Lia construction progress

The registered completion date for Lia is May 2028. At the last site inspection, in October 2026, it was 4.1% built. The developer is Avenew Real Estate Development.

4.1%

Built, at the site inspection of 2 October 2026

Running behind its date

Registered completion date
May 2028
Finish at recent pace
October 2047
Construction started
March 2026
First registered
November 2025
Units
82
Escrow bank
Dubai Islamic Bank
Name in Arabic
ليا
Project number
4195
Site inspections
3

Schedule

Between November 2025 and October 2026 the site added about 0.4 points a month. At that rate it would finish around October 2047, more than three months after its registered date of May 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

2 October 2026

4.1%+4.0 pts

  • Lia construction site, inspection photo 1, 2 October 2026
  • Lia construction site, inspection photo 2, 2 October 2026
  • Lia construction site, inspection photo 3, 2 October 2026
  • Lia construction site, inspection photo 4, 2 October 2026

10 June 2026

0.1%+0.1 pts

  • Lia construction site, inspection photo 1, 10 June 2026
  • Lia construction site, inspection photo 2, 10 June 2026
  • Lia construction site, inspection photo 3, 10 June 2026
  • Lia construction site, inspection photo 4, 10 June 2026

11 November 2025

0%

  • Lia construction site, inspection photo 1, 11 November 2025
  • Lia construction site, inspection photo 2, 11 November 2025

All 11 site photos, by inspection date

Context

Avenew Real Estate Development has 8 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Lia?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Lia handover date?
The registered completion date is May 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2047. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Lia?
Lia was 4.1% built at the site inspection on 2 October 2026. The site has been inspected 3 times since November 2025. The Land Department took 11 site photos at its inspections.
Is Lia delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2028.
Who is building Lia?
The registered developer is Avenew Real Estate Development. It has 7 other projects under construction in Dubai.
Which bank holds the escrow account for Lia?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.