Skip to content

Emerge Residences construction progress

The registered completion date for Emerge Residences in Meydan Racecourse Community is November 2027. At the last site inspection, in September 2026, it was 21% built. The developer is N A A S Real Estate Development.

21%

Built, at the site inspection of 2 September 2026

Running behind its date

Registered completion date
November 2027
Finish at recent pace
April 2028
Construction started
August 2025
First registered
August 2025
Developer
N A A S Real Estate Development
Units
82
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
Emerge Residences
Project number
3363
Site inspections
3

Schedule

Between April 2026 and September 2026 the site added about 4.1 points a month. At that rate it would finish around April 2028, more than three months after its registered date of November 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

2 September 2026

21%+19 pts

  • Emerge Residences construction site, inspection photo 1, 2 September 2026
  • Emerge Residences construction site, inspection photo 2, 2 September 2026
  • Emerge Residences construction site, inspection photo 3, 2 September 2026
  • Emerge Residences construction site, inspection photo 4, 2 September 2026

14 April 2026

2.4%+2.4 pts

  • Emerge Residences construction site, inspection photo 1, 14 April 2026
  • Emerge Residences construction site, inspection photo 2, 14 April 2026
  • Emerge Residences construction site, inspection photo 3, 14 April 2026
  • Emerge Residences construction site, inspection photo 4, 14 April 2026

27 November 2024

0%

  • Emerge Residences construction site, inspection photo 1, 27 November 2024
  • Emerge Residences construction site, inspection photo 2, 27 November 2024

All 13 site photos, by inspection date

Context

Meydan Racecourse Community has 9 projects under construction, 31% built on average.

Own a unit in Emerge Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Emerge Residences handover date?
The registered completion date is November 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Emerge Residences?
Emerge Residences was 21% built at the site inspection on 2 September 2026. The site has been inspected 3 times since November 2024. The Land Department took 13 site photos at its inspections.
Is Emerge Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2027.
Who is building Emerge Residences?
The registered developer is N A A S Real Estate Development.
Which bank holds the escrow account for Emerge Residences?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.