The Portman construction progress

The Portman in Jumeirah Village Circle is 79% built at the Land Department inspection of August 2026. Developer Ellington Properties Development. Completion registered for September 2025.

79%

Built, at the Land Department site inspection of 7 August 2026

12 months past its registered completion date

Completion date (Land Department)
September 2025
Finish at recent pace
February 2027
Construction started
December 2022
Registered with the Land Department
January 2023
Units
167
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
بورتمان
Land Department project number
2537
Land Department site inspections
9

Schedule

The Portman was registered to complete in September 2025, 12 months ago, and is still under construction. Over the last year of inspections it has added about 3.3 points a month. Kept at that rate, the site would reach 100% around February 2027.

0%25%50%75%100%2023202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

7 August 2026

79%+22 pts

  • The Portman construction site, Land Department inspection photo 1, 7 August 2026
  • The Portman construction site, Land Department inspection photo 2, 7 August 2026
  • The Portman construction site, Land Department inspection photo 3, 7 August 2026
  • The Portman construction site, Land Department inspection photo 4, 7 August 2026

20 April 2026

57%+6.1 pts

  • The Portman construction site, Land Department inspection photo 1, 20 April 2026
  • The Portman construction site, Land Department inspection photo 2, 20 April 2026
  • The Portman construction site, Land Department inspection photo 3, 20 April 2026
  • The Portman construction site, Land Department inspection photo 4, 20 April 2026

24 November 2025

51%+14 pts

  • The Portman construction site, Land Department inspection photo 1, 24 November 2025
  • The Portman construction site, Land Department inspection photo 2, 24 November 2025
  • The Portman construction site, Land Department inspection photo 3, 24 November 2025
  • The Portman construction site, Land Department inspection photo 4, 24 November 2025

3 June 2025

37%+22 pts

  • The Portman construction site, Land Department inspection photo 1, 3 June 2025
  • The Portman construction site, Land Department inspection photo 2, 3 June 2025
  • The Portman construction site, Land Department inspection photo 3, 3 June 2025
  • The Portman construction site, Land Department inspection photo 4, 3 June 2025

29 January 2025

15%+9.6 pts

  • The Portman construction site, Land Department inspection photo 1, 29 January 2025
  • The Portman construction site, Land Department inspection photo 2, 29 January 2025
  • The Portman construction site, Land Department inspection photo 3, 29 January 2025
  • The Portman construction site, Land Department inspection photo 4, 29 January 2025

26 June 2024

5.3%+1.1 pts

  • The Portman construction site, Land Department inspection photo 1, 26 June 2024
  • The Portman construction site, Land Department inspection photo 2, 26 June 2024

30 October 2023

4.2%+4.1 pts

  • The Portman construction site, Land Department inspection photo 1, 30 October 2023
  • The Portman construction site, Land Department inspection photo 2, 30 October 2023
  • The Portman construction site, Land Department inspection photo 3, 30 October 2023
  • The Portman construction site, Land Department inspection photo 4, 30 October 2023

9 May 2023

0%+0.0 pts

  • The Portman construction site, Land Department inspection photo 1, 9 May 2023
  • The Portman construction site, Land Department inspection photo 2, 9 May 2023
  • The Portman construction site, Land Department inspection photo 3, 9 May 2023

22 December 2022

0%

  • The Portman construction site, Land Department inspection photo 1, 22 December 2022
  • The Portman construction site, Land Department inspection photo 2, 22 December 2022
  • The Portman construction site, Land Department inspection photo 3, 22 December 2022

All 65 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average.

Ellington Properties Development has 18 projects under construction in Dubai; 6 have passed their registered completion date.

Own a unit in The Portman?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will The Portman be completed?
The completion date registered with the Dubai Land Department is September 2025. At the pace of its recent inspections the site would reach 100% around February 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of The Portman is built?
79%, measured at the Land Department site inspection on 7 August 2026. The Land Department engineers have inspected the site 9 times since December 2022.
Is The Portman delayed?
Yes. Its registered completion date of September 2025 has passed and the Land Department still lists it as under construction.
Who is building The Portman?
The registered developer is Ellington Properties Development. It has 17 other projects under construction in Dubai.
Which bank holds the escrow account for The Portman?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.