Skip to content

Emerge Residences construction progress

Emerge Residences in Meydan Racecourse Community is 21% built at the Land Department inspection of September 2026. Developer N A A S Real Estate Development. Completion registered for November 2027.

21%

Built, at the Land Department site inspection of 2 September 2026

Running behind its date

Completion date (Land Department)
November 2027
Finish at recent pace
April 2028
Construction started
August 2025
Registered with the Land Department
August 2025
Developer
N A A S Real Estate Development
Units
82
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
Emerge Residences
Land Department project number
3363
Land Department site inspections
3

Schedule

Between April 2026 and September 2026 the site added about 4.1 points a month. At that rate it would finish around April 2028, more than three months after the November 2027 date registered with the Land Department.

0%25%50%75%100%202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

2 September 2026

21%+19 pts

  • Emerge Residences construction site, Land Department inspection photo 1, 2 September 2026
  • Emerge Residences construction site, Land Department inspection photo 2, 2 September 2026
  • Emerge Residences construction site, Land Department inspection photo 3, 2 September 2026
  • Emerge Residences construction site, Land Department inspection photo 4, 2 September 2026

14 April 2026

2.4%+2.4 pts

  • Emerge Residences construction site, Land Department inspection photo 1, 14 April 2026
  • Emerge Residences construction site, Land Department inspection photo 2, 14 April 2026
  • Emerge Residences construction site, Land Department inspection photo 3, 14 April 2026
  • Emerge Residences construction site, Land Department inspection photo 4, 14 April 2026

27 November 2024

0%

  • Emerge Residences construction site, Land Department inspection photo 1, 27 November 2024
  • Emerge Residences construction site, Land Department inspection photo 2, 27 November 2024

All 13 site photos, by inspection date

Context

Meydan Racecourse Community has 9 projects under construction, 31% built on average.

Own a unit in Emerge Residences?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Emerge Residences be completed?
The completion date registered with the Dubai Land Department is November 2027. At the pace of its recent inspections the site would reach 100% around April 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Emerge Residences is built?
21%, measured at the Land Department site inspection on 2 September 2026. The Land Department engineers have inspected the site 3 times since November 2024.
Is Emerge Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2027.
Who is building Emerge Residences?
The registered developer is N A A S Real Estate Development.
Which bank holds the escrow account for Emerge Residences?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.