Samana Business Park 2 construction progress

Samana Business Park 2 in Majan is 3.0% built at the Land Department inspection of April 2026. Developer Samana Signature Real Estate Developments. Completion registered for October 2028.

3.0%

Built, at the Land Department site inspection of 16 April 2026

Running behind its date

Completion date (Land Department)
October 2028
Finish at recent pace
January 2045
Construction started
November 2025
Registered with the Land Department
February 2026
Community
Majan
Units
174
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
سامانا بيزنس بارك 2
Land Department project number
4110
Land Department site inspections
2

Schedule

Between September 2025 and April 2026 the site added about 0.4 points a month. At that rate it would finish around January 2045, more than three months after the October 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

16 April 2026

3.0%+3.0 pts

  • Samana Business Park 2 construction site, Land Department inspection photo 1, 16 April 2026
  • Samana Business Park 2 construction site, Land Department inspection photo 2, 16 April 2026

19 September 2025

0%

  • Samana Business Park 2 construction site, Land Department inspection photo 1, 19 September 2025
  • Samana Business Park 2 construction site, Land Department inspection photo 2, 19 September 2025

All 4 site photos, by inspection date

Context

Majan has 25 projects under construction, 24% built on average.

Samana Signature Real Estate Developments has 12 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Samana Business Park 2?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Samana Business Park 2 be completed?
The completion date registered with the Dubai Land Department is October 2028. At the pace of its recent inspections the site would reach 100% around January 2045. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Samana Business Park 2 is built?
3.0%, measured at the Land Department site inspection on 16 April 2026. The Land Department engineers have inspected the site 2 times since September 2025.
Is Samana Business Park 2 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2028.
Who is building Samana Business Park 2?
The registered developer is Samana Signature Real Estate Developments. It has 11 other projects under construction in Dubai.
Which bank holds the escrow account for Samana Business Park 2?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.