Azizi Greenfield construction progress
The register lists Azizi Greenfield in Meydan Racecourse Community as complete, with a registered completion date of March 2024. Its last site inspection on record was in March 2024. The developer is Azizi Developments.
100%
Built, at the site inspection of 8 March 2024
Construction complete
- Registered completion date
- March 2024
- Construction started
- February 2018
- First registered
- March 2018
- Developer
- Azizi Developments
- Community
- Meydan Racecourse Community
- Units
- 102
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- عزيزي غرينفيلد
- Project number
- 2035
- Site inspections
- 6
Schedule
The register lists Azizi Greenfield as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
8 March 2024
100%+59 pts
29 March 2023
41%+8.4 pts
26 October 2022
32%+2.0 pts
4 April 2022
30%+13 pts
10 October 2021
17%+16 pts
28 February 2021
1.0%
Context
Meydan Racecourse Community has 9 projects under construction, 31% built on average.
Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.
Own a unit in Azizi Greenfield?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Azizi Greenfield handover date?
- Construction of Azizi Greenfield is recorded as complete, with a registered completion date of March 2024. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Azizi Greenfield?
- Azizi Greenfield was 100% built at the site inspection on 8 March 2024. The site has been inspected 6 times since February 2021. The Land Department took 44 site photos at its inspections.
- Is Azizi Greenfield delayed?
- The register lists construction as complete.
- Who is building Azizi Greenfield?
- The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
- Which bank holds the escrow account for Azizi Greenfield?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Azizi GrandAlso by Azizi Developments. 82%, Due February 2025, passed.
- Azizi Riviera ReveAlso by Azizi Developments. 77%, Due February 2025, passed.
- Azizi Venice 3Also by Azizi Developments. 76%, Due December 2025, passed.
- Azizi Venice 4Also by Azizi Developments. 62%, Due December 2025, passed.
- Royal ManorNearby in Meydan Racecourse Community. 78%, Due December 2018, passed.
- Tonino Lamborghini ResidencesNearby in Meydan Racecourse Community. 60%, Due December 2026.
- Emerge ResidencesNearby in Meydan Racecourse Community. 21%, Due November 2027.
- Mews MansionsNearby in Meydan Racecourse Community. 56%, Due December 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.

.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)

.jpg&w=3840&q=75)

.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)

.jpg&w=3840&q=75)
.jpg&w=3840&q=75)