Royal Manor construction progress

Royal Manor in Meydan Racecourse Community is 78% built at the Land Department inspection of September 2018. Developer Blue Coast Real Estate Development. Completion registered for December 2018.

78%

Built, at the Land Department site inspection of 9 September 2018

94 months past its registered completion date

Completion date (Land Department)
December 2018
Finish at recent pace
March 2019
Construction started
September 2016
Registered with the Land Department
May 2017
Developer
Blue Coast Real Estate Development
Units
36
Escrow bank
Dubai Islamic Bank
Name in Arabic
رويال مانور
Land Department project number
1855
Land Department site inspections
3

Schedule

Royal Manor was registered to complete in December 2018, 94 months ago, and is still under construction. Over the last year of inspections it has added about 3.6 points a month. Kept at that rate, the site would reach 100% around March 2019.

0%25%50%75%100%20172018
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

9 September 2018

78%+31 pts

  • Royal Manor construction site, Land Department inspection photo 1, 9 September 2018
  • Royal Manor construction site, Land Department inspection photo 2, 9 September 2018
  • Royal Manor construction site, Land Department inspection photo 3, 9 September 2018
  • Royal Manor construction site, Land Department inspection photo 4, 9 September 2018

26 December 2017

47%+9.8 pts

  • Royal Manor construction site, Land Department inspection photo 1, 26 December 2017
  • Royal Manor construction site, Land Department inspection photo 2, 26 December 2017
  • Royal Manor construction site, Land Department inspection photo 3, 26 December 2017
  • Royal Manor construction site, Land Department inspection photo 4, 26 December 2017

22 August 2017

37%

  • Royal Manor construction site, Land Department inspection photo 1, 22 August 2017
  • Royal Manor construction site, Land Department inspection photo 2, 22 August 2017
  • Royal Manor construction site, Land Department inspection photo 3, 22 August 2017
  • Royal Manor construction site, Land Department inspection photo 4, 22 August 2017

All 28 site photos, by inspection date

Context

Meydan Racecourse Community has 9 projects under construction, 31% built on average.

Own a unit in Royal Manor?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Royal Manor be completed?
The completion date registered with the Dubai Land Department is December 2018. At the pace of its recent inspections the site would reach 100% around March 2019. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Royal Manor is built?
78%, measured at the Land Department site inspection on 9 September 2018. The Land Department engineers have inspected the site 3 times since August 2017.
Is Royal Manor delayed?
Yes. Its registered completion date of December 2018 has passed and the Land Department still lists it as under construction.
Who is building Royal Manor?
The registered developer is Blue Coast Real Estate Development.
Which bank holds the escrow account for Royal Manor?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.