The Oasis - Palace Villas - Ostra construction progress

The registered completion date for The Oasis - Palace Villas - Ostra in Me'aisem Second is September 2029. At the last site inspection, in July 2026, it was 6.5% built. The developer is Emaar Development.

6.5%

Built, at the site inspection of 20 July 2026

Running behind its date

Registered completion date
September 2029
Finish at recent pace
April 2039
Construction started
August 2025
First registered
March 2025
Units
526
Escrow bank
First Abu Dhabi Bank
Name in Arabic
ذا اويسيس - بالاس فيلا - اوسترا
Project number
3581
Site inspections
4

Schedule

Between September 2025 and July 2026 the site added about 0.6 points a month. At that rate it would finish around April 2039, more than three months after its registered date of September 2029.

0%25%50%75%100%2026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

20 July 2026

6.5%+3.4 pts

  • The Oasis - Palace Villas - Ostra construction site, inspection photo 1, 20 July 2026
  • The Oasis - Palace Villas - Ostra construction site, inspection photo 2, 20 July 2026
  • The Oasis - Palace Villas - Ostra construction site, inspection photo 3, 20 July 2026
  • The Oasis - Palace Villas - Ostra construction site, inspection photo 4, 20 July 2026

12 March 2026

3.1%+2.8 pts

  • The Oasis - Palace Villas - Ostra construction site, inspection photo 1, 12 March 2026
  • The Oasis - Palace Villas - Ostra construction site, inspection photo 2, 12 March 2026
  • The Oasis - Palace Villas - Ostra construction site, inspection photo 3, 12 March 2026
  • The Oasis - Palace Villas - Ostra construction site, inspection photo 4, 12 March 2026

11 September 2025

0.3%+0.3 pts

  • The Oasis - Palace Villas - Ostra construction site, inspection photo 1, 11 September 2025
  • The Oasis - Palace Villas - Ostra construction site, inspection photo 2, 11 September 2025
  • The Oasis - Palace Villas - Ostra construction site, inspection photo 3, 11 September 2025

25 February 2025

0%

  • The Oasis - Palace Villas - Ostra construction site, inspection photo 1, 25 February 2025
  • The Oasis - Palace Villas - Ostra construction site, inspection photo 2, 25 February 2025

All 19 site photos, by inspection date

Context

Me'aisem Second has 7 projects under construction, 45% built on average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Oasis - Palace Villas - Ostra?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Oasis - Palace Villas - Ostra handover date?
The registered completion date is September 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2039. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Oasis - Palace Villas - Ostra?
The Oasis - Palace Villas - Ostra was 6.5% built at the site inspection on 20 July 2026. The site has been inspected 4 times since February 2025. The Land Department took 19 site photos at its inspections.
Is The Oasis - Palace Villas - Ostra delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2029.
Who is building The Oasis - Palace Villas - Ostra?
The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
Which bank holds the escrow account for The Oasis - Palace Villas - Ostra?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.