Silver Stallions construction progress

Silver Stallions in Jumeirah Village Triangle is 12% built at the Land Department inspection of March 2016. Developer Dot Life Real Estate Development. Completion registered for December 2017.

12%

Built, at the Land Department site inspection of 7 March 2016

105 months past its registered completion date

Completion date (Land Department)
December 2017
Finish at recent pace
December 2035
Construction started
June 2009
Registered with the Land Department
June 2009
Developer
Dot Life Real Estate Development
Units
495
Escrow bank
Bank of Baroda
Name in Arabic
الفحول الفضية
Land Department project number
835
Land Department site inspections
5

Schedule

Silver Stallions was registered to complete in December 2017, 105 months ago, and is still under construction. Over the last year of inspections it has added about 0.4 points a month. Kept at that rate, the site would reach 100% around December 2035.

0%25%50%75%100%2010201220142016
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

7 March 2016

12%+3.6 pts

  • Silver Stallions construction site, Land Department inspection photo 1, 7 March 2016
  • Silver Stallions construction site, Land Department inspection photo 2, 7 March 2016
  • Silver Stallions construction site, Land Department inspection photo 3, 7 March 2016

17 May 2015

8.9%+3.7 pts

  • Silver Stallions construction site, Land Department inspection photo 1, 17 May 2015
  • Silver Stallions construction site, Land Department inspection photo 2, 17 May 2015
  • Silver Stallions construction site, Land Department inspection photo 3, 17 May 2015
  • Silver Stallions construction site, Land Department inspection photo 4, 17 May 2015

24 September 2014

5.3%+1.0 pts

  • Silver Stallions construction site, Land Department inspection photo 1, 24 September 2014
  • Silver Stallions construction site, Land Department inspection photo 2, 24 September 2014
  • Silver Stallions construction site, Land Department inspection photo 3, 24 September 2014
  • Silver Stallions construction site, Land Department inspection photo 4, 24 September 2014

3 March 2014

4.2%+0.6 pts

  • Silver Stallions construction site, Land Department inspection photo 1, 3 March 2014
  • Silver Stallions construction site, Land Department inspection photo 2, 3 March 2014
  • Silver Stallions construction site, Land Department inspection photo 3, 3 March 2014
  • Silver Stallions construction site, Land Department inspection photo 4, 3 March 2014

2 March 2013

3.6%

  • Silver Stallions construction site, Land Department inspection photo 1, 2 March 2013
  • Silver Stallions construction site, Land Department inspection photo 2, 2 March 2013
  • Silver Stallions construction site, Land Department inspection photo 3, 2 March 2013
  • Silver Stallions construction site, Land Department inspection photo 4, 2 March 2013

All 26 site photos, by inspection date

Context

Jumeirah Village Triangle has 31 projects under construction, 28% built on average. Silver Stallions is behind that average.

Own a unit in Silver Stallions?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Silver Stallions be completed?
The completion date registered with the Dubai Land Department is December 2017. At the pace of its recent inspections the site would reach 100% around December 2035. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Silver Stallions is built?
12%, measured at the Land Department site inspection on 7 March 2016. The Land Department engineers have inspected the site 5 times since March 2013.
Is Silver Stallions delayed?
Yes. Its registered completion date of December 2017 has passed and the Land Department still lists it as under construction.
Who is building Silver Stallions?
The registered developer is Dot Life Real Estate Development.
Which bank holds the escrow account for Silver Stallions?
Bank of Baroda. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.