Skip to content

Verde By Sobha construction progress

The registered completion date for Verde By Sobha in Jumeirah Lakes Towers is June 2027. At the last site inspection, in August 2026, it was 85% built. The developer is Sobha.

85%

Built, at the site inspection of 24 August 2026

On pace for its date

Registered completion date
June 2027
Finish at recent pace
December 2026
Construction started
April 2023
First registered
April 2023
Developer
Sobha
Units
610
Escrow bank
First Abu Dhabi Bank
Name in Arabic
فيردي باي شوبا
Project number
2583
Site inspections
9

Schedule

Since November 2025 Verde By Sobha has added about 4.2 points a month. That puts 100% around December 2026, within three months of its registered completion date of June 2027.

0%25%50%75%100%2024202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

24 August 2026

85%+9.4 pts

  • Verde By Sobha construction site, inspection photo 1, 24 August 2026
  • Verde By Sobha construction site, inspection photo 2, 24 August 2026
  • Verde By Sobha construction site, inspection photo 3, 24 August 2026
  • Verde By Sobha construction site, inspection photo 4, 24 August 2026

22 May 2026

76%+14 pts

  • Verde By Sobha construction site, inspection photo 1, 22 May 2026
  • Verde By Sobha construction site, inspection photo 2, 22 May 2026
  • Verde By Sobha construction site, inspection photo 3, 22 May 2026
  • Verde By Sobha construction site, inspection photo 4, 22 May 2026

23 February 2026

62%+17 pts

  • Verde By Sobha construction site, inspection photo 1, 23 February 2026
  • Verde By Sobha construction site, inspection photo 2, 23 February 2026
  • Verde By Sobha construction site, inspection photo 3, 23 February 2026
  • Verde By Sobha construction site, inspection photo 4, 23 February 2026

5 November 2025

45%+18 pts

  • Verde By Sobha construction site, inspection photo 1, 5 November 2025
  • Verde By Sobha construction site, inspection photo 2, 5 November 2025
  • Verde By Sobha construction site, inspection photo 3, 5 November 2025
  • Verde By Sobha construction site, inspection photo 4, 5 November 2025

17 April 2025

27%+7.8 pts

  • Verde By Sobha construction site, inspection photo 1, 17 April 2025
  • Verde By Sobha construction site, inspection photo 2, 17 April 2025
  • Verde By Sobha construction site, inspection photo 3, 17 April 2025
  • Verde By Sobha construction site, inspection photo 4, 17 April 2025

23 December 2024

19%+9.5 pts

  • Verde By Sobha construction site, inspection photo 1, 23 December 2024
  • Verde By Sobha construction site, inspection photo 2, 23 December 2024
  • Verde By Sobha construction site, inspection photo 3, 23 December 2024
  • Verde By Sobha construction site, inspection photo 4, 23 December 2024

15 March 2024

9.4%+5.1 pts

  • Verde By Sobha construction site, inspection photo 1, 15 March 2024
  • Verde By Sobha construction site, inspection photo 2, 15 March 2024
  • Verde By Sobha construction site, inspection photo 3, 15 March 2024
  • Verde By Sobha construction site, inspection photo 4, 15 March 2024

6 October 2023

4.4%+4.4 pts

  • Verde By Sobha construction site, inspection photo 1, 6 October 2023
  • Verde By Sobha construction site, inspection photo 2, 6 October 2023
  • Verde By Sobha construction site, inspection photo 3, 6 October 2023
  • Verde By Sobha construction site, inspection photo 4, 6 October 2023

16 February 2023

0%

  • Verde By Sobha construction site, inspection photo 1, 16 February 2023
  • Verde By Sobha construction site, inspection photo 2, 16 February 2023

All 79 site photos, by inspection date

Context

Jumeirah Lakes Towers has 8 projects under construction, 51% built on average.

Sobha has 27 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Verde By Sobha?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Verde By Sobha handover date?
The registered completion date is June 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Verde By Sobha?
Verde By Sobha was 85% built at the site inspection on 24 August 2026. The site has been inspected 9 times since February 2023. The Land Department took 79 site photos at its inspections.
Is Verde By Sobha delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of June 2027.
Who is building Verde By Sobha?
The registered developer is Sobha. It has 26 other projects under construction in Dubai.
Which bank holds the escrow account for Verde By Sobha?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.