Edgewater Residences construction progress
No completion date is registered for Edgewater Residences in Palm Deira yet. At the last site inspection, in August 2026, it was 48% built. The developer is M G S Development.
48%
Built, at the site inspection of 31 August 2026
- Finish at recent pace
- November 2027
- Construction started
- April 2024
- First registered
- April 2024
- Developer
- M G S Development
- Community
- Palm Deira
- Units
- 79
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- مساكن ايدج ووتر
- Project number
- 2930
- Site inspections
- 6
Schedule
Since November 2025 Edgewater Residences has added about 3.5 points a month. At that rate the site reaches 100% around November 2027. No completion date is on record to compare it with.
Site inspections
31 August 2026
48%+20 pts
6 April 2026
28%+12 pts
27 November 2025
16%+6.6 pts
15 July 2025
9.2%+6.4 pts
27 January 2025
2.8%+2.8 pts
12 February 2024
0%
Context
Palm Deira has 94 projects under construction, 24% built on average.
M G S Development has 3 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Edgewater Residences?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Edgewater Residences handover date?
- No completion date is on record for Edgewater Residences yet. Handover follows completion, so there is no date to give.
- What is the latest construction update on Edgewater Residences?
- Edgewater Residences was 48% built at the site inspection on 31 August 2026. The site has been inspected 6 times since February 2024. The Land Department took 35 site photos at its inspections.
- Who is building Edgewater Residences?
- The registered developer is M G S Development. It has 2 other projects under construction in Dubai.
- Which bank holds the escrow account for Edgewater Residences?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Edgewater Residences 2Also by M G S Development. 55%, Due August 2026, passed.
- Edgewater Residences 3Also by M G S Development. 30%, Due January 2027.
- Bay Residences Dubai IslandsNearby in Palm Deira. 48%, Due October 2026, passed.
- Beach Residences Dubai IslandsNearby in Palm Deira. 29%.
- Bay Villas - Dubai IslandsNearby in Palm Deira. 23%, Due May 2027.
- Hatimi Residences By FakhruddinNearby in Palm Deira. 63%, Due October 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.