The registered completion date for Rise By Athlon 4 in Wadi Al Safa 5 is December 2029. At the last site inspection, in October 2026, it was 0.6% built. The developer is Aurora Spv 3.

0.6%

Built, at the site inspection of 22 October 2026

Running behind its date

Registered completion date
December 2029
Construction started
January 2026
First registered
September 2025
Developer
Aurora Spv 3
Units
66
Escrow bank
First Abu Dhabi Bank
Name in Arabic
رايز من أثلون 4
Project number
4047
Site inspections
3

Schedule

0%25%50%75%100%2026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

22 October 2026

0.6%

  • Rise By Athlon 4 construction site, inspection photo 1, 22 October 2026
  • Rise By Athlon 4 construction site, inspection photo 2, 22 October 2026
  • Rise By Athlon 4 construction site, inspection photo 3, 22 October 2026

19 May 2026

0.6%+0.6 pts

  • Rise By Athlon 4 construction site, inspection photo 1, 19 May 2026
  • Rise By Athlon 4 construction site, inspection photo 2, 19 May 2026
  • Rise By Athlon 4 construction site, inspection photo 3, 19 May 2026
  • Rise By Athlon 4 construction site, inspection photo 4, 19 May 2026

3 September 2025

0%

  • Rise By Athlon 4 construction site, inspection photo 1, 3 September 2025
  • Rise By Athlon 4 construction site, inspection photo 2, 3 September 2025

All 9 site photos, by inspection date

Context

Wadi Al Safa 5 has 13 projects under construction, 24% built on average.

Aurora Spv 3 has 6 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Rise By Athlon 4?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Rise By Athlon 4 handover date?
The registered completion date is December 2029. Handover of units starts once construction is complete, on the developer's schedule. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Rise By Athlon 4?
Rise By Athlon 4 was 0.6% built at the site inspection on 22 October 2026. The site has been inspected 3 times since September 2025. The Land Department took 9 site photos at its inspections.
Is Rise By Athlon 4 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2029.
Who is building Rise By Athlon 4?
The registered developer is Aurora Spv 3. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Rise By Athlon 4?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.