Azizi Gardens construction progress

The register lists Azizi Gardens in Meydan Racecourse Community as complete, with a registered completion date of December 2023. Its last site inspection on record was in December 2023. The developer is Azizi Developments.

100%

Built, at the site inspection of 11 December 2023

Construction complete

Registered completion date
December 2023
Construction started
February 2018
First registered
March 2018
Units
82
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
عزيزي غاردنز
Project number
2037
Site inspections
6

Schedule

The register lists Azizi Gardens as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20192020202120222023
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

11 December 2023

100%+20 pts

  • Azizi Gardens construction site, inspection photo 1, 11 December 2023
  • Azizi Gardens construction site, inspection photo 2, 11 December 2023
  • Azizi Gardens construction site, inspection photo 3, 11 December 2023
  • Azizi Gardens construction site, inspection photo 4, 11 December 2023

29 March 2023

80%+52 pts

  • Azizi Gardens construction site, inspection photo 1, 29 March 2023
  • Azizi Gardens construction site, inspection photo 2, 29 March 2023
  • Azizi Gardens construction site, inspection photo 3, 29 March 2023
  • Azizi Gardens construction site, inspection photo 4, 29 March 2023

25 August 2022

28%+10 pts

  • Azizi Gardens construction site, inspection photo 1, 25 August 2022
  • Azizi Gardens construction site, inspection photo 2, 25 August 2022
  • Azizi Gardens construction site, inspection photo 3, 25 August 2022
  • Azizi Gardens construction site, inspection photo 4, 25 August 2022

1 March 2022

18%+8.4 pts

  • Azizi Gardens construction site, inspection photo 1, 1 March 2022
  • Azizi Gardens construction site, inspection photo 2, 1 March 2022
  • Azizi Gardens construction site, inspection photo 3, 1 March 2022
  • Azizi Gardens construction site, inspection photo 4, 1 March 2022

10 October 2021

9.4%+8.9 pts

  • Azizi Gardens construction site, inspection photo 1, 10 October 2021
  • Azizi Gardens construction site, inspection photo 2, 10 October 2021
  • Azizi Gardens construction site, inspection photo 3, 10 October 2021
  • Azizi Gardens construction site, inspection photo 4, 10 October 2021

18 February 2021

0.6%

  • Azizi Gardens construction site, inspection photo 1, 18 February 2021
  • Azizi Gardens construction site, inspection photo 2, 18 February 2021
  • Azizi Gardens construction site, inspection photo 3, 18 February 2021
  • Azizi Gardens construction site, inspection photo 4, 18 February 2021

All 53 site photos, by inspection date

Context

Meydan Racecourse Community has 9 projects under construction, 31% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi Gardens?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Azizi Gardens handover date?
Construction of Azizi Gardens is recorded as complete, with a registered completion date of December 2023. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Azizi Gardens?
Azizi Gardens was 100% built at the site inspection on 11 December 2023. The site has been inspected 6 times since February 2021. The Land Department took 53 site photos at its inspections.
Is Azizi Gardens delayed?
The register lists construction as complete.
Who is building Azizi Gardens?
The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Gardens?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.