Mews Mansions construction progress

Mews Mansions in Meydan Racecourse Community was registered to complete in December 2025 and is still under construction. At the last site inspection, in March 2026, it was 56% built. The developer is Dubai General Properties.

56%

Built, at the site inspection of 5 March 2026

11 months past its registered completion date

Registered completion date
December 2025
Finish at recent pace
July 2027
Construction started
February 2023
First registered
January 2025
Developer
Dubai General Properties
Units
10
Escrow bank
Emirates NBD
Name in Arabic
ميوز مانشنز
Project number
3416
Site inspections
3

Schedule

Mews Mansions was registered to complete in December 2025, 11 months ago, and is still under construction. Over the last year of inspections it has added about 2.7 points a month. Kept at that rate, the site would reach 100% around July 2027.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

5 March 2026

56%+15 pts

  • Mews Mansions construction site, inspection photo 1, 5 March 2026
  • Mews Mansions construction site, inspection photo 2, 5 March 2026
  • Mews Mansions construction site, inspection photo 3, 5 March 2026
  • Mews Mansions construction site, inspection photo 4, 5 March 2026

17 September 2025

40%+11 pts

  • Mews Mansions construction site, inspection photo 1, 17 September 2025
  • Mews Mansions construction site, inspection photo 2, 17 September 2025
  • Mews Mansions construction site, inspection photo 3, 17 September 2025
  • Mews Mansions construction site, inspection photo 4, 17 September 2025

9 December 2024

29%

  • Mews Mansions construction site, inspection photo 1, 9 December 2024
  • Mews Mansions construction site, inspection photo 2, 9 December 2024
  • Mews Mansions construction site, inspection photo 3, 9 December 2024
  • Mews Mansions construction site, inspection photo 4, 9 December 2024

All 23 site photos, by inspection date

Context

Meydan Racecourse Community has 9 projects under construction, 31% built on average.

Dubai General Properties has 2 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Mews Mansions?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Mews Mansions handover date?
The registered completion date was December 2025, and the register still lists Mews Mansions as under construction. At the pace of its recent inspections the site would reach 100% around July 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Mews Mansions?
Mews Mansions was 56% built at the site inspection on 5 March 2026. The site has been inspected 3 times since December 2024. The Land Department took 23 site photos at its inspections.
Is Mews Mansions delayed?
Yes. Its registered completion date of December 2025 has passed and the project is still listed as under construction.
Who is building Mews Mansions?
The registered developer is Dubai General Properties. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Mews Mansions?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.