Uh East By Ellington construction progress

Uh East By Ellington in Jumeirah Lakes Towers is 47% built at the Land Department inspection of June 2026. Developer Ellington Properties Development. Completion registered for March 2026.

47%

Built, at the Land Department site inspection of 11 June 2026

7 months past its registered completion date

Completion date (Land Department)
March 2026
Finish at recent pace
December 2027
Construction started
May 2023
Registered with the Land Department
August 2023
Units
381
Escrow bank
First Abu Dhabi Bank
Name in Arabic
يو اتش إيست من إلينغتون
Land Department project number
2685
Land Department site inspections
7

Schedule

Uh East By Ellington was registered to complete in March 2026, 7 months ago, and is still under construction. Over the last year of inspections it has added about 2.9 points a month. Kept at that rate, the site would reach 100% around December 2027.

0%25%50%75%100%202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

11 June 2026

47%+10 pts

  • Uh East By Ellington construction site, Land Department inspection photo 1, 11 June 2026
  • Uh East By Ellington construction site, Land Department inspection photo 2, 11 June 2026
  • Uh East By Ellington construction site, Land Department inspection photo 3, 11 June 2026
  • Uh East By Ellington construction site, Land Department inspection photo 4, 11 June 2026

5 February 2026

36%+16 pts

  • Uh East By Ellington construction site, Land Department inspection photo 1, 5 February 2026
  • Uh East By Ellington construction site, Land Department inspection photo 2, 5 February 2026
  • Uh East By Ellington construction site, Land Department inspection photo 3, 5 February 2026
  • Uh East By Ellington construction site, Land Department inspection photo 4, 5 February 2026

16 September 2025

21%+7.3 pts

  • Uh East By Ellington construction site, Land Department inspection photo 1, 16 September 2025
  • Uh East By Ellington construction site, Land Department inspection photo 2, 16 September 2025
  • Uh East By Ellington construction site, Land Department inspection photo 3, 16 September 2025
  • Uh East By Ellington construction site, Land Department inspection photo 4, 16 September 2025

10 April 2025

14%+6.4 pts

  • Uh East By Ellington construction site, Land Department inspection photo 1, 10 April 2025
  • Uh East By Ellington construction site, Land Department inspection photo 2, 10 April 2025
  • Uh East By Ellington construction site, Land Department inspection photo 3, 10 April 2025
  • Uh East By Ellington construction site, Land Department inspection photo 4, 10 April 2025

4 July 2024

7.2%+4.7 pts

  • Uh East By Ellington construction site, Land Department inspection photo 1, 4 July 2024
  • Uh East By Ellington construction site, Land Department inspection photo 2, 4 July 2024

14 March 2024

2.5%+2.5 pts

  • Uh East By Ellington construction site, Land Department inspection photo 1, 14 March 2024
  • Uh East By Ellington construction site, Land Department inspection photo 2, 14 March 2024
  • Uh East By Ellington construction site, Land Department inspection photo 3, 14 March 2024
  • Uh East By Ellington construction site, Land Department inspection photo 4, 14 March 2024

31 May 2023

0%

  • Uh East By Ellington construction site, Land Department inspection photo 1, 31 May 2023
  • Uh East By Ellington construction site, Land Department inspection photo 2, 31 May 2023
  • Uh East By Ellington construction site, Land Department inspection photo 3, 31 May 2023
  • Uh East By Ellington construction site, Land Department inspection photo 4, 31 May 2023

All 46 site photos, by inspection date

Context

Jumeirah Lakes Towers has 8 projects under construction, 44% built on average.

Ellington Properties Development has 18 projects under construction in Dubai; 6 have passed their registered completion date.

Own a unit in Uh East By Ellington?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Uh East By Ellington be completed?
The completion date registered with the Dubai Land Department is March 2026. At the pace of its recent inspections the site would reach 100% around December 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Uh East By Ellington is built?
47%, measured at the Land Department site inspection on 11 June 2026. The Land Department engineers have inspected the site 7 times since May 2023.
Is Uh East By Ellington delayed?
Yes. Its registered completion date of March 2026 has passed and the Land Department still lists it as under construction.
Who is building Uh East By Ellington?
The registered developer is Ellington Properties Development. It has 17 other projects under construction in Dubai.
Which bank holds the escrow account for Uh East By Ellington?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.