Shoaq construction photos
19 photos taken by Dubai Land Department engineers at 5 site inspections, newest first. The percentage is how much of Shoaq was built on the day of each visit.
31 July 20268.6% built
1 May 20265.6% built
19 February 20262.4% built
24 October 20250.3% built
10 April 20250% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.