The Portman construction photos

65 photos taken by Dubai Land Department engineers at 9 site inspections, newest first. The percentage is how much of The Portman was built on the day of each visit.

7 August 202679% built

20 April 202657% built

24 November 202551% built

3 June 202537% built

29 January 202515% built

26 June 20245.3% built

30 October 20234.2% built

9 May 20230% built

22 December 20220% built

Back to The Portman construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.