Samana Barari Avenue construction progress
The registered completion date for Samana Barari Avenue in Majan is October 2028. At the last site inspection, in September 2026, it was 6.0% built. The developer is Samana Signature Real Estate Developments.
6.0%
Built, at the site inspection of 23 September 2026
Running behind its date
- Registered completion date
- October 2028
- Finish at recent pace
- September 2043
- Construction started
- June 2025
- First registered
- July 2025
- Community
- Majan
- Units
- 349
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- سامانا براري افنيو
- Project number
- 3829
- Site inspections
- 5
Schedule
Between December 2025 and September 2026 the site added about 0.5 points a month. At that rate it would finish around September 2043, more than three months after its registered date of October 2028.
Site inspections
23 September 2026
6.0%+1.4 pts
18 June 2026
4.6%+0.3 pts
22 April 2026
4.3%+2.6 pts
15 December 2025
1.7%+1.7 pts
11 June 2025
0%
Context
Majan has 25 projects under construction, 28% built on average.
Samana Signature Real Estate Developments has 12 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Samana Barari Avenue?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Samana Barari Avenue handover date?
- The registered completion date is October 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2043. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Samana Barari Avenue?
- Samana Barari Avenue was 6.0% built at the site inspection on 23 September 2026. The site has been inspected 5 times since June 2025. The Land Department took 17 site photos at its inspections.
- Is Samana Barari Avenue delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2028.
- Who is building Samana Barari Avenue?
- The registered developer is Samana Signature Real Estate Developments. It has 11 other projects under construction in Dubai.
- Which bank holds the escrow account for Samana Barari Avenue?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Samana SkyrosAlso by Samana Signature Real Estate Developments. 71%, Due April 2026, passed.
- Samana Lake ViewsAlso by Samana Signature Real Estate Developments. 23%.
- Samana Lake Views 2Also by Samana Signature Real Estate Developments. 12%.
- Samana Barari LagoonsAlso by Samana Signature Real Estate Developments. 17%, Due March 2028.
- Sherena Residence 2Nearby in Majan. 82%, Due August 2022, passed.
- Samana Barari ViewsNearby in Majan. 32%, Due March 2027.
- Samana Barari Views 2Nearby in Majan. 26%.
- Barari Parkview By Al MawaredNearby in Majan. 45%, Due December 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)