The Waterside Villas By Ellington construction progress

The Waterside Villas By Ellington in Mohammed Bin Rashid Al Maktoum District 11 is 32% built at the Land Department inspection of June 2026. Developer Ellington Properties Development. Completion registered for June 2026.

32%

Built, at the Land Department site inspection of 9 June 2026

3 months past its registered completion date

Completion date (Land Department)
June 2026
Finish at recent pace
March 2028
Construction started
June 2023
Registered with the Land Department
September 2023
Units
17
Escrow bank
Commercial Bank of Dubai
Name in Arabic
ذا واترسايد فيلاز من إلينغتون
Land Department project number
2716
Land Department site inspections
6

Schedule

The Waterside Villas By Ellington was registered to complete in June 2026, 3 months ago, and is still under construction. Over the last year of inspections it has added about 3.2 points a month. Kept at that rate, the site would reach 100% around March 2028.

0%25%50%75%100%202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

9 June 2026

32%+15 pts

  • The Waterside Villas By Ellington construction site, Land Department inspection photo 1, 9 June 2026
  • The Waterside Villas By Ellington construction site, Land Department inspection photo 2, 9 June 2026
  • The Waterside Villas By Ellington construction site, Land Department inspection photo 3, 9 June 2026
  • The Waterside Villas By Ellington construction site, Land Department inspection photo 4, 9 June 2026

2 February 2026

17%+10 pts

  • The Waterside Villas By Ellington construction site, Land Department inspection photo 1, 2 February 2026
  • The Waterside Villas By Ellington construction site, Land Department inspection photo 2, 2 February 2026
  • The Waterside Villas By Ellington construction site, Land Department inspection photo 3, 2 February 2026
  • The Waterside Villas By Ellington construction site, Land Department inspection photo 4, 2 February 2026

16 October 2025

7.0%+4.5 pts

  • The Waterside Villas By Ellington construction site, Land Department inspection photo 1, 16 October 2025
  • The Waterside Villas By Ellington construction site, Land Department inspection photo 2, 16 October 2025
  • The Waterside Villas By Ellington construction site, Land Department inspection photo 3, 16 October 2025
  • The Waterside Villas By Ellington construction site, Land Department inspection photo 4, 16 October 2025

4 June 2025

2.5%+2.4 pts

  • The Waterside Villas By Ellington construction site, Land Department inspection photo 1, 4 June 2025
  • The Waterside Villas By Ellington construction site, Land Department inspection photo 2, 4 June 2025
  • The Waterside Villas By Ellington construction site, Land Department inspection photo 3, 4 June 2025
  • The Waterside Villas By Ellington construction site, Land Department inspection photo 4, 4 June 2025

2 July 2024

0.1%+0.1 pts

  • The Waterside Villas By Ellington construction site, Land Department inspection photo 1, 2 July 2024
  • The Waterside Villas By Ellington construction site, Land Department inspection photo 2, 2 July 2024

10 July 2023

0%

  • The Waterside Villas By Ellington construction site, Land Department inspection photo 1, 10 July 2023
  • The Waterside Villas By Ellington construction site, Land Department inspection photo 2, 10 July 2023
  • The Waterside Villas By Ellington construction site, Land Department inspection photo 3, 10 July 2023
  • The Waterside Villas By Ellington construction site, Land Department inspection photo 4, 10 July 2023

All 32 site photos, by inspection date

Context

Mohammed Bin Rashid Al Maktoum District 11 has 27 projects under construction, 26% built on average. The Waterside Villas By Ellington is ahead of that average.

Ellington Properties Development has 18 projects under construction in Dubai; 5 have passed their registered completion date.

Own a unit in The Waterside Villas By Ellington?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will The Waterside Villas By Ellington be completed?
The completion date registered with the Dubai Land Department is June 2026. At the pace of its recent inspections the site would reach 100% around March 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of The Waterside Villas By Ellington is built?
32%, measured at the Land Department site inspection on 9 June 2026. The Land Department engineers have inspected the site 6 times since July 2023.
Is The Waterside Villas By Ellington delayed?
Yes. Its registered completion date of June 2026 has passed and the Land Department still lists it as under construction.
Who is building The Waterside Villas By Ellington?
The registered developer is Ellington Properties Development. It has 17 other projects under construction in Dubai.
Which bank holds the escrow account for The Waterside Villas By Ellington?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.