Luxury Family Residence construction progress
Luxury Family Residence in Jumeirah Village Circle is 76% built at the Land Department inspection of April 2026. Developer Kappa Acca Real Estate Development. Completion registered for December 2023.
76%
Built, at the Land Department site inspection of 25 April 2026
33 months past its registered completion date
- Completion date (Land Department)
- December 2023
- Finish at recent pace
- October 2029
- Construction started
- August 2019
- Registered with the Land Department
- May 2022
- Developer
- Kappa Acca Real Estate Development
- Community
- Jumeirah Village Circle
- Units
- 428
- Escrow bank
- Emirates NBD
- Name in Arabic
- لوكجري فاميلى ريزيدنس
- Land Department project number
- 2353
- Land Department site inspections
- 7
Schedule
Luxury Family Residence was registered to complete in December 2023, 33 months ago, and is still under construction. Over the last year of inspections it has added about 0.6 points a month. Kept at that rate, the site would reach 100% around October 2029.
Site inspections
25 April 2026
76%+3.5 pts
21 October 2025
72%+2.4 pts
18 February 2025
70%+12 pts
15 March 2024
58%+2.9 pts
3 July 2023
56%+8.8 pts
13 October 2022
47%+1.9 pts
10 February 2022
45%
Context
Jumeirah Village Circle has 119 projects under construction, 40% built on average. Luxury Family Residence is ahead of that average.
Kappa Acca Real Estate Development has 2 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Luxury Family Residence?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Luxury Family Residence be completed?
- The completion date registered with the Dubai Land Department is December 2023. At the pace of its recent inspections the site would reach 100% around October 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Luxury Family Residence is built?
- 76%, measured at the Land Department site inspection on 25 April 2026. The Land Department engineers have inspected the site 7 times since February 2022.
- Is Luxury Family Residence delayed?
- Yes. Its registered completion date of December 2023 has passed and the Land Department still lists it as under construction.
- Who is building Luxury Family Residence?
- The registered developer is Kappa Acca Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Luxury Family Residence?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Luxury Family Residence IiiAlso by Kappa Acca Real Estate Development. 51%, Due June 2025, passed.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 42%, Due January 2013, passed.
- Serenity Lakes 2Nearby in Jumeirah Village Circle. 50%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 90%, Due April 2026, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.