La Tilia At Villanova Phase 1 construction progress
La Tilia At Villanova Phase 1 in Wadi Al Safa 5 is 14% built at the Land Department inspection of October 2026. Developer North Dubailand Projects. Completion registered for August 2028.
14%
Built, at the Land Department site inspection of 5 October 2026
Running behind its date
- Completion date (Land Department)
- August 2028
- Finish at recent pace
- March 2032
- Construction started
- January 2025
- Registered with the Land Department
- December 2024
- Developer
- North Dubailand Projects
- Community
- Wadi Al Safa 5
- Units
- 410
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- لا تيليا في فيلانوفا المرحلة 1
- Land Department project number
- 3455
- Land Department site inspections
- 7
Schedule
Between December 2025 and October 2026 the site added about 1.3 points a month. At that rate it would finish around March 2032, more than three months after the August 2028 date registered with the Land Department.
Site inspections
5 October 2026
14%+8.7 pts
29 June 2026
5.0%+2.8 pts
24 March 2026
2.2%+0.9 pts
22 December 2025
1.3%+0.5 pts
8 September 2025
0.8%+0.6 pts
26 June 2025
0.2%+0.2 pts
16 December 2024
0%
Context
Wadi Al Safa 5 has 13 projects under construction, 17% built on average.
North Dubailand Projects has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in La Tilia At Villanova Phase 1?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will La Tilia At Villanova Phase 1 be completed?
- The completion date registered with the Dubai Land Department is August 2028. At the pace of its recent inspections the site would reach 100% around March 2032. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of La Tilia At Villanova Phase 1 is built?
- 14%, measured at the Land Department site inspection on 5 October 2026. The Land Department engineers have inspected the site 7 times since December 2024.
- Is La Tilia At Villanova Phase 1 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2028.
- Who is building La Tilia At Villanova Phase 1?
- The registered developer is North Dubailand Projects. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for La Tilia At Villanova Phase 1?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- La Tilia At Villanova Phase 2Also by North Dubailand Projects. 11%, Due August 2028.
- Haven By Aldar 1Nearby in Wadi Al Safa 5. 44%, Due November 2027.
- Haven By Aldar 2Nearby in Wadi Al Safa 5. 40%.
- Haven By Aldar 3Nearby in Wadi Al Safa 5. 58%, Due March 2028.
- Athlon By Al Dar 1Nearby in Wadi Al Safa 5. 18%, Due May 2028.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.





%2520(3).jpeg&w=3840&q=75)
%2520(4).jpeg&w=3840&q=75)
%2520(10).jpeg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)

