Paradise One construction progress

Paradise One in Jumeirah Village Triangle is 70% built at the Land Department inspection of April 2026. Developer Danat Aldunia Real Estate Development. Completion registered for April 2027.

70%

Built, at the Land Department site inspection of 23 April 2026

Running behind its date

Completion date (Land Department)
April 2027
Finish at recent pace
January 2152
Construction started
October 2025
Registered with the Land Department
October 2025
Developer
Danat Aldunia Real Estate Development
Units
121
Escrow bank
Sharjah Islamic Bank
Name in Arabic
الجنة الأولى
Land Department project number
807
Land Department site inspections
17

Schedule

Between June 2019 and April 2026 the site added about 0.0 points a month. At that rate it would finish around January 2152, more than three months after the April 2027 date registered with the Land Department.

0%25%50%75%100%20132016201920222025
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

23 April 2026

70%+1.7 pts

  • Paradise One construction site, Land Department inspection photo 1, 23 April 2026
  • Paradise One construction site, Land Department inspection photo 2, 23 April 2026
  • Paradise One construction site, Land Department inspection photo 3, 23 April 2026

19 June 2019

68%+3.5 pts

  • Paradise One construction site, Land Department inspection photo 1, 19 June 2019
  • Paradise One construction site, Land Department inspection photo 2, 19 June 2019
  • Paradise One construction site, Land Department inspection photo 3, 19 June 2019
  • Paradise One construction site, Land Department inspection photo 4, 19 June 2019

20 December 2018

65%+1.3 pts

  • Paradise One construction site, Land Department inspection photo 1, 20 December 2018
  • Paradise One construction site, Land Department inspection photo 2, 20 December 2018
  • Paradise One construction site, Land Department inspection photo 3, 20 December 2018
  • Paradise One construction site, Land Department inspection photo 4, 20 December 2018

30 October 2017

63%+2.9 pts

  • Paradise One construction site, Land Department inspection photo 1, 30 October 2017
  • Paradise One construction site, Land Department inspection photo 2, 30 October 2017
  • Paradise One construction site, Land Department inspection photo 3, 30 October 2017
  • Paradise One construction site, Land Department inspection photo 4, 30 October 2017

1 May 2017

60%+5.3 pts

  • Paradise One construction site, Land Department inspection photo 1, 1 May 2017
  • Paradise One construction site, Land Department inspection photo 2, 1 May 2017
  • Paradise One construction site, Land Department inspection photo 3, 1 May 2017
  • Paradise One construction site, Land Department inspection photo 4, 1 May 2017

30 October 2016

55%+7.1 pts

  • Paradise One construction site, Land Department inspection photo 1, 30 October 2016
  • Paradise One construction site, Land Department inspection photo 2, 30 October 2016
  • Paradise One construction site, Land Department inspection photo 3, 30 October 2016
  • Paradise One construction site, Land Department inspection photo 4, 30 October 2016

28 July 2016

48%+1.4 pts

  • Paradise One construction site, Land Department inspection photo 1, 28 July 2016
  • Paradise One construction site, Land Department inspection photo 2, 28 July 2016
  • Paradise One construction site, Land Department inspection photo 3, 28 July 2016
  • Paradise One construction site, Land Department inspection photo 4, 28 July 2016

14 January 2016

47%+1.1 pts

  • Paradise One construction site, Land Department inspection photo 1, 14 January 2016
  • Paradise One construction site, Land Department inspection photo 2, 14 January 2016
  • Paradise One construction site, Land Department inspection photo 3, 14 January 2016
  • Paradise One construction site, Land Department inspection photo 4, 14 January 2016

12 July 2015

46%+7.0 pts

  • Paradise One construction site, Land Department inspection photo 1, 12 July 2015
  • Paradise One construction site, Land Department inspection photo 2, 12 July 2015
  • Paradise One construction site, Land Department inspection photo 3, 12 July 2015

9 February 2015

39%+9.3 pts

  • Paradise One construction site, Land Department inspection photo 1, 9 February 2015
  • Paradise One construction site, Land Department inspection photo 2, 9 February 2015
  • Paradise One construction site, Land Department inspection photo 3, 9 February 2015
  • Paradise One construction site, Land Department inspection photo 4, 9 February 2015

All 105 site photos, by inspection date

Context

Jumeirah Village Triangle has 31 projects under construction, 28% built on average. Paradise One is ahead of that average.

Own a unit in Paradise One?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Paradise One be completed?
The completion date registered with the Dubai Land Department is April 2027. At the pace of its recent inspections the site would reach 100% around January 2152. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Paradise One is built?
70%, measured at the Land Department site inspection on 23 April 2026. The Land Department engineers have inspected the site 17 times since September 2012.
Is Paradise One delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of April 2027.
Who is building Paradise One?
The registered developer is Danat Aldunia Real Estate Development.
Which bank holds the escrow account for Paradise One?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.