Samana Waves construction photos
75 photos from 10 site inspections, newest first. The percentage is how much of Samana Waves was built on the day of each visit.
16 October 202691% built
19 June 202690% built
5 February 202677% built
20 November 202573% built
14 July 202554% built
31 January 202540% built
13 November 202427% built
14 May 202410% built
15 March 20233.6% built
5 December 20220% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.