Bay Villas - Dubai Islands construction progress

The registered completion date for Bay Villas - Dubai Islands in Palm Deira is May 2027. At the last site inspection, in August 2026, it was 23% built. The developer is Dubai Islands.

23%

Built, at the site inspection of 19 August 2026

Running behind its date

Registered completion date
May 2027
Finish at recent pace
December 2029
Construction started
July 2024
First registered
February 2024
Developer
Dubai Islands
Community
Palm Deira
Units
636
Escrow bank
Dubai Islamic Bank
Name in Arabic
باي فيلاز - جزر دبي
Project number
2899
Site inspections
8

Schedule

Between October 2025 and August 2026 the site added about 1.9 points a month. At that rate it would finish around December 2029, more than three months after its registered date of May 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

19 August 2026

23%+8.0 pts

  • Bay Villas - Dubai Islands construction site, inspection photo 1, 19 August 2026
  • Bay Villas - Dubai Islands construction site, inspection photo 2, 19 August 2026
  • Bay Villas - Dubai Islands construction site, inspection photo 3, 19 August 2026
  • Bay Villas - Dubai Islands construction site, inspection photo 4, 19 August 2026

7 May 2026

15%+7.7 pts

  • Bay Villas - Dubai Islands construction site, inspection photo 1, 7 May 2026
  • Bay Villas - Dubai Islands construction site, inspection photo 2, 7 May 2026
  • Bay Villas - Dubai Islands construction site, inspection photo 3, 7 May 2026
  • Bay Villas - Dubai Islands construction site, inspection photo 4, 7 May 2026

26 January 2026

7.0%+4.4 pts

  • Bay Villas - Dubai Islands construction site, inspection photo 1, 26 January 2026
  • Bay Villas - Dubai Islands construction site, inspection photo 2, 26 January 2026
  • Bay Villas - Dubai Islands construction site, inspection photo 3, 26 January 2026
  • Bay Villas - Dubai Islands construction site, inspection photo 4, 26 January 2026

2 October 2025

2.6%+2.2 pts

  • Bay Villas - Dubai Islands construction site, inspection photo 1, 2 October 2025
  • Bay Villas - Dubai Islands construction site, inspection photo 2, 2 October 2025
  • Bay Villas - Dubai Islands construction site, inspection photo 3, 2 October 2025
  • Bay Villas - Dubai Islands construction site, inspection photo 4, 2 October 2025

10 June 2025

0.4%+0.2 pts

  • Bay Villas - Dubai Islands construction site, inspection photo 1, 10 June 2025
  • Bay Villas - Dubai Islands construction site, inspection photo 2, 10 June 2025
  • Bay Villas - Dubai Islands construction site, inspection photo 3, 10 June 2025
  • Bay Villas - Dubai Islands construction site, inspection photo 4, 10 June 2025

10 March 2025

0.2%+0.2 pts

  • Bay Villas - Dubai Islands construction site, inspection photo 1, 10 March 2025
  • Bay Villas - Dubai Islands construction site, inspection photo 2, 10 March 2025
  • Bay Villas - Dubai Islands construction site, inspection photo 3, 10 March 2025
  • Bay Villas - Dubai Islands construction site, inspection photo 4, 10 March 2025

26 September 2024

0%

  • Bay Villas - Dubai Islands construction site, inspection photo 1, 26 September 2024
  • Bay Villas - Dubai Islands construction site, inspection photo 2, 26 September 2024
  • Bay Villas - Dubai Islands construction site, inspection photo 3, 26 September 2024
  • Bay Villas - Dubai Islands construction site, inspection photo 4, 26 September 2024

6 February 2024

0%

  • Bay Villas - Dubai Islands construction site, inspection photo 1, 6 February 2024
  • Bay Villas - Dubai Islands construction site, inspection photo 2, 6 February 2024
  • Bay Villas - Dubai Islands construction site, inspection photo 3, 6 February 2024

All 53 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Dubai Islands has 6 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Bay Villas - Dubai Islands?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Bay Villas - Dubai Islands handover date?
The registered completion date is May 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Bay Villas - Dubai Islands?
Bay Villas - Dubai Islands was 23% built at the site inspection on 19 August 2026. The site has been inspected 8 times since February 2024. The Land Department took 53 site photos at its inspections.
Is Bay Villas - Dubai Islands delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2027.
Who is building Bay Villas - Dubai Islands?
The registered developer is Dubai Islands. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Bay Villas - Dubai Islands?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.