Silena Residences construction progress

Silena Residences in Palm Deira is 3.8% built at the Land Department inspection of July 2026. Developer Avenew Real Estate Development. Completion registered for May 2028.

3.8%

Built, at the Land Department site inspection of 31 July 2026

Running behind its date

Completion date (Land Department)
May 2028
Finish at recent pace
April 2039
Construction started
December 2025
Registered with the Land Department
August 2025
Community
Palm Deira
Units
137
Escrow bank
Dubai Islamic Bank
Name in Arabic
سيلينا ريزيدنسز
Land Department project number
3808
Land Department site inspections
4

Schedule

Between January 2026 and July 2026 the site added about 0.6 points a month. At that rate it would finish around April 2039, more than three months after the May 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

31 July 2026

3.8%+2.2 pts

  • Silena Residences construction site, Land Department inspection photo 1, 31 July 2026
  • Silena Residences construction site, Land Department inspection photo 2, 31 July 2026
  • Silena Residences construction site, Land Department inspection photo 3, 31 July 2026
  • Silena Residences construction site, Land Department inspection photo 4, 31 July 2026

1 May 2026

1.6%+1.6 pts

  • Silena Residences construction site, Land Department inspection photo 1, 1 May 2026
  • Silena Residences construction site, Land Department inspection photo 2, 1 May 2026
  • Silena Residences construction site, Land Department inspection photo 3, 1 May 2026
  • Silena Residences construction site, Land Department inspection photo 4, 1 May 2026

29 January 2026

0%+0.0 pts

  • Silena Residences construction site, Land Department inspection photo 1, 29 January 2026
  • Silena Residences construction site, Land Department inspection photo 2, 29 January 2026
  • Silena Residences construction site, Land Department inspection photo 3, 29 January 2026
  • Silena Residences construction site, Land Department inspection photo 4, 29 January 2026

24 June 2025

0%

  • Silena Residences construction site, Land Department inspection photo 1, 24 June 2025
  • Silena Residences construction site, Land Department inspection photo 2, 24 June 2025

All 15 site photos, by inspection date

Context

Palm Deira has 95 projects under construction, 22% built on average.

Avenew Real Estate Development has 7 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Silena Residences?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Silena Residences be completed?
The completion date registered with the Dubai Land Department is May 2028. At the pace of its recent inspections the site would reach 100% around April 2039. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Silena Residences is built?
3.8%, measured at the Land Department site inspection on 31 July 2026. The Land Department engineers have inspected the site 4 times since June 2025.
Is Silena Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2028.
Who is building Silena Residences?
The registered developer is Avenew Real Estate Development. It has 6 other projects under construction in Dubai.
Which bank holds the escrow account for Silena Residences?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.