Tonino Lamborghini Residences construction progress

The registered completion date for Tonino Lamborghini Residences in Meydan Racecourse Community is December 2026. At the last site inspection, in September 2026, it was 60% built. The developer is Gulf Land Property Developers.

60%

Built, at the site inspection of 21 September 2026

Running behind its date

Registered completion date
December 2026
Finish at recent pace
June 2030
Construction started
October 2017
First registered
October 2017
Developer
Gulf Land Property Developers
Units
553
Escrow bank
Commercial Bank International
Name in Arabic
تونينو لامبورغيني ريزيدنسز
Project number
1941
Site inspections
13

Schedule

Between October 2025 and September 2026 the site added about 0.9 points a month. At that rate it would finish around June 2030, more than three months after its registered date of December 2026.

0%25%50%75%100%20182020202220242026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

21 September 2026

60%+6.1 pts

  • Tonino Lamborghini Residences construction site, inspection photo 1, 21 September 2026
  • Tonino Lamborghini Residences construction site, inspection photo 2, 21 September 2026
  • Tonino Lamborghini Residences construction site, inspection photo 3, 21 September 2026
  • Tonino Lamborghini Residences construction site, inspection photo 4, 21 September 2026

10 September 2026

54%+2.0 pts

  • Tonino Lamborghini Residences construction site, inspection photo 1, 10 September 2026
  • Tonino Lamborghini Residences construction site, inspection photo 2, 10 September 2026
  • Tonino Lamborghini Residences construction site, inspection photo 3, 10 September 2026
  • Tonino Lamborghini Residences construction site, inspection photo 4, 10 September 2026

24 March 2026

52%+1.3 pts

  • Tonino Lamborghini Residences construction site, inspection photo 1, 24 March 2026
  • Tonino Lamborghini Residences construction site, inspection photo 2, 24 March 2026
  • Tonino Lamborghini Residences construction site, inspection photo 3, 24 March 2026
  • Tonino Lamborghini Residences construction site, inspection photo 4, 24 March 2026

30 October 2025

51%+0.4 pts

  • Tonino Lamborghini Residences construction site, inspection photo 1, 30 October 2025
  • Tonino Lamborghini Residences construction site, inspection photo 2, 30 October 2025
  • Tonino Lamborghini Residences construction site, inspection photo 3, 30 October 2025
  • Tonino Lamborghini Residences construction site, inspection photo 4, 30 October 2025

18 June 2025

50%+9.8 pts

  • Tonino Lamborghini Residences construction site, inspection photo 1, 18 June 2025
  • Tonino Lamborghini Residences construction site, inspection photo 2, 18 June 2025
  • Tonino Lamborghini Residences construction site, inspection photo 3, 18 June 2025
  • Tonino Lamborghini Residences construction site, inspection photo 4, 18 June 2025

30 January 2025

40%+6.1 pts

  • Tonino Lamborghini Residences construction site, inspection photo 1, 30 January 2025
  • Tonino Lamborghini Residences construction site, inspection photo 2, 30 January 2025
  • Tonino Lamborghini Residences construction site, inspection photo 3, 30 January 2025
  • Tonino Lamborghini Residences construction site, inspection photo 4, 30 January 2025

24 December 2024

34%+6.9 pts

  • Tonino Lamborghini Residences construction site, inspection photo 1, 24 December 2024
  • Tonino Lamborghini Residences construction site, inspection photo 2, 24 December 2024
  • Tonino Lamborghini Residences construction site, inspection photo 3, 24 December 2024
  • Tonino Lamborghini Residences construction site, inspection photo 4, 24 December 2024

7 June 2024

27%+1.0 pts

  • Tonino Lamborghini Residences construction site, inspection photo 1, 7 June 2024
  • Tonino Lamborghini Residences construction site, inspection photo 2, 7 June 2024
  • Tonino Lamborghini Residences construction site, inspection photo 3, 7 June 2024
  • Tonino Lamborghini Residences construction site, inspection photo 4, 7 June 2024

17 August 2020

26%+0.7 pts

  • Tonino Lamborghini Residences construction site, inspection photo 1, 17 August 2020
  • Tonino Lamborghini Residences construction site, inspection photo 2, 17 August 2020
  • Tonino Lamborghini Residences construction site, inspection photo 3, 17 August 2020
  • Tonino Lamborghini Residences construction site, inspection photo 4, 17 August 2020

17 April 2019

26%+5.4 pts

  • Tonino Lamborghini Residences construction site, inspection photo 1, 17 April 2019
  • Tonino Lamborghini Residences construction site, inspection photo 2, 17 April 2019
  • Tonino Lamborghini Residences construction site, inspection photo 3, 17 April 2019
  • Tonino Lamborghini Residences construction site, inspection photo 4, 17 April 2019

All 92 site photos, by inspection date

Context

Meydan Racecourse Community has 9 projects under construction, 31% built on average.

Gulf Land Property Developers has 2 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Tonino Lamborghini Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Tonino Lamborghini Residences handover date?
The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Tonino Lamborghini Residences?
Tonino Lamborghini Residences was 60% built at the site inspection on 21 September 2026. The site has been inspected 13 times since March 2018. The Land Department took 92 site photos at its inspections.
Is Tonino Lamborghini Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Tonino Lamborghini Residences?
The registered developer is Gulf Land Property Developers. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Tonino Lamborghini Residences?
Commercial Bank International. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.