The Woodland Residences construction progress

The Woodland Residences in Mohammed Bin Rashid Al Maktoum District 11 was registered to complete in April 2026 and is still under construction. At the last site inspection, in September 2026, it was 75% built. The developer is A M I S Real Estate Development.

75%

Built, at the site inspection of 2 September 2026

8 months past its registered completion date

Registered completion date
April 2026
Finish at recent pace
February 2027
Construction started
April 2024
First registered
January 2024
Units
30
Escrow bank
United Bank Limited
Name in Arabic
دا وودلاند ريزيدنسز
Project number
2854
Site inspections
7

Schedule

The Woodland Residences was registered to complete in April 2026, 8 months ago, and is still under construction. Over the last year of inspections it has added about 4.5 points a month. Kept at that rate, the site would reach 100% around February 2027.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

2 September 2026

75%+19 pts

  • The Woodland Residences construction site, inspection photo 1, 2 September 2026
  • The Woodland Residences construction site, inspection photo 2, 2 September 2026
  • The Woodland Residences construction site, inspection photo 3, 2 September 2026
  • The Woodland Residences construction site, inspection photo 4, 2 September 2026

22 April 2026

56%+13 pts

  • The Woodland Residences construction site, inspection photo 1, 22 April 2026
  • The Woodland Residences construction site, inspection photo 2, 22 April 2026
  • The Woodland Residences construction site, inspection photo 3, 22 April 2026
  • The Woodland Residences construction site, inspection photo 4, 22 April 2026

15 January 2026

44%+18 pts

  • The Woodland Residences construction site, inspection photo 1, 15 January 2026
  • The Woodland Residences construction site, inspection photo 2, 15 January 2026
  • The Woodland Residences construction site, inspection photo 3, 15 January 2026
  • The Woodland Residences construction site, inspection photo 4, 15 January 2026

1 October 2025

26%+17 pts

  • The Woodland Residences construction site, inspection photo 1, 1 October 2025
  • The Woodland Residences construction site, inspection photo 2, 1 October 2025
  • The Woodland Residences construction site, inspection photo 3, 1 October 2025
  • The Woodland Residences construction site, inspection photo 4, 1 October 2025

28 May 2025

8.7%+5.2 pts

  • The Woodland Residences construction site, inspection photo 1, 28 May 2025
  • The Woodland Residences construction site, inspection photo 2, 28 May 2025
  • The Woodland Residences construction site, inspection photo 3, 28 May 2025
  • The Woodland Residences construction site, inspection photo 4, 28 May 2025

5 December 2024

3.5%+3.5 pts

  • The Woodland Residences construction site, inspection photo 1, 5 December 2024
  • The Woodland Residences construction site, inspection photo 2, 5 December 2024
  • The Woodland Residences construction site, inspection photo 3, 5 December 2024
  • The Woodland Residences construction site, inspection photo 4, 5 December 2024

24 November 2023

0%

  • The Woodland Residences construction site, inspection photo 1, 24 November 2023
  • The Woodland Residences construction site, inspection photo 2, 24 November 2023

All 42 site photos, by inspection date

Context

Mohammed Bin Rashid Al Maktoum District 11 has 27 projects under construction, 29% built on average.

A M I S Real Estate Development has 3 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in The Woodland Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Woodland Residences handover date?
The registered completion date was April 2026, and the register still lists The Woodland Residences as under construction. At the pace of its recent inspections the site would reach 100% around February 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Woodland Residences?
The Woodland Residences was 75% built at the site inspection on 2 September 2026. The site has been inspected 7 times since November 2023. The Land Department took 42 site photos at its inspections.
Is The Woodland Residences delayed?
Yes. Its registered completion date of April 2026 has passed and the project is still listed as under construction.
Who is building The Woodland Residences?
The registered developer is A M I S Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for The Woodland Residences?
United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.