Luxury Family Residence construction progress
Luxury Family Residence in Jumeirah Village Circle was registered to complete in December 2023 and is still under construction. At the last site inspection, in April 2026, it was 76% built. The developer is Kappa Acca Real Estate Development.
76%
Built, at the site inspection of 25 April 2026
35 months past its registered completion date
- Registered completion date
- December 2023
- Finish at recent pace
- October 2029
- Construction started
- August 2019
- First registered
- May 2022
- Developer
- Kappa Acca Real Estate Development
- Community
- Jumeirah Village Circle
- Units
- 428
- Escrow bank
- Emirates NBD
- Name in Arabic
- لوكجري فاميلى ريزيدنس
- Project number
- 2353
- Site inspections
- 7
Schedule
Luxury Family Residence was registered to complete in December 2023, 35 months ago, and is still under construction. Over the last year of inspections it has added about 0.6 points a month. Kept at that rate, the site would reach 100% around October 2029.
Site inspections
25 April 2026
76%+3.5 pts
21 October 2025
72%+2.4 pts
18 February 2025
70%+12 pts
15 March 2024
58%+2.9 pts
3 July 2023
56%+8.8 pts
13 October 2022
47%+1.9 pts
10 February 2022
45%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Kappa Acca Real Estate Development has 2 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in Luxury Family Residence?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Luxury Family Residence handover date?
- The registered completion date was December 2023, and the register still lists Luxury Family Residence as under construction. At the pace of its recent inspections the site would reach 100% around October 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Luxury Family Residence?
- Luxury Family Residence was 76% built at the site inspection on 25 April 2026. The site has been inspected 7 times since February 2022. The Land Department took 65 site photos at its inspections.
- Is Luxury Family Residence delayed?
- Yes. Its registered completion date of December 2023 has passed and the project is still listed as under construction.
- Who is building Luxury Family Residence?
- The registered developer is Kappa Acca Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Luxury Family Residence?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Luxury Family Residence IIIAlso by Kappa Acca Real Estate Development. 51%, Due June 2025, passed.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
















.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)