Skip to content

Lia construction progress

Lia is 4.1% built at the Land Department inspection of October 2026. Developer Avenew Real Estate Development. Completion registered for May 2028.

4.1%

Built, at the Land Department site inspection of 2 October 2026

Running behind its date

Completion date (Land Department)
May 2028
Finish at recent pace
October 2047
Construction started
March 2026
Registered with the Land Department
November 2025
Units
82
Escrow bank
Dubai Islamic Bank
Name in Arabic
ليا
Land Department project number
4195
Land Department site inspections
3

Schedule

Between November 2025 and October 2026 the site added about 0.4 points a month. At that rate it would finish around October 2047, more than three months after the May 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

2 October 2026

4.1%+4.0 pts

  • Lia construction site, Land Department inspection photo 1, 2 October 2026
  • Lia construction site, Land Department inspection photo 2, 2 October 2026
  • Lia construction site, Land Department inspection photo 3, 2 October 2026
  • Lia construction site, Land Department inspection photo 4, 2 October 2026

10 June 2026

0.1%+0.1 pts

  • Lia construction site, Land Department inspection photo 1, 10 June 2026
  • Lia construction site, Land Department inspection photo 2, 10 June 2026
  • Lia construction site, Land Department inspection photo 3, 10 June 2026
  • Lia construction site, Land Department inspection photo 4, 10 June 2026

11 November 2025

0%

  • Lia construction site, Land Department inspection photo 1, 11 November 2025
  • Lia construction site, Land Department inspection photo 2, 11 November 2025

All 11 site photos, by inspection date

Context

Avenew Real Estate Development has 7 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Lia?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Lia be completed?
The completion date registered with the Dubai Land Department is May 2028. At the pace of its recent inspections the site would reach 100% around October 2047. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Lia is built?
4.1%, measured at the Land Department site inspection on 2 October 2026. The Land Department engineers have inspected the site 3 times since November 2025.
Is Lia delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2028.
Who is building Lia?
The registered developer is Avenew Real Estate Development. It has 6 other projects under construction in Dubai.
Which bank holds the escrow account for Lia?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.