Samana Waves 2 construction progress
Samana Waves 2 in Jumeirah Village Circle was registered to complete in March 2026 and is still under construction. At the last site inspection, in October 2026, it was 52% built. The developer is Samana Si Holding Limited Dubai Branch.
52%
Built, at the site inspection of 2 October 2026
8 months past its registered completion date
- Registered completion date
- March 2026
- Finish at recent pace
- April 2028
- Construction started
- September 2023
- First registered
- April 2023
- Community
- Jumeirah Village Circle
- Units
- 173
- Escrow bank
- Emirates NBD
- Name in Arabic
- سامانا ويفز 2
- Project number
- 2574
- Site inspections
- 7
Schedule
Samana Waves 2 was registered to complete in March 2026, 8 months ago, and is still under construction. Over the last year of inspections it has added about 2.7 points a month. Kept at that rate, the site would reach 100% around April 2028.
Site inspections
2 October 2026
52%+4.8 pts
19 June 2026
47%+12 pts
11 February 2026
35%+10 pts
27 November 2025
25%+11 pts
29 July 2025
14%+9.4 pts
24 January 2025
5.0%+5.0 pts
7 February 2023
0%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Samana Si Holding Limited Dubai Branch has 4 projects under construction in Dubai; 3 have passed their registered completion date.
Own a unit in Samana Waves 2?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Samana Waves 2 handover date?
- The registered completion date was March 2026, and the register still lists Samana Waves 2 as under construction. At the pace of its recent inspections the site would reach 100% around April 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Samana Waves 2?
- Samana Waves 2 was 52% built at the site inspection on 2 October 2026. The site has been inspected 7 times since February 2023. The Land Department took 41 site photos at its inspections.
- Is Samana Waves 2 delayed?
- Yes. Its registered completion date of March 2026 has passed and the project is still listed as under construction.
- Who is building Samana Waves 2?
- The registered developer is Samana Si Holding Limited Dubai Branch. It has 3 other projects under construction in Dubai.
- Which bank holds the escrow account for Samana Waves 2?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Samana WavesAlso by Samana Si Holding Limited Dubai Branch. 91%, Due April 2026, passed.
- Miami By SdAlso by Samana Si Holding Limited Dubai Branch. 71%, Due July 2026, passed.
- California By SdAlso by Samana Si Holding Limited Dubai Branch. 24%.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Luxury Family ResidenceNearby in Jumeirah Village Circle. 76%, Due December 2023, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.