Guzel Towers construction progress
The registered completion date for Guzel Towers in Jumeirah Village Triangle is December 2027. At the last site inspection, in October 2026, it was 7.3% built. The developer is Tiger Properties.
7.3%
Built, at the site inspection of 7 October 2026
Running behind its date
- Registered completion date
- December 2027
- Finish at recent pace
- June 2038
- Construction started
- December 2024
- First registered
- January 2025
- Developer
- Tiger Properties
- Community
- Jumeirah Village Triangle
- Units
- 522
- Escrow bank
- Emirates NBD
- Name in Arabic
- جوزيل تاورز
- Project number
- 3458
- Site inspections
- 5
Schedule
Between December 2025 and October 2026 the site added about 0.7 points a month. At that rate it would finish around June 2038, more than three months after its registered date of December 2027.
Site inspections
7 October 2026
7.3%+0.3 pts
24 July 2026
7.0%+3.4 pts
13 April 2026
3.6%+2.4 pts
30 December 2025
1.2%+1.2 pts
20 December 2024
0%
Context
Jumeirah Village Triangle has 29 projects under construction, 27% built on average.
Tiger Properties has 8 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Guzel Towers?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Guzel Towers handover date?
- The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2038. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Guzel Towers?
- Guzel Towers was 7.3% built at the site inspection on 7 October 2026. The site has been inspected 5 times since December 2024. The Land Department took 15 site photos at its inspections.
- Is Guzel Towers delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
- Who is building Guzel Towers?
- The registered developer is Tiger Properties. It has 7 other projects under construction in Dubai.
- Which bank holds the escrow account for Guzel Towers?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Tiger Sky TowerAlso by Tiger Properties. 10%.
- Volga TowerAlso by Tiger Properties. 51%.
- Red SquareAlso by Tiger Properties. 27%.
- Jade TowerAlso by Tiger Properties. 11%, Due March 2027.
- Paradise OneNearby in Jumeirah Village Triangle. 70%, Due April 2027.
- Silver StallionsNearby in Jumeirah Village Triangle. 12%, Due December 2017, passed.
- Fashionz 1 By DanubeNearby in Jumeirah Village Triangle. 40%.
- Santorini Residences By LoutrakiNearby in Jumeirah Village Triangle. 65%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.