Nineteen Riviera Lagoon construction progress

The registered completion date for Nineteen Riviera Lagoon in Mohammed Bin Rashid Al Maktoum District 11 is February 2027. At the last site inspection, in June 2026, it was 34% built. The developer is Riviera Properties Development.

34%

Built, at the site inspection of 25 June 2026

Running behind its date

Registered completion date
February 2027
Finish at recent pace
March 2028
Construction started
August 2024
First registered
June 2024
Developer
Riviera Properties Development
Units
19
Escrow bank
United Bank Limited
Name in Arabic
تسعة عشر بحيرة ريفييرا
Project number
2980
Site inspections
5

Schedule

Between August 2025 and June 2026 the site added about 3.1 points a month. At that rate it would finish around March 2028, more than three months after its registered date of February 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

25 June 2026

34%+22 pts

  • Nineteen Riviera Lagoon construction site, inspection photo 1, 25 June 2026
  • Nineteen Riviera Lagoon construction site, inspection photo 2, 25 June 2026
  • Nineteen Riviera Lagoon construction site, inspection photo 3, 25 June 2026
  • Nineteen Riviera Lagoon construction site, inspection photo 4, 25 June 2026

26 December 2025

12%+9.7 pts

  • Nineteen Riviera Lagoon construction site, inspection photo 1, 26 December 2025
  • Nineteen Riviera Lagoon construction site, inspection photo 2, 26 December 2025
  • Nineteen Riviera Lagoon construction site, inspection photo 3, 26 December 2025
  • Nineteen Riviera Lagoon construction site, inspection photo 4, 26 December 2025

20 August 2025

2.4%+2.4 pts

  • Nineteen Riviera Lagoon construction site, inspection photo 1, 20 August 2025
  • Nineteen Riviera Lagoon construction site, inspection photo 2, 20 August 2025
  • Nineteen Riviera Lagoon construction site, inspection photo 3, 20 August 2025
  • Nineteen Riviera Lagoon construction site, inspection photo 4, 20 August 2025

29 April 2025

0%+0.0 pts

  • Nineteen Riviera Lagoon construction site, inspection photo 1, 29 April 2025
  • Nineteen Riviera Lagoon construction site, inspection photo 2, 29 April 2025
  • Nineteen Riviera Lagoon construction site, inspection photo 3, 29 April 2025
  • Nineteen Riviera Lagoon construction site, inspection photo 4, 29 April 2025

13 March 2024

0%

  • Nineteen Riviera Lagoon construction site, inspection photo 1, 13 March 2024
  • Nineteen Riviera Lagoon construction site, inspection photo 2, 13 March 2024

All 30 site photos, by inspection date

Context

Mohammed Bin Rashid Al Maktoum District 11 has 27 projects under construction, 29% built on average.

Own a unit in Nineteen Riviera Lagoon?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Nineteen Riviera Lagoon handover date?
The registered completion date is February 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Nineteen Riviera Lagoon?
Nineteen Riviera Lagoon was 34% built at the site inspection on 25 June 2026. The site has been inspected 5 times since March 2024. The Land Department took 30 site photos at its inspections.
Is Nineteen Riviera Lagoon delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2027.
Who is building Nineteen Riviera Lagoon?
The registered developer is Riviera Properties Development.
Which bank holds the escrow account for Nineteen Riviera Lagoon?
United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.