Royal Manor construction progress
Royal Manor in Meydan Racecourse Community was registered to complete in December 2018 and is still under construction. At the last site inspection, in September 2018, it was 78% built. The developer is Blue Coast Real Estate Development.
78%
Built, at the site inspection of 9 September 2018
95 months past its registered completion date
- Registered completion date
- December 2018
- Finish at recent pace
- March 2019
- Construction started
- September 2016
- First registered
- May 2017
- Developer
- Blue Coast Real Estate Development
- Community
- Meydan Racecourse Community
- Units
- 36
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- رويال مانور
- Project number
- 1855
- Site inspections
- 3
Schedule
Royal Manor was registered to complete in December 2018, 95 months ago, and is still under construction. Over the last year of inspections it has added about 3.6 points a month. Kept at that rate, the site would reach 100% around March 2019.
Site inspections
9 September 2018
78%+31 pts
26 December 2017
47%+9.8 pts
22 August 2017
37%
Context
Meydan Racecourse Community has 9 projects under construction, 31% built on average.
Own a unit in Royal Manor?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Royal Manor handover date?
- The registered completion date was December 2018, and the register still lists Royal Manor as under construction. At the pace of its recent inspections the site would reach 100% around March 2019. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Royal Manor?
- Royal Manor was 78% built at the site inspection on 9 September 2018. The site has been inspected 3 times since August 2017. The Land Department took 28 site photos at its inspections.
- Is Royal Manor delayed?
- Yes. Its registered completion date of December 2018 has passed and the project is still listed as under construction.
- Who is building Royal Manor?
- The registered developer is Blue Coast Real Estate Development.
- Which bank holds the escrow account for Royal Manor?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Tonino Lamborghini ResidencesNearby in Meydan Racecourse Community. 60%, Due December 2026.
- Emerge ResidencesNearby in Meydan Racecourse Community. 21%, Due November 2027.
- Mews MansionsNearby in Meydan Racecourse Community. 56%, Due December 2025, passed.
- Woodland CrestNearby in Meydan Racecourse Community. 1.4%, Due June 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.