Samana Waves 2 construction progress

Samana Waves 2 in Jumeirah Village Circle was registered to complete in March 2026 and is still under construction. At the last site inspection, in October 2026, it was 52% built. The developer is Samana Si Holding Limited Dubai Branch.

52%

Built, at the site inspection of 2 October 2026

8 months past its registered completion date

Registered completion date
March 2026
Finish at recent pace
April 2028
Construction started
September 2023
First registered
April 2023
Units
173
Escrow bank
Emirates NBD
Name in Arabic
سامانا ويفز 2
Project number
2574
Site inspections
7

Schedule

Samana Waves 2 was registered to complete in March 2026, 8 months ago, and is still under construction. Over the last year of inspections it has added about 2.7 points a month. Kept at that rate, the site would reach 100% around April 2028.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

2 October 2026

52%+4.8 pts

  • Samana Waves 2 construction site, inspection photo 1, 2 October 2026
  • Samana Waves 2 construction site, inspection photo 2, 2 October 2026
  • Samana Waves 2 construction site, inspection photo 3, 2 October 2026
  • Samana Waves 2 construction site, inspection photo 4, 2 October 2026

19 June 2026

47%+12 pts

  • Samana Waves 2 construction site, inspection photo 1, 19 June 2026
  • Samana Waves 2 construction site, inspection photo 2, 19 June 2026
  • Samana Waves 2 construction site, inspection photo 3, 19 June 2026
  • Samana Waves 2 construction site, inspection photo 4, 19 June 2026

11 February 2026

35%+10 pts

  • Samana Waves 2 construction site, inspection photo 1, 11 February 2026
  • Samana Waves 2 construction site, inspection photo 2, 11 February 2026
  • Samana Waves 2 construction site, inspection photo 3, 11 February 2026
  • Samana Waves 2 construction site, inspection photo 4, 11 February 2026

27 November 2025

25%+11 pts

  • Samana Waves 2 construction site, inspection photo 1, 27 November 2025
  • Samana Waves 2 construction site, inspection photo 2, 27 November 2025
  • Samana Waves 2 construction site, inspection photo 3, 27 November 2025
  • Samana Waves 2 construction site, inspection photo 4, 27 November 2025

29 July 2025

14%+9.4 pts

  • Samana Waves 2 construction site, inspection photo 1, 29 July 2025
  • Samana Waves 2 construction site, inspection photo 2, 29 July 2025
  • Samana Waves 2 construction site, inspection photo 3, 29 July 2025
  • Samana Waves 2 construction site, inspection photo 4, 29 July 2025

24 January 2025

5.0%+5.0 pts

  • Samana Waves 2 construction site, inspection photo 1, 24 January 2025
  • Samana Waves 2 construction site, inspection photo 2, 24 January 2025
  • Samana Waves 2 construction site, inspection photo 3, 24 January 2025
  • Samana Waves 2 construction site, inspection photo 4, 24 January 2025

7 February 2023

0%

  • Samana Waves 2 construction site, inspection photo 1, 7 February 2023
  • Samana Waves 2 construction site, inspection photo 2, 7 February 2023

All 41 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Samana Si Holding Limited Dubai Branch has 4 projects under construction in Dubai; 3 have passed their registered completion date.

Own a unit in Samana Waves 2?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Samana Waves 2 handover date?
The registered completion date was March 2026, and the register still lists Samana Waves 2 as under construction. At the pace of its recent inspections the site would reach 100% around April 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Samana Waves 2?
Samana Waves 2 was 52% built at the site inspection on 2 October 2026. The site has been inspected 7 times since February 2023. The Land Department took 41 site photos at its inspections.
Is Samana Waves 2 delayed?
Yes. Its registered completion date of March 2026 has passed and the project is still listed as under construction.
Who is building Samana Waves 2?
The registered developer is Samana Si Holding Limited Dubai Branch. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Samana Waves 2?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.