43 photos from 7 site inspections, newest first. The percentage is how much of The Waterside Villas By Ellington was built on the day of each visit.

26 October 202645% built

9 June 202632% built

2 February 202617% built

16 October 20257.0% built

4 June 20252.5% built

2 July 20240.1% built

10 July 20230% built

Back to The Waterside Villas By Ellington construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.