Uh West By Ellington construction progress
Uh West By Ellington in Jumeirah Lakes Towers is 71% built at the Land Department inspection of June 2026. Developer Ellington Properties Development. Completion registered for March 2026.
71%
Built, at the Land Department site inspection of 11 June 2026
7 months past its registered completion date
- Completion date (Land Department)
- March 2026
- Finish at recent pace
- January 2027
- Construction started
- May 2023
- Registered with the Land Department
- August 2023
- Developer
- Ellington Properties Development
- Community
- Jumeirah Lakes Towers
- Units
- 381
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- يو اتش ويست من إلينغتون
- Land Department project number
- 2684
- Land Department site inspections
- 7
Schedule
Uh West By Ellington was registered to complete in March 2026, 7 months ago, and is still under construction. Over the last year of inspections it has added about 3.7 points a month. Kept at that rate, the site would reach 100% around January 2027.
Site inspections
11 June 2026
71%+12 pts
10 February 2026
60%+23 pts
30 August 2025
36%+11 pts
10 April 2025
26%+15 pts
4 July 2024
11%+4.1 pts
14 March 2024
6.8%+6.8 pts
31 May 2023
0%
Context
Jumeirah Lakes Towers has 8 projects under construction, 44% built on average.
Ellington Properties Development has 18 projects under construction in Dubai; 6 have passed their registered completion date.
Own a unit in Uh West By Ellington?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Uh West By Ellington be completed?
- The completion date registered with the Dubai Land Department is March 2026. At the pace of its recent inspections the site would reach 100% around January 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Uh West By Ellington is built?
- 71%, measured at the Land Department site inspection on 11 June 2026. The Land Department engineers have inspected the site 7 times since May 2023.
- Is Uh West By Ellington delayed?
- Yes. Its registered completion date of March 2026 has passed and the Land Department still lists it as under construction.
- Who is building Uh West By Ellington?
- The registered developer is Ellington Properties Development. It has 17 other projects under construction in Dubai.
- Which bank holds the escrow account for Uh West By Ellington?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The PortmanAlso by Ellington Properties Development. 79%, Due September 2025, passed.
- The HighburyAlso by Ellington Properties Development. 80%.
- Uh East By EllingtonAlso by Ellington Properties Development. 47%, Due March 2026, passed.
- The Waterside Villas By EllingtonAlso by Ellington Properties Development. 32%, Due June 2026, passed.
- Vue Du LacNearby in Jumeirah Lakes Towers. 0%, Due December 2026.
- Viewz 1 By DanubeNearby in Jumeirah Lakes Towers. 50%, Due June 2026, passed.
- Viewz 2 By DanubeNearby in Jumeirah Lakes Towers. 50%, Due June 2026, passed.
- Verde By SobhaNearby in Jumeirah Lakes Towers. 85%, Due June 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.