Silena Residences construction progress
Silena Residences in Palm Deira is 3.8% built at the Land Department inspection of July 2026. Developer Avenew Real Estate Development. Completion registered for May 2028.
3.8%
Built, at the Land Department site inspection of 31 July 2026
Running behind its date
- Completion date (Land Department)
- May 2028
- Finish at recent pace
- April 2039
- Construction started
- December 2025
- Registered with the Land Department
- August 2025
- Developer
- Avenew Real Estate Development
- Community
- Palm Deira
- Units
- 137
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- سيلينا ريزيدنسز
- Land Department project number
- 3808
- Land Department site inspections
- 4
Schedule
Between January 2026 and July 2026 the site added about 0.6 points a month. At that rate it would finish around April 2039, more than three months after the May 2028 date registered with the Land Department.
Site inspections
31 July 2026
3.8%+2.2 pts
1 May 2026
1.6%+1.6 pts
29 January 2026
0%+0.0 pts
24 June 2025
0%
Context
Palm Deira has 95 projects under construction, 22% built on average.
Avenew Real Estate Development has 7 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Silena Residences?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Silena Residences be completed?
- The completion date registered with the Dubai Land Department is May 2028. At the pace of its recent inspections the site would reach 100% around April 2039. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Silena Residences is built?
- 3.8%, measured at the Land Department site inspection on 31 July 2026. The Land Department engineers have inspected the site 4 times since June 2025.
- Is Silena Residences delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2028.
- Who is building Silena Residences?
- The registered developer is Avenew Real Estate Development. It has 6 other projects under construction in Dubai.
- Which bank holds the escrow account for Silena Residences?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- RenaAlso by Avenew Real Estate Development. 32%.
- ShoaqAlso by Avenew Real Estate Development. 8.6%, Due October 2027.
- Avenew888 - ModoAlso by Avenew Real Estate Development. 15%, Due March 2028.
- LiaAlso by Avenew Real Estate Development. 4.1%, Due May 2028.
- Bay Residences Dubai IslandsNearby in Palm Deira. 48%, Due October 2026.
- Beach Residences Dubai IslandsNearby in Palm Deira. 29%.
- Bay Villas - Dubai IslandsNearby in Palm Deira. 23%, Due May 2027.
- Edgewater ResidencesNearby in Palm Deira. 48%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.








.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)