Rena construction progress

The registered completion date for Rena in Palm Deira is May 2027. At the last site inspection, in August 2026, it was 32% built. The developer is Avenew Real Estate Development.

32%

Built, at the site inspection of 31 August 2026

Running behind its date

Registered completion date
May 2027
Finish at recent pace
November 2028
Construction started
May 2025
First registered
February 2025
Community
Palm Deira
Units
64
Escrow bank
Dubai Islamic Bank
Name in Arabic
رينا
Project number
3447
Site inspections
6

Schedule

Between September 2025 and August 2026 the site added about 2.5 points a month. At that rate it would finish around November 2028, more than three months after its registered date of May 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

31 August 2026

32%+12 pts

  • Rena construction site, inspection photo 1, 31 August 2026
  • Rena construction site, inspection photo 2, 31 August 2026
  • Rena construction site, inspection photo 3, 31 August 2026
  • Rena construction site, inspection photo 4, 31 August 2026

23 June 2026

20%+3.5 pts

  • Rena construction site, inspection photo 1, 23 June 2026
  • Rena construction site, inspection photo 2, 23 June 2026
  • Rena construction site, inspection photo 3, 23 June 2026
  • Rena construction site, inspection photo 4, 23 June 2026

30 April 2026

16%+8.6 pts

  • Rena construction site, inspection photo 1, 30 April 2026
  • Rena construction site, inspection photo 2, 30 April 2026
  • Rena construction site, inspection photo 3, 30 April 2026

29 January 2026

7.9%+4.1 pts

  • Rena construction site, inspection photo 1, 29 January 2026
  • Rena construction site, inspection photo 2, 29 January 2026
  • Rena construction site, inspection photo 3, 29 January 2026
  • Rena construction site, inspection photo 4, 29 January 2026

29 September 2025

3.8%+3.8 pts

  • Rena construction site, inspection photo 1, 29 September 2025
  • Rena construction site, inspection photo 2, 29 September 2025
  • Rena construction site, inspection photo 3, 29 September 2025

7 February 2025

0%

  • Rena construction site, inspection photo 1, 7 February 2025
  • Rena construction site, inspection photo 2, 7 February 2025

All 32 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Avenew Real Estate Development has 8 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Rena?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Rena handover date?
The registered completion date is May 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Rena?
Rena was 32% built at the site inspection on 31 August 2026. The site has been inspected 6 times since February 2025. The Land Department took 32 site photos at its inspections.
Is Rena delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2027.
Who is building Rena?
The registered developer is Avenew Real Estate Development. It has 7 other projects under construction in Dubai.
Which bank holds the escrow account for Rena?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.