Wadi 645 construction progress

Wadi 645 in Majan is 55% built at the Land Department inspection of August 2026. Developer Greenside Development.

55%

Built, at the Land Department site inspection of 18 August 2026

Finish at recent pace
August 2027
Construction started
July 2024
Registered with the Land Department
April 2024
Developer
Greenside Development
Community
Majan
Units
70
Escrow bank
Commercial Bank of Dubai
Name in Arabic
وادي 645
Land Department project number
2999
Land Department site inspections
7

Schedule

Since November 2025 Wadi 645 has added about 3.9 points a month. At that rate the site reaches 100% around August 2027. The Land Department has no completion date on record to compare it with.

0%25%50%75%100%20252026
Progress at each Land Department site inspection

Site inspections

18 August 2026

55%+13 pts

  • Wadi 645 construction site, Land Department inspection photo 1, 18 August 2026
  • Wadi 645 construction site, Land Department inspection photo 2, 18 August 2026
  • Wadi 645 construction site, Land Department inspection photo 3, 18 August 2026
  • Wadi 645 construction site, Land Department inspection photo 4, 18 August 2026

21 May 2026

42%+13 pts

  • Wadi 645 construction site, Land Department inspection photo 1, 21 May 2026
  • Wadi 645 construction site, Land Department inspection photo 2, 21 May 2026
  • Wadi 645 construction site, Land Department inspection photo 3, 21 May 2026
  • Wadi 645 construction site, Land Department inspection photo 4, 21 May 2026

9 February 2026

29%+11 pts

  • Wadi 645 construction site, Land Department inspection photo 1, 9 February 2026
  • Wadi 645 construction site, Land Department inspection photo 2, 9 February 2026
  • Wadi 645 construction site, Land Department inspection photo 3, 9 February 2026
  • Wadi 645 construction site, Land Department inspection photo 4, 9 February 2026

4 November 2025

19%+8.1 pts

  • Wadi 645 construction site, Land Department inspection photo 1, 4 November 2025
  • Wadi 645 construction site, Land Department inspection photo 2, 4 November 2025
  • Wadi 645 construction site, Land Department inspection photo 3, 4 November 2025
  • Wadi 645 construction site, Land Department inspection photo 4, 4 November 2025

25 May 2025

11%+7.2 pts

  • Wadi 645 construction site, Land Department inspection photo 1, 25 May 2025
  • Wadi 645 construction site, Land Department inspection photo 2, 25 May 2025
  • Wadi 645 construction site, Land Department inspection photo 3, 25 May 2025
  • Wadi 645 construction site, Land Department inspection photo 4, 25 May 2025

11 February 2025

3.4%+3.4 pts

  • Wadi 645 construction site, Land Department inspection photo 1, 11 February 2025
  • Wadi 645 construction site, Land Department inspection photo 2, 11 February 2025
  • Wadi 645 construction site, Land Department inspection photo 3, 11 February 2025

15 March 2024

0%

  • Wadi 645 construction site, Land Department inspection photo 1, 15 March 2024
  • Wadi 645 construction site, Land Department inspection photo 2, 15 March 2024

All 43 site photos, by inspection date

Context

Majan has 25 projects under construction, 24% built on average.

Own a unit in Wadi 645?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Wadi 645 be completed?
The Land Department has no completion date on record for Wadi 645 yet.
How much of Wadi 645 is built?
55%, measured at the Land Department site inspection on 18 August 2026. The Land Department engineers have inspected the site 7 times since March 2024.
Who is building Wadi 645?
The registered developer is Greenside Development.
Which bank holds the escrow account for Wadi 645?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.