Tonino Lamborghini Residences construction progress
Tonino Lamborghini Residences in Meydan Racecourse Community is 60% built at the Land Department inspection of September 2026. Developer Gulf Land Property Developers. Completion registered for December 2026.
60%
Built, at the Land Department site inspection of 21 September 2026
Running behind its date
- Completion date (Land Department)
- December 2026
- Finish at recent pace
- June 2030
- Construction started
- October 2017
- Registered with the Land Department
- October 2017
- Developer
- Gulf Land Property Developers
- Community
- Meydan Racecourse Community
- Units
- 553
- Escrow bank
- Commercial Bank International
- Name in Arabic
- تونينو لامبورغيني ريزيدنسز
- Land Department project number
- 1941
- Land Department site inspections
- 13
Schedule
Between October 2025 and September 2026 the site added about 0.9 points a month. At that rate it would finish around June 2030, more than three months after the December 2026 date registered with the Land Department.
Site inspections
21 September 2026
60%+6.1 pts
10 September 2026
54%+2.0 pts
24 March 2026
52%+1.3 pts
30 October 2025
51%+0.4 pts
18 June 2025
50%+9.8 pts
30 January 2025
40%+6.1 pts
24 December 2024
34%+6.9 pts
7 June 2024
27%+1.0 pts
17 August 2020
26%+0.7 pts
17 April 2019
26%+5.4 pts
Context
Meydan Racecourse Community has 9 projects under construction, 31% built on average.
Gulf Land Property Developers has 2 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Tonino Lamborghini Residences?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Tonino Lamborghini Residences be completed?
- The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around June 2030. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Tonino Lamborghini Residences is built?
- 60%, measured at the Land Department site inspection on 21 September 2026. The Land Department engineers have inspected the site 13 times since March 2018.
- Is Tonino Lamborghini Residences delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building Tonino Lamborghini Residences?
- The registered developer is Gulf Land Property Developers. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Tonino Lamborghini Residences?
- Commercial Bank International. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Serenity Lakes 2Also by Gulf Land Property Developers. 50%, Due November 2025, passed.
- Royal ManorNearby in Meydan Racecourse Community. 78%, Due December 2018, passed.
- Emerge ResidencesNearby in Meydan Racecourse Community. 21%, Due November 2027.
- Mews MansionsNearby in Meydan Racecourse Community. 56%, Due December 2025, passed.
- Woodland CrestNearby in Meydan Racecourse Community. 1.4%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.