Miami By Sd construction progress
Miami By Sd in Al Barsha South Fifth is 71% built at the Land Department inspection of October 2026. Developer Samana Si Holding Limited Dubai Branch. Completion registered for July 2026.
71%
Built, at the Land Department site inspection of 2 October 2026
2 months past its registered completion date
- Completion date (Land Department)
- July 2026
- Finish at recent pace
- June 2027
- Construction started
- March 2023
- Registered with the Land Department
- November 2022
- Community
- Al Barsha South Fifth
- Units
- 115
- Escrow bank
- Emirates NBD
- Name in Arabic
- ميامي باي اس دي
- Land Department project number
- 2454
- Land Department site inspections
- 8
Schedule
Miami By Sd was registered to complete in July 2026, 2 months ago, and is still under construction. Over the last year of inspections it has added about 3.2 points a month. Kept at that rate, the site would reach 100% around June 2027.
Site inspections
2 October 2026
71%+5.0 pts
21 May 2026
66%+12 pts
17 February 2026
54%+16 pts
26 November 2025
38%+10 pts
17 July 2025
28%+11 pts
25 March 2025
17%+7.0 pts
23 October 2024
10%+10 pts
13 October 2022
0%
Context
Al Barsha South Fifth has 2 projects under construction, 42% built on average.
Samana Si Holding Limited Dubai Branch has 4 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in Miami By Sd?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Miami By Sd be completed?
- The completion date registered with the Dubai Land Department is July 2026. At the pace of its recent inspections the site would reach 100% around June 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Miami By Sd is built?
- 71%, measured at the Land Department site inspection on 2 October 2026. The Land Department engineers have inspected the site 8 times since October 2022.
- Is Miami By Sd delayed?
- Yes. Its registered completion date of July 2026 has passed and the Land Department still lists it as under construction.
- Who is building Miami By Sd?
- The registered developer is Samana Si Holding Limited Dubai Branch. It has 3 other projects under construction in Dubai.
- Which bank holds the escrow account for Miami By Sd?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Samana WavesAlso by Samana Si Holding Limited Dubai Branch. 90%, Due April 2026, passed.
- Samana Waves 2Also by Samana Si Holding Limited Dubai Branch. 52%.
- California By SdAlso by Samana Si Holding Limited Dubai Branch. 24%.
- Vivid TowerNearby in Al Barsha South Fifth. 12%, Due November 2026.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)