Paradise One construction progress
Paradise One in Jumeirah Village Triangle is 70% built at the Land Department inspection of April 2026. Developer Danat Aldunia Real Estate Development. Completion registered for April 2027.
70%
Built, at the Land Department site inspection of 23 April 2026
Running behind its date
- Completion date (Land Department)
- April 2027
- Finish at recent pace
- January 2152
- Construction started
- October 2025
- Registered with the Land Department
- October 2025
- Developer
- Danat Aldunia Real Estate Development
- Community
- Jumeirah Village Triangle
- Units
- 121
- Escrow bank
- Sharjah Islamic Bank
- Name in Arabic
- الجنة الأولى
- Land Department project number
- 807
- Land Department site inspections
- 17
Schedule
Between June 2019 and April 2026 the site added about 0.0 points a month. At that rate it would finish around January 2152, more than three months after the April 2027 date registered with the Land Department.
Site inspections
23 April 2026
70%+1.7 pts
19 June 2019
68%+3.5 pts
20 December 2018
65%+1.3 pts
30 October 2017
63%+2.9 pts
1 May 2017
60%+5.3 pts
30 October 2016
55%+7.1 pts
28 July 2016
48%+1.4 pts
14 January 2016
47%+1.1 pts
12 July 2015
46%+7.0 pts
9 February 2015
39%+9.3 pts
Context
Jumeirah Village Triangle has 31 projects under construction, 28% built on average. Paradise One is ahead of that average.
Own a unit in Paradise One?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Paradise One be completed?
- The completion date registered with the Dubai Land Department is April 2027. At the pace of its recent inspections the site would reach 100% around January 2152. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Paradise One is built?
- 70%, measured at the Land Department site inspection on 23 April 2026. The Land Department engineers have inspected the site 17 times since September 2012.
- Is Paradise One delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of April 2027.
- Who is building Paradise One?
- The registered developer is Danat Aldunia Real Estate Development.
- Which bank holds the escrow account for Paradise One?
- Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Silver StallionsNearby in Jumeirah Village Triangle. 12%, Due December 2017, passed.
- Altai TowerNearby in Jumeirah Village Triangle. 98%, Due January 2026, passed.
- Fashionz 1 By DanubeNearby in Jumeirah Village Triangle. 40%.
- Volga TowerNearby in Jumeirah Village Triangle. 51%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.