Miami By Sd construction progress
Miami By Sd in Al Barsha South Fifth was registered to complete in July 2026 and is still under construction. At the last site inspection, in October 2026, it was 71% built. The developer is Samana Si Holding Limited Dubai Branch.
71%
Built, at the site inspection of 2 October 2026
4 months past its registered completion date
- Registered completion date
- July 2026
- Finish at recent pace
- June 2027
- Construction started
- March 2023
- First registered
- November 2022
- Community
- Al Barsha South Fifth
- Units
- 115
- Escrow bank
- Emirates NBD
- Name in Arabic
- ميامي باي اس دي
- Project number
- 2454
- Site inspections
- 8
Schedule
Miami By Sd was registered to complete in July 2026, 4 months ago, and is still under construction. Over the last year of inspections it has added about 3.2 points a month. Kept at that rate, the site would reach 100% around June 2027.
Site inspections
2 October 2026
71%+5.0 pts
21 May 2026
66%+12 pts
17 February 2026
54%+16 pts
26 November 2025
38%+10 pts
17 July 2025
28%+11 pts
25 March 2025
17%+7.0 pts
23 October 2024
10%+10 pts
13 October 2022
0%
Context
Al Barsha South Fifth has 2 projects under construction, 42% built on average.
Samana Si Holding Limited Dubai Branch has 4 projects under construction in Dubai; 3 have passed their registered completion date.
Own a unit in Miami By Sd?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Miami By Sd handover date?
- The registered completion date was July 2026, and the register still lists Miami By Sd as under construction. At the pace of its recent inspections the site would reach 100% around June 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Miami By Sd?
- Miami By Sd was 71% built at the site inspection on 2 October 2026. The site has been inspected 8 times since October 2022. The Land Department took 59 site photos at its inspections.
- Is Miami By Sd delayed?
- Yes. Its registered completion date of July 2026 has passed and the project is still listed as under construction.
- Who is building Miami By Sd?
- The registered developer is Samana Si Holding Limited Dubai Branch. It has 3 other projects under construction in Dubai.
- Which bank holds the escrow account for Miami By Sd?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Samana WavesAlso by Samana Si Holding Limited Dubai Branch. 91%, Due April 2026, passed.
- Samana Waves 2Also by Samana Si Holding Limited Dubai Branch. 52%, Due March 2026, passed.
- California By SdAlso by Samana Si Holding Limited Dubai Branch. 24%.
- Vivid TowerNearby in Al Barsha South Fifth. 12%, Due November 2026.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)