Uh West By Ellington construction progress

Uh West By Ellington in Jumeirah Lakes Towers was registered to complete in March 2026 and is still under construction. At the last site inspection, in October 2026, it was 84% built. The developer is Ellington Properties Development.

84%

Built, at the site inspection of 27 October 2026

9 months past its registered completion date

Registered completion date
March 2026
Finish at recent pace
April 2027
Construction started
May 2023
First registered
August 2023
Units
381
Escrow bank
First Abu Dhabi Bank
Name in Arabic
يو اتش ويست من إلينغتون
Project number
2684
Site inspections
8

Schedule

Uh West By Ellington was registered to complete in March 2026, 9 months ago, and is still under construction. Over the last year of inspections it has added about 2.8 points a month. Kept at that rate, the site would reach 100% around April 2027.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

27 October 2026

84%+12 pts

  • Uh West By Ellington construction site, inspection photo 1, 27 October 2026
  • Uh West By Ellington construction site, inspection photo 2, 27 October 2026
  • Uh West By Ellington construction site, inspection photo 3, 27 October 2026
  • Uh West By Ellington construction site, inspection photo 4, 27 October 2026

11 June 2026

71%+12 pts

  • Uh West By Ellington construction site, inspection photo 1, 11 June 2026
  • Uh West By Ellington construction site, inspection photo 2, 11 June 2026
  • Uh West By Ellington construction site, inspection photo 3, 11 June 2026
  • Uh West By Ellington construction site, inspection photo 4, 11 June 2026

10 February 2026

60%+23 pts

  • Uh West By Ellington construction site, inspection photo 1, 10 February 2026
  • Uh West By Ellington construction site, inspection photo 2, 10 February 2026
  • Uh West By Ellington construction site, inspection photo 3, 10 February 2026
  • Uh West By Ellington construction site, inspection photo 4, 10 February 2026

30 August 2025

36%+11 pts

  • Uh West By Ellington construction site, inspection photo 1, 30 August 2025
  • Uh West By Ellington construction site, inspection photo 2, 30 August 2025
  • Uh West By Ellington construction site, inspection photo 3, 30 August 2025
  • Uh West By Ellington construction site, inspection photo 4, 30 August 2025

10 April 2025

26%+15 pts

  • Uh West By Ellington construction site, inspection photo 1, 10 April 2025
  • Uh West By Ellington construction site, inspection photo 2, 10 April 2025
  • Uh West By Ellington construction site, inspection photo 3, 10 April 2025
  • Uh West By Ellington construction site, inspection photo 4, 10 April 2025

4 July 2024

11%+4.1 pts

  • Uh West By Ellington construction site, inspection photo 1, 4 July 2024
  • Uh West By Ellington construction site, inspection photo 2, 4 July 2024
  • Uh West By Ellington construction site, inspection photo 3, 4 July 2024
  • Uh West By Ellington construction site, inspection photo 4, 4 July 2024

14 March 2024

6.8%+6.8 pts

  • Uh West By Ellington construction site, inspection photo 1, 14 March 2024
  • Uh West By Ellington construction site, inspection photo 2, 14 March 2024
  • Uh West By Ellington construction site, inspection photo 3, 14 March 2024
  • Uh West By Ellington construction site, inspection photo 4, 14 March 2024

31 May 2023

0%

  • Uh West By Ellington construction site, inspection photo 1, 31 May 2023
  • Uh West By Ellington construction site, inspection photo 2, 31 May 2023
  • Uh West By Ellington construction site, inspection photo 3, 31 May 2023
  • Uh West By Ellington construction site, inspection photo 4, 31 May 2023

All 67 site photos, by inspection date

Context

Jumeirah Lakes Towers has 8 projects under construction, 51% built on average.

Ellington Properties Development has 18 projects under construction in Dubai; 6 have passed their registered completion date.

Own a unit in Uh West By Ellington?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Uh West By Ellington handover date?
The registered completion date was March 2026, and the register still lists Uh West By Ellington as under construction. At the pace of its recent inspections the site would reach 100% around April 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Uh West By Ellington?
Uh West By Ellington was 84% built at the site inspection on 27 October 2026. The site has been inspected 8 times since May 2023. The Land Department took 67 site photos at its inspections.
Is Uh West By Ellington delayed?
Yes. Its registered completion date of March 2026 has passed and the project is still listed as under construction.
Who is building Uh West By Ellington?
The registered developer is Ellington Properties Development. It has 17 other projects under construction in Dubai.
Which bank holds the escrow account for Uh West By Ellington?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.