Rise By Athlon 4 construction progress
Rise By Athlon 4 in Wadi Al Safa 5 is 0.6% built at the Land Department inspection of May 2026. Developer Aurora Spv 3. Completion registered for December 2029.
0.6%
Built, at the Land Department site inspection of 19 May 2026
Running behind its date
- Completion date (Land Department)
- December 2029
- Finish at recent pace
- October 2151
- Construction started
- January 2026
- Registered with the Land Department
- September 2025
- Developer
- Aurora Spv 3
- Community
- Wadi Al Safa 5
- Units
- 66
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- رايز من أثلون 4
- Land Department project number
- 4047
- Land Department site inspections
- 2
Schedule
Between September 2025 and May 2026 the site added about 0.1 points a month. At that rate it would finish around October 2151, more than three months after the December 2029 date registered with the Land Department.
Site inspections
19 May 2026
0.6%+0.6 pts
3 September 2025
0%
Context
Wadi Al Safa 5 has 13 projects under construction, 17% built on average.
Aurora Spv 3 has 6 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Rise By Athlon 4?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Rise By Athlon 4 be completed?
- The completion date registered with the Dubai Land Department is December 2029. At the pace of its recent inspections the site would reach 100% around October 2151. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Rise By Athlon 4 is built?
- 0.6%, measured at the Land Department site inspection on 19 May 2026. The Land Department engineers have inspected the site 2 times since September 2025.
- Is Rise By Athlon 4 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2029.
- Who is building Rise By Athlon 4?
- The registered developer is Aurora Spv 3. It has 5 other projects under construction in Dubai.
- Which bank holds the escrow account for Rise By Athlon 4?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Athlon By Al Dar 1Also by Aurora Spv 3. 18%, Due May 2028.
- Athlon By Al Dar 2Also by Aurora Spv 3. 12%, Due September 2028.
- Rise By Athlon 1Also by Aurora Spv 3. 0.7%, Due December 2029.
- Rise By Athlon 2Also by Aurora Spv 3. 0.1%, Due January 2030.
- Haven By Aldar 1Nearby in Wadi Al Safa 5. 44%, Due November 2027.
- Haven By Aldar 2Nearby in Wadi Al Safa 5. 40%.
- Haven By Aldar 3Nearby in Wadi Al Safa 5. 58%, Due March 2028.
- Verdes By Haven 1Nearby in Wadi Al Safa 5. 13%, Due May 2028.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)