Lua Residences construction progress
Lua Residences in Mohammed Bin Rashid Al Maktoum District 11 was registered to complete in March 2026 and is still under construction. At the last site inspection, in September 2026, it was 64% built. The developer is Swank Real Estate Development.
64%
Built, at the site inspection of 22 September 2026
8 months past its registered completion date
- Registered completion date
- March 2026
- Finish at recent pace
- January 2028
- Construction started
- May 2024
- First registered
- May 2024
- Developer
- Swank Real Estate Development
- Units
- 37
- Escrow bank
- Emirates Islamic Bank
- Name in Arabic
- مساكن لوا
- Project number
- 2974
- Site inspections
- 7
Schedule
Lua Residences was registered to complete in March 2026, 8 months ago, and is still under construction. Over the last year of inspections it has added about 2.2 points a month. Kept at that rate, the site would reach 100% around January 2028.
Site inspections
22 September 2026
64%+9.2 pts
16 June 2026
55%+12 pts
3 December 2025
43%+12 pts
19 June 2025
31%+12 pts
16 April 2025
19%+14 pts
21 December 2024
5.3%+5.3 pts
11 March 2024
0%
Context
Mohammed Bin Rashid Al Maktoum District 11 has 27 projects under construction, 29% built on average.
Swank Real Estate Development has 2 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Lua Residences?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Lua Residences handover date?
- The registered completion date was March 2026, and the register still lists Lua Residences as under construction. At the pace of its recent inspections the site would reach 100% around January 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Lua Residences?
- Lua Residences was 64% built at the site inspection on 22 September 2026. The site has been inspected 7 times since March 2024. The Land Department took 47 site photos at its inspections.
- Is Lua Residences delayed?
- Yes. Its registered completion date of March 2026 has passed and the project is still listed as under construction.
- Who is building Lua Residences?
- The registered developer is Swank Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Lua Residences?
- Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Selora ResidencesAlso by Swank Real Estate Development. 3.5%, Due April 2027.
- The Waterside Villas By EllingtonNearby in Mohammed Bin Rashid Al Maktoum District 11. 45%, Due June 2026, passed.
- The Lakeview Villas By EllingtonNearby in Mohammed Bin Rashid Al Maktoum District 11. 20%, Due August 2026, passed.
- The Woodland ResidencesNearby in Mohammed Bin Rashid Al Maktoum District 11. 75%, Due April 2026, passed.
- The Beachfront Villas By EllingtonNearby in Mohammed Bin Rashid Al Maktoum District 11. 47%, Due August 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)












.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)