Mews Mansions construction progress
Mews Mansions in Meydan Racecourse Community is 56% built at the Land Department inspection of March 2026. Developer Dubai General Properties. Completion registered for December 2025.
56%
Built, at the Land Department site inspection of 5 March 2026
9 months past its registered completion date
- Completion date (Land Department)
- December 2025
- Finish at recent pace
- July 2027
- Construction started
- February 2023
- Registered with the Land Department
- January 2025
- Developer
- Dubai General Properties
- Community
- Meydan Racecourse Community
- Units
- 10
- Escrow bank
- Emirates NBD
- Name in Arabic
- ميوز مانشنز
- Land Department project number
- 3416
- Land Department site inspections
- 3
Schedule
Mews Mansions was registered to complete in December 2025, 9 months ago, and is still under construction. Over the last year of inspections it has added about 2.7 points a month. Kept at that rate, the site would reach 100% around July 2027.
Site inspections
5 March 2026
56%+15 pts
17 September 2025
40%+11 pts
9 December 2024
29%
Context
Meydan Racecourse Community has 9 projects under construction, 31% built on average.
Dubai General Properties has 2 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in Mews Mansions?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Mews Mansions be completed?
- The completion date registered with the Dubai Land Department is December 2025. At the pace of its recent inspections the site would reach 100% around July 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Mews Mansions is built?
- 56%, measured at the Land Department site inspection on 5 March 2026. The Land Department engineers have inspected the site 3 times since December 2024.
- Is Mews Mansions delayed?
- Yes. Its registered completion date of December 2025 has passed and the Land Department still lists it as under construction.
- Who is building Mews Mansions?
- The registered developer is Dubai General Properties. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Mews Mansions?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Api- Barsha Residential TowerAlso by Dubai General Properties. 93%, Due October 2025, passed.
- Royal ManorNearby in Meydan Racecourse Community. 78%, Due December 2018, passed.
- Tonino Lamborghini ResidencesNearby in Meydan Racecourse Community. 60%, Due December 2026.
- Emerge ResidencesNearby in Meydan Racecourse Community. 21%, Due November 2027.
- Woodland CrestNearby in Meydan Racecourse Community. 1.4%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.