Rena construction progress
The registered completion date for Rena in Palm Deira is May 2027. At the last site inspection, in August 2026, it was 32% built. The developer is Avenew Real Estate Development.
32%
Built, at the site inspection of 31 August 2026
Running behind its date
- Registered completion date
- May 2027
- Finish at recent pace
- November 2028
- Construction started
- May 2025
- First registered
- February 2025
- Developer
- Avenew Real Estate Development
- Community
- Palm Deira
- Units
- 64
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- رينا
- Project number
- 3447
- Site inspections
- 6
Schedule
Between September 2025 and August 2026 the site added about 2.5 points a month. At that rate it would finish around November 2028, more than three months after its registered date of May 2027.
Site inspections
31 August 2026
32%+12 pts
23 June 2026
20%+3.5 pts
30 April 2026
16%+8.6 pts
29 January 2026
7.9%+4.1 pts
29 September 2025
3.8%+3.8 pts
7 February 2025
0%
Context
Palm Deira has 94 projects under construction, 24% built on average.
Avenew Real Estate Development has 8 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Rena?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Rena handover date?
- The registered completion date is May 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Rena?
- Rena was 32% built at the site inspection on 31 August 2026. The site has been inspected 6 times since February 2025. The Land Department took 32 site photos at its inspections.
- Is Rena delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2027.
- Who is building Rena?
- The registered developer is Avenew Real Estate Development. It has 7 other projects under construction in Dubai.
- Which bank holds the escrow account for Rena?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- ShoaqAlso by Avenew Real Estate Development. 16%, Due October 2027.
- Silena ResidencesAlso by Avenew Real Estate Development. 5.7%, Due May 2028.
- Avenew888 - ModoAlso by Avenew Real Estate Development. 21%, Due March 2028.
- LiaAlso by Avenew Real Estate Development. 4.1%, Due May 2028.
- Bay Residences Dubai IslandsNearby in Palm Deira. 48%, Due October 2026, passed.
- Beach Residences Dubai IslandsNearby in Palm Deira. 29%.
- Bay Villas - Dubai IslandsNearby in Palm Deira. 23%, Due May 2027.
- Edgewater ResidencesNearby in Palm Deira. 48%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.