Silver Stallions construction progress
Silver Stallions in Jumeirah Village Triangle was registered to complete in December 2017 and is still under construction. At the last site inspection, in March 2016, it was 12% built. The developer is Dot Life Real Estate Development.
12%
Built, at the site inspection of 7 March 2016
107 months past its registered completion date
- Registered completion date
- December 2017
- Finish at recent pace
- December 2035
- Construction started
- June 2009
- First registered
- June 2009
- Developer
- Dot Life Real Estate Development
- Community
- Jumeirah Village Triangle
- Units
- 495
- Escrow bank
- Bank of Baroda
- Name in Arabic
- الفحول الفضية
- Project number
- 835
- Site inspections
- 5
Schedule
Silver Stallions was registered to complete in December 2017, 107 months ago, and is still under construction. Over the last year of inspections it has added about 0.4 points a month. Kept at that rate, the site would reach 100% around December 2035.
Site inspections
7 March 2016
12%+3.6 pts
17 May 2015
8.9%+3.7 pts
24 September 2014
5.3%+1.0 pts
3 March 2014
4.2%+0.6 pts
2 March 2013
3.6%
Context
Jumeirah Village Triangle has 29 projects under construction, 27% built on average.
Own a unit in Silver Stallions?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Silver Stallions handover date?
- The registered completion date was December 2017, and the register still lists Silver Stallions as under construction. At the pace of its recent inspections the site would reach 100% around December 2035. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Silver Stallions?
- Silver Stallions was 12% built at the site inspection on 7 March 2016. The site has been inspected 5 times since March 2013. The Land Department took 26 site photos at its inspections.
- Is Silver Stallions delayed?
- Yes. Its registered completion date of December 2017 has passed and the project is still listed as under construction.
- Who is building Silver Stallions?
- The registered developer is Dot Life Real Estate Development.
- Which bank holds the escrow account for Silver Stallions?
- Bank of Baroda. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Paradise OneNearby in Jumeirah Village Triangle. 70%, Due April 2027.
- Fashionz 1 By DanubeNearby in Jumeirah Village Triangle. 40%.
- Volga TowerNearby in Jumeirah Village Triangle. 51%.
- Santorini Residences By LoutrakiNearby in Jumeirah Village Triangle. 65%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.