Shoaq construction progress

Shoaq in Palm Deira is 8.6% built at the Land Department inspection of July 2026. Developer Avenew Real Estate Development. Completion registered for October 2027.

8.6%

Built, at the Land Department site inspection of 31 July 2026

Running behind its date

Completion date (Land Department)
October 2027
Finish at recent pace
January 2035
Construction started
September 2025
Registered with the Land Department
April 2025
Community
Palm Deira
Units
78
Escrow bank
Dubai Islamic Bank
Name in Arabic
شوق
Land Department project number
3630
Land Department site inspections
5

Schedule

Between October 2025 and July 2026 the site added about 0.9 points a month. At that rate it would finish around January 2035, more than three months after the October 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

31 July 2026

8.6%+3.0 pts

  • Shoaq construction site, Land Department inspection photo 1, 31 July 2026
  • Shoaq construction site, Land Department inspection photo 2, 31 July 2026
  • Shoaq construction site, Land Department inspection photo 3, 31 July 2026
  • Shoaq construction site, Land Department inspection photo 4, 31 July 2026

1 May 2026

5.6%+3.2 pts

  • Shoaq construction site, Land Department inspection photo 1, 1 May 2026
  • Shoaq construction site, Land Department inspection photo 2, 1 May 2026
  • Shoaq construction site, Land Department inspection photo 3, 1 May 2026
  • Shoaq construction site, Land Department inspection photo 4, 1 May 2026

19 February 2026

2.4%+2.0 pts

  • Shoaq construction site, Land Department inspection photo 1, 19 February 2026
  • Shoaq construction site, Land Department inspection photo 2, 19 February 2026
  • Shoaq construction site, Land Department inspection photo 3, 19 February 2026
  • Shoaq construction site, Land Department inspection photo 4, 19 February 2026

24 October 2025

0.3%+0.3 pts

  • Shoaq construction site, Land Department inspection photo 1, 24 October 2025
  • Shoaq construction site, Land Department inspection photo 2, 24 October 2025

10 April 2025

0%

  • Shoaq construction site, Land Department inspection photo 1, 10 April 2025
  • Shoaq construction site, Land Department inspection photo 2, 10 April 2025

All 19 site photos, by inspection date

Context

Palm Deira has 95 projects under construction, 22% built on average.

Avenew Real Estate Development has 7 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Shoaq?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Shoaq be completed?
The completion date registered with the Dubai Land Department is October 2027. At the pace of its recent inspections the site would reach 100% around January 2035. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Shoaq is built?
8.6%, measured at the Land Department site inspection on 31 July 2026. The Land Department engineers have inspected the site 5 times since April 2025.
Is Shoaq delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2027.
Who is building Shoaq?
The registered developer is Avenew Real Estate Development. It has 6 other projects under construction in Dubai.
Which bank holds the escrow account for Shoaq?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.