Wadi Villas By Arista construction progress
The registered completion date for Wadi Villas By Arista in Mohammed Bin Rashid Al Maktoum District 11 is December 2026. At the last site inspection, in September 2026, it was 60% built. The developer is Pbg Real Estate Development.
60%
Built, at the site inspection of 2 September 2026
Running behind its date
- Registered completion date
- December 2026
- Finish at recent pace
- August 2027
- Construction started
- March 2024
- First registered
- March 2024
- Developer
- Pbg Real Estate Development
- Units
- 30
- Escrow bank
- Mashreq Bank
- Name in Arabic
- وادي فيلاس من اريستا
- Project number
- 2967
- Site inspections
- 8
Schedule
Between January 2026 and September 2026 the site added about 3.6 points a month. At that rate it would finish around August 2027, more than three months after its registered date of December 2026.
Site inspections
2 September 2026
60%+12 pts
5 May 2026
49%+16 pts
5 January 2026
32%+12 pts
31 July 2025
21%+10 pts
28 March 2025
10%+6.5 pts
7 January 2025
3.8%+3.5 pts
25 September 2024
0.3%+0.3 pts
19 February 2024
0%
Context
Mohammed Bin Rashid Al Maktoum District 11 has 27 projects under construction, 29% built on average.
Own a unit in Wadi Villas By Arista?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Wadi Villas By Arista handover date?
- The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Wadi Villas By Arista?
- Wadi Villas By Arista was 60% built at the site inspection on 2 September 2026. The site has been inspected 8 times since February 2024. The Land Department took 57 site photos at its inspections.
- Is Wadi Villas By Arista delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building Wadi Villas By Arista?
- The registered developer is Pbg Real Estate Development.
- Which bank holds the escrow account for Wadi Villas By Arista?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The Waterside Villas By EllingtonNearby in Mohammed Bin Rashid Al Maktoum District 11. 45%, Due June 2026, passed.
- The Lakeview Villas By EllingtonNearby in Mohammed Bin Rashid Al Maktoum District 11. 20%, Due August 2026, passed.
- The Woodland ResidencesNearby in Mohammed Bin Rashid Al Maktoum District 11. 75%, Due April 2026, passed.
- The Beachfront Villas By EllingtonNearby in Mohammed Bin Rashid Al Maktoum District 11. 47%, Due August 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.


.jpeg&w=3840&q=75)





.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)