Royal Manor construction progress
Royal Manor in Meydan Racecourse Community is 78% built at the Land Department inspection of September 2018. Developer Blue Coast Real Estate Development. Completion registered for December 2018.
78%
Built, at the Land Department site inspection of 9 September 2018
94 months past its registered completion date
- Completion date (Land Department)
- December 2018
- Finish at recent pace
- March 2019
- Construction started
- September 2016
- Registered with the Land Department
- May 2017
- Developer
- Blue Coast Real Estate Development
- Community
- Meydan Racecourse Community
- Units
- 36
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- رويال مانور
- Land Department project number
- 1855
- Land Department site inspections
- 3
Schedule
Royal Manor was registered to complete in December 2018, 94 months ago, and is still under construction. Over the last year of inspections it has added about 3.6 points a month. Kept at that rate, the site would reach 100% around March 2019.
Site inspections
9 September 2018
78%+31 pts
26 December 2017
47%+9.8 pts
22 August 2017
37%
Context
Meydan Racecourse Community has 9 projects under construction, 31% built on average.
Own a unit in Royal Manor?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Royal Manor be completed?
- The completion date registered with the Dubai Land Department is December 2018. At the pace of its recent inspections the site would reach 100% around March 2019. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Royal Manor is built?
- 78%, measured at the Land Department site inspection on 9 September 2018. The Land Department engineers have inspected the site 3 times since August 2017.
- Is Royal Manor delayed?
- Yes. Its registered completion date of December 2018 has passed and the Land Department still lists it as under construction.
- Who is building Royal Manor?
- The registered developer is Blue Coast Real Estate Development.
- Which bank holds the escrow account for Royal Manor?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Tonino Lamborghini ResidencesNearby in Meydan Racecourse Community. 60%, Due December 2026.
- Emerge ResidencesNearby in Meydan Racecourse Community. 21%, Due November 2027.
- Mews MansionsNearby in Meydan Racecourse Community. 56%, Due December 2025, passed.
- Woodland CrestNearby in Meydan Racecourse Community. 1.4%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.