 December 2025
  • La Tilia At Villanova Phase 1 construction site, inspection photo 3, 22 December 2025
  • La Tilia At Villanova Phase 1 construction site, inspection photo 4, 22 December 2025

8 September 2025

0.8%+0.6 pts

  • La Tilia At Villanova Phase 1 construction site, inspection photo 1, 8 September 2025
  • La Tilia At Villanova Phase 1 construction site, inspection photo 2, 8 September 2025
  • La Tilia At Villanova Phase 1 construction site, inspection photo 3, 8 September 2025

26 June 2025

0.2%+0.2 pts

  • La Tilia At Villanova Phase 1 construction site, inspection photo 1, 26 June 2025
  • La Tilia At Villanova Phase 1 construction site, inspection photo 2, 26 June 2025
  • La Tilia At Villanova Phase 1 construction site, inspection photo 3, 26 June 2025

16 December 2024

0%

  • La Tilia At Villanova Phase 1 construction site, inspection photo 1, 16 December 2024
  • La Tilia At Villanova Phase 1 construction site, inspection photo 2, 16 December 2024

All 28 site photos, by inspection date

Context

Wadi Al Safa 5 has 13 projects under construction, 24% built on average.

North Dubailand Projects has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in La Tilia At Villanova Phase 1?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the La Tilia At Villanova Phase 1 handover date?
The registered completion date is August 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2032. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on La Tilia At Villanova Phase 1?
La Tilia At Villanova Phase 1 was 14% built at the site inspection on 5 October 2026. The site has been inspected 7 times since December 2024. The Land Department took 28 site photos at its inspections.
Is La Tilia At Villanova Phase 1 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2028.
Who is building La Tilia At Villanova Phase 1?
The registered developer is North Dubailand Projects. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for La Tilia At Villanova Phase 1?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.