The Portman construction progress

The Portman in Jumeirah Village Circle was registered to complete in September 2025 and is still under construction. At the last site inspection, in August 2026, it was 79% built. The developer is Ellington Properties Development.

79%

Built, at the site inspection of 7 August 2026

14 months past its registered completion date

Registered completion date
September 2025
Finish at recent pace
February 2027
Construction started
December 2022
First registered
January 2023
Units
167
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
بورتمان
Project number
2537
Site inspections
9

Schedule

The Portman was registered to complete in September 2025, 14 months ago, and is still under construction. Over the last year of inspections it has added about 3.3 points a month. Kept at that rate, the site would reach 100% around February 2027.

0%25%50%75%100%2023202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

7 August 2026

79%+22 pts

  • The Portman construction site, inspection photo 1, 7 August 2026
  • The Portman construction site, inspection photo 2, 7 August 2026
  • The Portman construction site, inspection photo 3, 7 August 2026
  • The Portman construction site, inspection photo 4, 7 August 2026

20 April 2026

57%+6.1 pts

  • The Portman construction site, inspection photo 1, 20 April 2026
  • The Portman construction site, inspection photo 2, 20 April 2026
  • The Portman construction site, inspection photo 3, 20 April 2026
  • The Portman construction site, inspection photo 4, 20 April 2026

24 November 2025

51%+14 pts

  • The Portman construction site, inspection photo 1, 24 November 2025
  • The Portman construction site, inspection photo 2, 24 November 2025
  • The Portman construction site, inspection photo 3, 24 November 2025
  • The Portman construction site, inspection photo 4, 24 November 2025

3 June 2025

37%+22 pts

  • The Portman construction site, inspection photo 1, 3 June 2025
  • The Portman construction site, inspection photo 2, 3 June 2025
  • The Portman construction site, inspection photo 3, 3 June 2025
  • The Portman construction site, inspection photo 4, 3 June 2025

29 January 2025

15%+9.6 pts

  • The Portman construction site, inspection photo 1, 29 January 2025
  • The Portman construction site, inspection photo 2, 29 January 2025
  • The Portman construction site, inspection photo 3, 29 January 2025
  • The Portman construction site, inspection photo 4, 29 January 2025

26 June 2024

5.3%+1.1 pts

  • The Portman construction site, inspection photo 1, 26 June 2024
  • The Portman construction site, inspection photo 2, 26 June 2024

30 October 2023

4.2%+4.1 pts

  • The Portman construction site, inspection photo 1, 30 October 2023
  • The Portman construction site, inspection photo 2, 30 October 2023
  • The Portman construction site, inspection photo 3, 30 October 2023
  • The Portman construction site, inspection photo 4, 30 October 2023

9 May 2023

0%+0.0 pts

  • The Portman construction site, inspection photo 1, 9 May 2023
  • The Portman construction site, inspection photo 2, 9 May 2023
  • The Portman construction site, inspection photo 3, 9 May 2023

22 December 2022

0%

  • The Portman construction site, inspection photo 1, 22 December 2022
  • The Portman construction site, inspection photo 2, 22 December 2022
  • The Portman construction site, inspection photo 3, 22 December 2022

All 65 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Ellington Properties Development has 18 projects under construction in Dubai; 6 have passed their registered completion date.

Own a unit in The Portman?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Portman handover date?
The registered completion date was September 2025, and the register still lists The Portman as under construction. At the pace of its recent inspections the site would reach 100% around February 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Portman?
The Portman was 79% built at the site inspection on 7 August 2026. The site has been inspected 9 times since December 2022. The Land Department took 65 site photos at its inspections.
Is The Portman delayed?
Yes. Its registered completion date of September 2025 has passed and the project is still listed as under construction.
Who is building The Portman?
The registered developer is Ellington Properties Development. It has 17 other projects under construction in Dubai.
Which bank holds the escrow account for The Portman?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.