Luxury Family Residence construction progress

Luxury Family Residence in Jumeirah Village Circle was registered to complete in December 2023 and is still under construction. At the last site inspection, in April 2026, it was 76% built. The developer is Kappa Acca Real Estate Development.

76%

Built, at the site inspection of 25 April 2026

35 months past its registered completion date

Registered completion date
December 2023
Finish at recent pace
October 2029
Construction started
August 2019
First registered
May 2022
Developer
Kappa Acca Real Estate Development
Units
428
Escrow bank
Emirates NBD
Name in Arabic
لوكجري فاميلى ريزيدنس
Project number
2353
Site inspections
7

Schedule

Luxury Family Residence was registered to complete in December 2023, 35 months ago, and is still under construction. Over the last year of inspections it has added about 0.6 points a month. Kept at that rate, the site would reach 100% around October 2029.

0%25%50%75%100%2020202220242026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

25 April 2026

76%+3.5 pts

  • Luxury Family Residence construction site, inspection photo 1, 25 April 2026
  • Luxury Family Residence construction site, inspection photo 2, 25 April 2026
  • Luxury Family Residence construction site, inspection photo 3, 25 April 2026
  • Luxury Family Residence construction site, inspection photo 4, 25 April 2026

21 October 2025

72%+2.4 pts

  • Luxury Family Residence construction site, inspection photo 1, 21 October 2025
  • Luxury Family Residence construction site, inspection photo 2, 21 October 2025
  • Luxury Family Residence construction site, inspection photo 3, 21 October 2025
  • Luxury Family Residence construction site, inspection photo 4, 21 October 2025

18 February 2025

70%+12 pts

  • Luxury Family Residence construction site, inspection photo 1, 18 February 2025
  • Luxury Family Residence construction site, inspection photo 2, 18 February 2025
  • Luxury Family Residence construction site, inspection photo 3, 18 February 2025
  • Luxury Family Residence construction site, inspection photo 4, 18 February 2025

15 March 2024

58%+2.9 pts

  • Luxury Family Residence construction site, inspection photo 1, 15 March 2024
  • Luxury Family Residence construction site, inspection photo 2, 15 March 2024
  • Luxury Family Residence construction site, inspection photo 3, 15 March 2024
  • Luxury Family Residence construction site, inspection photo 4, 15 March 2024

3 July 2023

56%+8.8 pts

  • Luxury Family Residence construction site, inspection photo 1, 3 July 2023
  • Luxury Family Residence construction site, inspection photo 2, 3 July 2023
  • Luxury Family Residence construction site, inspection photo 3, 3 July 2023
  • Luxury Family Residence construction site, inspection photo 4, 3 July 2023

13 October 2022

47%+1.9 pts

  • Luxury Family Residence construction site, inspection photo 1, 13 October 2022
  • Luxury Family Residence construction site, inspection photo 2, 13 October 2022
  • Luxury Family Residence construction site, inspection photo 3, 13 October 2022
  • Luxury Family Residence construction site, inspection photo 4, 13 October 2022

10 February 2022

45%

  • Luxury Family Residence construction site, inspection photo 1, 10 February 2022
  • Luxury Family Residence construction site, inspection photo 2, 10 February 2022
  • Luxury Family Residence construction site, inspection photo 3, 10 February 2022
  • Luxury Family Residence construction site, inspection photo 4, 10 February 2022

All 65 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Kappa Acca Real Estate Development has 2 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Luxury Family Residence?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Luxury Family Residence handover date?
The registered completion date was December 2023, and the register still lists Luxury Family Residence as under construction. At the pace of its recent inspections the site would reach 100% around October 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Luxury Family Residence?
Luxury Family Residence was 76% built at the site inspection on 25 April 2026. The site has been inspected 7 times since February 2022. The Land Department took 65 site photos at its inspections.
Is Luxury Family Residence delayed?
Yes. Its registered completion date of December 2023 has passed and the project is still listed as under construction.
Who is building Luxury Family Residence?
The registered developer is Kappa Acca Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Luxury Family Residence?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.