Lua Residences construction progress

Lua Residences in Mohammed Bin Rashid Al Maktoum District 11 was registered to complete in March 2026 and is still under construction. At the last site inspection, in September 2026, it was 64% built. The developer is Swank Real Estate Development.

64%

Built, at the site inspection of 22 September 2026

8 months past its registered completion date

Registered completion date
March 2026
Finish at recent pace
January 2028
Construction started
May 2024
First registered
May 2024
Developer
Swank Real Estate Development
Units
37
Escrow bank
Emirates Islamic Bank
Name in Arabic
مساكن لوا
Project number
2974
Site inspections
7

Schedule

Lua Residences was registered to complete in March 2026, 8 months ago, and is still under construction. Over the last year of inspections it has added about 2.2 points a month. Kept at that rate, the site would reach 100% around January 2028.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

22 September 2026

64%+9.2 pts

  • Lua Residences construction site, inspection photo 1, 22 September 2026
  • Lua Residences construction site, inspection photo 2, 22 September 2026
  • Lua Residences construction site, inspection photo 3, 22 September 2026
  • Lua Residences construction site, inspection photo 4, 22 September 2026

16 June 2026

55%+12 pts

  • Lua Residences construction site, inspection photo 1, 16 June 2026
  • Lua Residences construction site, inspection photo 2, 16 June 2026
  • Lua Residences construction site, inspection photo 3, 16 June 2026
  • Lua Residences construction site, inspection photo 4, 16 June 2026

3 December 2025

43%+12 pts

  • Lua Residences construction site, inspection photo 1, 3 December 2025
  • Lua Residences construction site, inspection photo 2, 3 December 2025
  • Lua Residences construction site, inspection photo 3, 3 December 2025
  • Lua Residences construction site, inspection photo 4, 3 December 2025

19 June 2025

31%+12 pts

  • Lua Residences construction site, inspection photo 1, 19 June 2025
  • Lua Residences construction site, inspection photo 2, 19 June 2025
  • Lua Residences construction site, inspection photo 3, 19 June 2025
  • Lua Residences construction site, inspection photo 4, 19 June 2025

16 April 2025

19%+14 pts

  • Lua Residences construction site, inspection photo 1, 16 April 2025
  • Lua Residences construction site, inspection photo 2, 16 April 2025
  • Lua Residences construction site, inspection photo 3, 16 April 2025
  • Lua Residences construction site, inspection photo 4, 16 April 2025

21 December 2024

5.3%+5.3 pts

  • Lua Residences construction site, inspection photo 1, 21 December 2024
  • Lua Residences construction site, inspection photo 2, 21 December 2024
  • Lua Residences construction site, inspection photo 3, 21 December 2024
  • Lua Residences construction site, inspection photo 4, 21 December 2024

11 March 2024

0%

  • Lua Residences construction site, inspection photo 1, 11 March 2024
  • Lua Residences construction site, inspection photo 2, 11 March 2024
  • Lua Residences construction site, inspection photo 3, 11 March 2024

All 47 site photos, by inspection date

Context

Mohammed Bin Rashid Al Maktoum District 11 has 27 projects under construction, 29% built on average.

Swank Real Estate Development has 2 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Lua Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Lua Residences handover date?
The registered completion date was March 2026, and the register still lists Lua Residences as under construction. At the pace of its recent inspections the site would reach 100% around January 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Lua Residences?
Lua Residences was 64% built at the site inspection on 22 September 2026. The site has been inspected 7 times since March 2024. The Land Department took 47 site photos at its inspections.
Is Lua Residences delayed?
Yes. Its registered completion date of March 2026 has passed and the project is still listed as under construction.
Who is building Lua Residences?
The registered developer is Swank Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Lua Residences?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.