Skip to content

Azizi Greenfield construction progress

The register lists Azizi Greenfield in Meydan Racecourse Community as complete, with a registered completion date of March 2024. Its last site inspection on record was in March 2024. The developer is Azizi Developments.

100%

Built, at the site inspection of 8 March 2024

Construction complete

Registered completion date
March 2024
Construction started
February 2018
First registered
March 2018
Units
102
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
عزيزي غرينفيلد
Project number
2035
Site inspections
6

Schedule

The register lists Azizi Greenfield as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201920212023
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

8 March 2024

100%+59 pts

  • Azizi Greenfield construction site, inspection photo 1, 8 March 2024
  • Azizi Greenfield construction site, inspection photo 2, 8 March 2024
  • Azizi Greenfield construction site, inspection photo 3, 8 March 2024
  • Azizi Greenfield construction site, inspection photo 4, 8 March 2024

29 March 2023

41%+8.4 pts

  • Azizi Greenfield construction site, inspection photo 1, 29 March 2023
  • Azizi Greenfield construction site, inspection photo 2, 29 March 2023
  • Azizi Greenfield construction site, inspection photo 3, 29 March 2023
  • Azizi Greenfield construction site, inspection photo 4, 29 March 2023

26 October 2022

32%+2.0 pts

  • Azizi Greenfield construction site, inspection photo 1, 26 October 2022
  • Azizi Greenfield construction site, inspection photo 2, 26 October 2022
  • Azizi Greenfield construction site, inspection photo 3, 26 October 2022
  • Azizi Greenfield construction site, inspection photo 4, 26 October 2022

4 April 2022

30%+13 pts

  • Azizi Greenfield construction site, inspection photo 1, 4 April 2022
  • Azizi Greenfield construction site, inspection photo 2, 4 April 2022
  • Azizi Greenfield construction site, inspection photo 3, 4 April 2022
  • Azizi Greenfield construction site, inspection photo 4, 4 April 2022

10 October 2021

17%+16 pts

  • Azizi Greenfield construction site, inspection photo 1, 10 October 2021
  • Azizi Greenfield construction site, inspection photo 2, 10 October 2021
  • Azizi Greenfield construction site, inspection photo 3, 10 October 2021
  • Azizi Greenfield construction site, inspection photo 4, 10 October 2021

28 February 2021

1.0%

  • Azizi Greenfield construction site, inspection photo 1, 28 February 2021
  • Azizi Greenfield construction site, inspection photo 2, 28 February 2021
  • Azizi Greenfield construction site, inspection photo 3, 28 February 2021
  • Azizi Greenfield construction site, inspection photo 4, 28 February 2021

All 44 site photos, by inspection date

Context

Meydan Racecourse Community has 9 projects under construction, 31% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi Greenfield?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Azizi Greenfield handover date?
Construction of Azizi Greenfield is recorded as complete, with a registered completion date of March 2024. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Azizi Greenfield?
Azizi Greenfield was 100% built at the site inspection on 8 March 2024. The site has been inspected 6 times since February 2021. The Land Department took 44 site photos at its inspections.
Is Azizi Greenfield delayed?
The register lists construction as complete.
Who is building Azizi Greenfield?
The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Greenfield?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.