Bay Residences Dubai Islands construction progress
Bay Residences Dubai Islands in Palm Deira was registered to complete in October 2026 and is still under construction. At the last site inspection, in June 2026, it was 48% built. The developer is Nakheel And Excelsior Real Estate.
48%
Built, at the site inspection of 22 June 2026
1 months past its registered completion date
- Registered completion date
- October 2026
- Finish at recent pace
- February 2028
- Construction started
- January 2024
- First registered
- July 2023
- Developer
- Nakheel And Excelsior Real Estate
- Community
- Palm Deira
- Units
- 302
- Escrow bank
- Mashreq Bank
- Name in Arabic
- باي ريزيدنسز جزر دبي
- Project number
- 2719
- Site inspections
- 8
Schedule
Bay Residences Dubai Islands was registered to complete in October 2026, 1 month ago, and is still under construction. Over the last year of inspections it has added about 2.6 points a month. Kept at that rate, the site would reach 100% around February 2028.
Site inspections
22 June 2026
48%+12 pts
26 March 2026
36%+12 pts
30 October 2025
25%+5.5 pts
24 July 2025
19%+5.2 pts
19 April 2025
14%+6.4 pts
22 January 2025
7.5%+7.3 pts
5 July 2024
0.2%+0.2 pts
11 July 2023
0%
Context
Palm Deira has 94 projects under construction, 24% built on average.
Nakheel And Excelsior Real Estate has 2 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Bay Residences Dubai Islands?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Bay Residences Dubai Islands handover date?
- The registered completion date was October 2026, and the register still lists Bay Residences Dubai Islands as under construction. At the pace of its recent inspections the site would reach 100% around February 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Bay Residences Dubai Islands?
- Bay Residences Dubai Islands was 48% built at the site inspection on 22 June 2026. The site has been inspected 8 times since July 2023. The Land Department took 59 site photos at its inspections.
- Is Bay Residences Dubai Islands delayed?
- Yes. Its registered completion date of October 2026 has passed and the project is still listed as under construction.
- Who is building Bay Residences Dubai Islands?
- The registered developer is Nakheel And Excelsior Real Estate. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Bay Residences Dubai Islands?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Beach Residences Dubai IslandsAlso by Nakheel And Excelsior Real Estate. 29%.
- Bay Villas - Dubai IslandsNearby in Palm Deira. 23%, Due May 2027.
- Edgewater ResidencesNearby in Palm Deira. 48%.
- Hatimi Residences By FakhruddinNearby in Palm Deira. 63%, Due October 2026, passed.
- Edgewater Residences 2Nearby in Palm Deira. 55%, Due August 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.


.jpg&w=3840&q=75)








.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)