Emerge Residences construction progress
The registered completion date for Emerge Residences in Meydan Racecourse Community is November 2027. At the last site inspection, in September 2026, it was 21% built. The developer is N A A S Real Estate Development.
21%
Built, at the site inspection of 2 September 2026
Running behind its date
- Registered completion date
- November 2027
- Finish at recent pace
- April 2028
- Construction started
- August 2025
- First registered
- August 2025
- Developer
- N A A S Real Estate Development
- Community
- Meydan Racecourse Community
- Units
- 82
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- Emerge Residences
- Project number
- 3363
- Site inspections
- 3
Schedule
Between April 2026 and September 2026 the site added about 4.1 points a month. At that rate it would finish around April 2028, more than three months after its registered date of November 2027.
Site inspections
2 September 2026
21%+19 pts
14 April 2026
2.4%+2.4 pts
27 November 2024
0%
Context
Meydan Racecourse Community has 9 projects under construction, 31% built on average.
Own a unit in Emerge Residences?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Emerge Residences handover date?
- The registered completion date is November 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Emerge Residences?
- Emerge Residences was 21% built at the site inspection on 2 September 2026. The site has been inspected 3 times since November 2024. The Land Department took 13 site photos at its inspections.
- Is Emerge Residences delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2027.
- Who is building Emerge Residences?
- The registered developer is N A A S Real Estate Development.
- Which bank holds the escrow account for Emerge Residences?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Royal ManorNearby in Meydan Racecourse Community. 78%, Due December 2018, passed.
- Tonino Lamborghini ResidencesNearby in Meydan Racecourse Community. 60%, Due December 2026.
- Mews MansionsNearby in Meydan Racecourse Community. 56%, Due December 2025, passed.
- Woodland CrestNearby in Meydan Racecourse Community. 1.4%, Due June 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.