Royal Manor construction progress

Royal Manor in Meydan Racecourse Community was registered to complete in December 2018 and is still under construction. At the last site inspection, in September 2018, it was 78% built. The developer is Blue Coast Real Estate Development.

78%

Built, at the site inspection of 9 September 2018

95 months past its registered completion date

Registered completion date
December 2018
Finish at recent pace
March 2019
Construction started
September 2016
First registered
May 2017
Developer
Blue Coast Real Estate Development
Units
36
Escrow bank
Dubai Islamic Bank
Name in Arabic
رويال مانور
Project number
1855
Site inspections
3

Schedule

Royal Manor was registered to complete in December 2018, 95 months ago, and is still under construction. Over the last year of inspections it has added about 3.6 points a month. Kept at that rate, the site would reach 100% around March 2019.

0%25%50%75%100%20172018
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

9 September 2018

78%+31 pts

  • Royal Manor construction site, inspection photo 1, 9 September 2018
  • Royal Manor construction site, inspection photo 2, 9 September 2018
  • Royal Manor construction site, inspection photo 3, 9 September 2018
  • Royal Manor construction site, inspection photo 4, 9 September 2018

26 December 2017

47%+9.8 pts

  • Royal Manor construction site, inspection photo 1, 26 December 2017
  • Royal Manor construction site, inspection photo 2, 26 December 2017
  • Royal Manor construction site, inspection photo 3, 26 December 2017
  • Royal Manor construction site, inspection photo 4, 26 December 2017

22 August 2017

37%

  • Royal Manor construction site, inspection photo 1, 22 August 2017
  • Royal Manor construction site, inspection photo 2, 22 August 2017
  • Royal Manor construction site, inspection photo 3, 22 August 2017
  • Royal Manor construction site, inspection photo 4, 22 August 2017

All 28 site photos, by inspection date

Context

Meydan Racecourse Community has 9 projects under construction, 31% built on average.

Own a unit in Royal Manor?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Royal Manor handover date?
The registered completion date was December 2018, and the register still lists Royal Manor as under construction. At the pace of its recent inspections the site would reach 100% around March 2019. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Royal Manor?
Royal Manor was 78% built at the site inspection on 9 September 2018. The site has been inspected 3 times since August 2017. The Land Department took 28 site photos at its inspections.
Is Royal Manor delayed?
Yes. Its registered completion date of December 2018 has passed and the project is still listed as under construction.
Who is building Royal Manor?
The registered developer is Blue Coast Real Estate Development.
Which bank holds the escrow account for Royal Manor?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.