Shoaq construction progress

The registered completion date for Shoaq in Palm Deira is October 2027. At the last site inspection, in October 2026, it was 16% built. The developer is Avenew Real Estate Development.

16%

Built, at the site inspection of 27 October 2026

Running behind its date

Registered completion date
October 2027
Finish at recent pace
January 2031
Construction started
September 2025
First registered
April 2025
Community
Palm Deira
Units
78
Escrow bank
Dubai Islamic Bank
Name in Arabic
شوق
Project number
3630
Site inspections
6

Schedule

Between February 2026 and October 2026 the site added about 1.7 points a month. At that rate it would finish around January 2031, more than three months after its registered date of October 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

27 October 2026

16%+7.4 pts

  • Shoaq construction site, inspection photo 1, 27 October 2026
  • Shoaq construction site, inspection photo 2, 27 October 2026
  • Shoaq construction site, inspection photo 3, 27 October 2026
  • Shoaq construction site, inspection photo 4, 27 October 2026

31 July 2026

8.6%+3.0 pts

  • Shoaq construction site, inspection photo 1, 31 July 2026
  • Shoaq construction site, inspection photo 2, 31 July 2026
  • Shoaq construction site, inspection photo 3, 31 July 2026
  • Shoaq construction site, inspection photo 4, 31 July 2026

1 May 2026

5.6%+3.2 pts

  • Shoaq construction site, inspection photo 1, 1 May 2026
  • Shoaq construction site, inspection photo 2, 1 May 2026
  • Shoaq construction site, inspection photo 3, 1 May 2026
  • Shoaq construction site, inspection photo 4, 1 May 2026

19 February 2026

2.4%+2.0 pts

  • Shoaq construction site, inspection photo 1, 19 February 2026
  • Shoaq construction site, inspection photo 2, 19 February 2026
  • Shoaq construction site, inspection photo 3, 19 February 2026
  • Shoaq construction site, inspection photo 4, 19 February 2026

24 October 2025

0.3%+0.3 pts

  • Shoaq construction site, inspection photo 1, 24 October 2025
  • Shoaq construction site, inspection photo 2, 24 October 2025

10 April 2025

0%

  • Shoaq construction site, inspection photo 1, 10 April 2025
  • Shoaq construction site, inspection photo 2, 10 April 2025

All 27 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Avenew Real Estate Development has 8 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Shoaq?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Shoaq handover date?
The registered completion date is October 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2031. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Shoaq?
Shoaq was 16% built at the site inspection on 27 October 2026. The site has been inspected 6 times since April 2025. The Land Department took 27 site photos at its inspections.
Is Shoaq delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2027.
Who is building Shoaq?
The registered developer is Avenew Real Estate Development. It has 7 other projects under construction in Dubai.
Which bank holds the escrow account for Shoaq?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.