The Oasis - Palace Villas - Ostra construction progress
The Oasis - Palace Villas - Ostra in Me'aisem Second is 6.5% built at the Land Department inspection of July 2026. Developer Emaar Development. Completion registered for September 2029.
6.5%
Built, at the Land Department site inspection of 20 July 2026
Running behind its date
- Completion date (Land Department)
- September 2029
- Finish at recent pace
- April 2039
- Construction started
- August 2025
- Registered with the Land Department
- March 2025
- Developer
- Emaar Development
- Community
- Me'aisem Second
- Units
- 526
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- ذا اويسيس - بالاس فيلا - اوسترا
- Land Department project number
- 3581
- Land Department site inspections
- 4
Schedule
Between September 2025 and July 2026 the site added about 0.6 points a month. At that rate it would finish around April 2039, more than three months after the September 2029 date registered with the Land Department.
Site inspections
20 July 2026
6.5%+3.4 pts
12 March 2026
3.1%+2.8 pts
11 September 2025
0.3%+0.3 pts
25 February 2025
0%
Context
Me'aisem Second has 7 projects under construction, 45% built on average.
Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.
Own a unit in The Oasis - Palace Villas - Ostra?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will The Oasis - Palace Villas - Ostra be completed?
- The completion date registered with the Dubai Land Department is September 2029. At the pace of its recent inspections the site would reach 100% around April 2039. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of The Oasis - Palace Villas - Ostra is built?
- 6.5%, measured at the Land Department site inspection on 20 July 2026. The Land Department engineers have inspected the site 4 times since February 2025.
- Is The Oasis - Palace Villas - Ostra delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2029.
- Who is building The Oasis - Palace Villas - Ostra?
- The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
- Which bank holds the escrow account for The Oasis - Palace Villas - Ostra?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The St. Regis Residences, Downtown DubaiAlso by Emaar Development. 76%, Due December 2026.
- Address The BayAlso by Emaar Development. 70%, Due December 2026.
- SeapointAlso by Emaar Development. 37%, Due March 2028.
- BayviewAlso by Emaar Development. 63%, Due July 2028.
- The Oasis - PalmieraNearby in Me'aisem Second. 82%.
- The Oasis - MirageNearby in Me'aisem Second. 47%.
- The Oasis - Palmiera 2Nearby in Me'aisem Second. 77%.
- The Oasis - Palmiera 3Nearby in Me'aisem Second. 73%, Due October 2028.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.








.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

