Samana Barari Heights construction progress
Samana Barari Heights in Majan is 4.0% built at the Land Department inspection of June 2026. Developer Samana International Real Estate Development. Completion registered for October 2028.
4.0%
Built, at the Land Department site inspection of 1 June 2026
Running behind its date
- Completion date (Land Department)
- October 2028
- Finish at recent pace
- April 2047
- Construction started
- July 2025
- Registered with the Land Department
- August 2025
- Community
- Majan
- Units
- 737
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- سامانا براري هايتس
- Land Department project number
- 3871
- Land Department site inspections
- 3
Schedule
Between July 2025 and June 2026 the site added about 0.4 points a month. At that rate it would finish around April 2047, more than three months after the October 2028 date registered with the Land Department.
Site inspections
1 June 2026
4.0%+3.7 pts
16 January 2026
0.3%+0.3 pts
15 July 2025
0%
Context
Majan has 25 projects under construction, 24% built on average.
Samana International Real Estate Development has 14 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in Samana Barari Heights?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Samana Barari Heights be completed?
- The completion date registered with the Dubai Land Department is October 2028. At the pace of its recent inspections the site would reach 100% around April 2047. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Samana Barari Heights is built?
- 4.0%, measured at the Land Department site inspection on 1 June 2026. The Land Department engineers have inspected the site 3 times since July 2025.
- Is Samana Barari Heights delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2028.
- Who is building Samana Barari Heights?
- The registered developer is Samana International Real Estate Development. It has 13 other projects under construction in Dubai.
- Which bank holds the escrow account for Samana Barari Heights?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Samana MykonosAlso by Samana International Real Estate Development. 91%, Due April 2026, passed.
- Samana Mykonos SignatureAlso by Samana International Real Estate Development. 80%, Due April 2026, passed.
- Samana Ivy GardensAlso by Samana International Real Estate Development. 41%.
- Samana Golf ViewsAlso by Samana International Real Estate Development. 56%.
- Sherena Residence 2Nearby in Majan. 82%, Due August 2022, passed.
- Barari Parkview By Al MawaredNearby in Majan. 45%, Due December 2027.
- Wadi 645Nearby in Majan. 55%.
- Jade TowerNearby in Majan. 11%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.