Avenew888 - Modo construction progress

The registered completion date for Avenew888 - Modo in Dubai South Residential District is March 2028. At the last site inspection, in October 2026, it was 21% built. The developer is Avenew Real Estate Development.

21%

Built, at the site inspection of 8 October 2026

Running behind its date

Registered completion date
March 2028
Finish at recent pace
October 2028
Construction started
November 2025
First registered
July 2025
Units
224
Escrow bank
Dubai Islamic Bank
Name in Arabic
أفينيو 888- مودو
Project number
3828
Site inspections
5

Schedule

Between March 2026 and October 2026 the site added about 3.2 points a month. At that rate it would finish around October 2028, more than three months after its registered date of March 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

8 October 2026

21%+5.7 pts

  • Avenew888 - Modo construction site, inspection photo 1, 8 October 2026
  • Avenew888 - Modo construction site, inspection photo 2, 8 October 2026
  • Avenew888 - Modo construction site, inspection photo 3, 8 October 2026
  • Avenew888 - Modo construction site, inspection photo 4, 8 October 2026

27 August 2026

15%+8.3 pts

  • Avenew888 - Modo construction site, inspection photo 1, 27 August 2026
  • Avenew888 - Modo construction site, inspection photo 2, 27 August 2026
  • Avenew888 - Modo construction site, inspection photo 3, 27 August 2026
  • Avenew888 - Modo construction site, inspection photo 4, 27 August 2026

17 July 2026

7.1%+6.0 pts

  • Avenew888 - Modo construction site, inspection photo 1, 17 July 2026
  • Avenew888 - Modo construction site, inspection photo 2, 17 July 2026
  • Avenew888 - Modo construction site, inspection photo 3, 17 July 2026
  • Avenew888 - Modo construction site, inspection photo 4, 17 July 2026

30 March 2026

1.2%+1.2 pts

  • Avenew888 - Modo construction site, inspection photo 1, 30 March 2026
  • Avenew888 - Modo construction site, inspection photo 2, 30 March 2026
  • Avenew888 - Modo construction site, inspection photo 3, 30 March 2026

24 June 2025

0%

  • Avenew888 - Modo construction site, inspection photo 1, 24 June 2025
  • Avenew888 - Modo construction site, inspection photo 2, 24 June 2025

All 22 site photos, by inspection date

Context

Dubai South Residential District has 37 projects under construction, 43% built on average.

Avenew Real Estate Development has 8 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Avenew888 - Modo?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Avenew888 - Modo handover date?
The registered completion date is March 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Avenew888 - Modo?
Avenew888 - Modo was 21% built at the site inspection on 8 October 2026. The site has been inspected 5 times since June 2025. The Land Department took 22 site photos at its inspections.
Is Avenew888 - Modo delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2028.
Who is building Avenew888 - Modo?
The registered developer is Avenew Real Estate Development. It has 7 other projects under construction in Dubai.
Which bank holds the escrow account for Avenew888 - Modo?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.