The Square construction progress

The register lists The Square in Jumeirah Village Circle as complete, with a registered completion date of December 2020. Its last site inspection on record was in July 2021. The developer is Tiger Properties.

100%

Built, at the site inspection of 27 July 2021

Construction complete

Registered completion date
December 2020
Construction started
December 2017
First registered
May 2018
Units
370
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
ذا سكوير
Project number
1969
Site inspections
8

Schedule

The register lists The Square as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2018201920202021
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

27 July 2021

100%+20 pts

  • The Square construction site, inspection photo 1, 27 July 2021
  • The Square construction site, inspection photo 2, 27 July 2021
  • The Square construction site, inspection photo 3, 27 July 2021
  • The Square construction site, inspection photo 4, 27 July 2021

28 February 2021

80%+30 pts

  • The Square construction site, inspection photo 1, 28 February 2021
  • The Square construction site, inspection photo 2, 28 February 2021
  • The Square construction site, inspection photo 3, 28 February 2021
  • The Square construction site, inspection photo 4, 28 February 2021

22 June 2020

50%+20 pts

  • The Square construction site, inspection photo 1, 22 June 2020
  • The Square construction site, inspection photo 2, 22 June 2020
  • The Square construction site, inspection photo 3, 22 June 2020
  • The Square construction site, inspection photo 4, 22 June 2020

27 January 2020

30%+13 pts

  • The Square construction site, inspection photo 1, 27 January 2020
  • The Square construction site, inspection photo 2, 27 January 2020
  • The Square construction site, inspection photo 3, 27 January 2020
  • The Square construction site, inspection photo 4, 27 January 2020

21 August 2019

17%+9.3 pts

  • The Square construction site, inspection photo 1, 21 August 2019
  • The Square construction site, inspection photo 2, 21 August 2019
  • The Square construction site, inspection photo 3, 21 August 2019
  • The Square construction site, inspection photo 4, 21 August 2019

13 March 2019

8.1%+1.4 pts

  • The Square construction site, inspection photo 1, 13 March 2019
  • The Square construction site, inspection photo 2, 13 March 2019
  • The Square construction site, inspection photo 3, 13 March 2019
  • The Square construction site, inspection photo 4, 13 March 2019

3 October 2018

6.6%+3.5 pts

  • The Square construction site, inspection photo 1, 3 October 2018
  • The Square construction site, inspection photo 2, 3 October 2018
  • The Square construction site, inspection photo 3, 3 October 2018
  • The Square construction site, inspection photo 4, 3 October 2018

20 June 2018

3.1%

  • The Square construction site, inspection photo 1, 20 June 2018
  • The Square construction site, inspection photo 2, 20 June 2018
  • The Square construction site, inspection photo 3, 20 June 2018
  • The Square construction site, inspection photo 4, 20 June 2018

All 70 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Tiger Properties has 8 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Square?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the The Square handover date?
Construction of The Square is recorded as complete, with a registered completion date of December 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on The Square?
The Square was 100% built at the site inspection on 27 July 2021. The site has been inspected 8 times since June 2018. The Land Department took 70 site photos at its inspections.
Is The Square delayed?
The register lists construction as complete.
Who is building The Square?
The registered developer is Tiger Properties. It has 8 other projects under construction in Dubai.
Which bank holds the escrow account for The Square?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.